Browsing by Subject "Design and construction"
Now showing 1 - 3 of 3
- Results Per Page
- Sort Options
Item Design and construction of small-scale bridge bents on drilled shaft foundations(2005-12-24) Black, Joshua Stephen; Wood, Sharon L.The response of structures with deep foundations subjected to dynamic loading is of key interest in areas of high seismicity and is not well understood. This lack of understanding has resulted in design practices which may be overly conservative or inadequate in describing complex structural systems. As part of an experimental program sponsored by the National Science Foundation, two quarter-scale bridge bents on drilled shaft foundations were constructed to investigate soil-foundation-structure interaction under dynamic loading. The bents represent supporting elements in typical highway bridge constructionItem Design and fabrication of an instrument to test the mechanical behavior of aluminum alloy sheets during high-temperature gas-pressure blow-forming(2008-05) Vanegas Moller, Ricardo; Taleff, Eric M.Hydraulic bulge forming has been used as a method to determine the properties of sheet metal alloys in biaxial stretching at room temperature. Gas-pressure bulge forming alleviates the issues of using hydraulic fluids when the tests are conducted at high temperatures (above 200°C). Testing a sheet metal alloy by gas-pressure blow-forming (GPBF) under controlled temperature and pressure conditions requires an accurate and reliable mechanism that delivers repeatable results. It was the purpose of this work to design and implement such an instrument. This instrument should deliver real-time data for material displacement during forming, which can then be used to better understand material plastic response and formability. Four different subsystems within this mechanism must interact, but also have enough independence for analysis and for assembly purposes. The combined sub-systems produced a GPBF apparatus capable of forming a sheet aluminum alloy AA5182 with a thickness of 1.5 mm into a dome with a height nearly equal to its radius under a constant gas pressure as low as 40 psi at 450°C. This GPBF apparatus produced, for the first time, in-situ data for dome peak displacement during gas-pressure bulge forming of AA5182 sheet at 450°C.Item Stabilizing techniques for curved steel I-girders during construction(2010-05) Petruzzi, Brian James; Helwig, Todd Aaron, 1965-; Engelhardt, Michael D.There are many issues and challenges to deal with when designing a curved I-girder bridge. These challenges primarily deal with the many performance stages that curved I-girder bridges have such as the erection, construction, and in-service stages. When design engineers assess the stability of a bridge system, they typically evaluate the system in its final configuration with all cross frames attached and the hardened concrete deck placed. The evaluation of girder stability during erection and early stages of construction stages is difficult because of the limited presence of bracing in the system. Due to a lack of readily available analytical tools, many contractors do not conduct detailed analytical evaluations of the bridge behavior during early stages of the construction when stability is often critical. Instead, many contractors use rules of thumb and experience to ensure stability during erection. Erection and construction practices typically vary among contractors and consistent erection methods are a rarity. Although some rules of thumb may be quite conservative, others are much less so. Therefore, coming up with design guidelines based on parametric studies rather than rules of thumb are desirable to help allow the contractor and the designer to work together to prevent issues that may occur due to the lack of communication between the two professions. Lastly, many challenges arise due to the complex geometry of curved I-girders. To prevent excessive rotation in erected girders, three points of vertical support are often provided. Two of these points usually consist of permanent supports in the form of bridge piers or abutments. The third point of support may consist of a temporary support in the form of a shore tower or holding crane. Cases where a holding crane may be satisfactory over a shore tower are also not well understood. To improve the understanding of lifting practices and temporary support requirements, parametric studies were conducted using the finite element program ANSYS. Field data consisting of displacement, stress, and girder rotations gathered from two tests were used to validate both the linear and geometric non-linear three-dimensional FEA models. Upon validation, the finite element model was used to conduct linear and geometric non-linear analyses to determine critical factors in curved I-girder bridges during construction. Specifically, serviceability limit states were studied for the lifting of curved girders. For partially constructed states, parametric studies were conducted to determine optimal locations to place temporary supports as well as to investigate stability differences between using a shore tower and a holding crane. Recommendations are presented to provide guidance for the lifting of curved I-girders as well as to maximize stability of partially constructed bridges.