Development and Application of Unsteady Flood Models Using Geographic Information Systems by Daniel Baldwin Snead Departmental Report Presented to the Faculty of the Civil Engineering Department of the University of Texas at Austin in Partial Fulfillment of the Requirements for the Degree of Master of Science in Engineering The University of Texas at Austin December 2000 ii Acknowledgements I am very grateful to all who have helped me throughout my research. I am indebted to Dr. David Maidment, my graduate advisor, who has always been very supportive of my work with the Corps of Engineers. A special thanks also goes to Jesper Kjelds from the Danish Hydraulic Institute for providing the DHI developed software. His expertise and support throughout my research made this project possible. Another special thanks goes to the Louisville District of the U.S. Army Corps of Engineers, especially to Glen Beckham and Lynn Funke for providing the study area data and financial support throughout the duration of this project. I am also grateful to the professors, students, and staff at the Center for Research in Water Resources, especially Dr. Francisco Olivera, Pete Andrysiak, Dave Anderson, Kwabena Asante, Esteban Azagra, and Ty Lehman. Without their assistance during some trying times, the results of my work would have been less than desirable. To the rest of the CRWR team, especially the members of the ?Blue Collar Room?, thanks for the camaraderie and best wishes to you all. Finally, I would sincerely like to thank my wife Melinda and my daughter Charlotte. They know all too well how difficult life can be as military dependents. Their continued love and support has made this project?s success possible. December, 2000 iii Abstract Development and Application of Unsteady Flood Models using Geographic Information Systems by Daniel Snead, M.S.E. The University of Texas at Austin, 2000 Supervisors: David Maidment and Francisco Olivera This document presents the application of two unsteady flow hydraulic models used for flood routing and visualization: the MIKE 11 model from the Danish Hydraulic Institute (DHI) and the HEC River Analysis System model, better known as HEC RAS, from U.S. Army Corps of Engineer?s Hydrologic Engineering Center. In this study, both hydraulic models use rainfall-runoff data in time series format from an existing HEC Hydrologic Modeling System (HEC HMS) model. The approach for both models leads to the spatial integration of unsteady flow simulations into a geographic information system (GIS) for flood visualization and animation. The study area applied to both models is the Mill Creek Watershed located in Cincinnati, Ohio. The Mill Creek watershed area is approximately 165 square miles consisting of 28 main stream miles. The study area used for the hydraulic models, referred to as the Primary Damage Center, is approximately 5.3 square miles in area consisting of 3.97 stream miles. The results found from this project support an on-going flood analysis study conducted by the Louisville District, U.S. Army Corps of Engineers. The primary source for the data used in the project was the Louisville District. The study?s focus was on 1) the development of an accurate and workable digital terrain model of the study area; 2) the development of a MIKE 11 model based on surveyed, stream cross-section data; 3) the development of a HEC RAS model based on stream cross-section data extracted from the terrain model; and 4) the creation of flood animations from the two hydraulic model simulations. The results iv of this study provide information on the two unsteady flow hydraulic model methods as well as what advantages they have over steady flow hydraulic models. The MIKE 11 model?s stream geometry was based on surveyed data, which did not extent over the full width of the inundated flood plain. The HEC RAS model?s stream geometry was extracted from the digital terrain model, which ensured that the flood plain?s extent was fully accounted for. The results were faster flood wave attenuation, higher maximum water surface elevation, and shorter flood duration for the MIKE 11 model simulation as compared to the HEC RAS simulation. The results of the HEC RAS unsteady flow model were also compared to the HEC RAS steady flow model based on steady flow peak runoff discharge values. The unsteady flow hydraulic model?s maximum water surface elevation was less than the steady flow hydraulic model?s water surface elevation because the steady flow hydraulic model assumes peak runoff occurs simultaneously in the individual drainage basins within the watershed, while the unsteady flow model more closely mimics the movement of the flood wave through the drainage area. v Table of Contents List of Tables.................................................................................................................x List of Figures ..............................................................................................................xi Chapter 1: Introduction ................................................................................................. 1 1.1 Objectives................................................................................................................ 2 1.2 Study Area............................................................................................................... 3 1.3 Structure of Report.................................................................................................. 6 Chapter 2: Literature Review ........................................................................................ 8 2.1 Flood Modeling....................................................................................................... 8 2.2 Dynamic Models ................................................................................................... 11 Chapter 3: Data Discussion......................................................................................... 16 3.1 Data Requirements ................................................................................................ 16 3.1.1 Hydraulic Data ............................................................................................... 16 3.1.2 Hydrologic Data ............................................................................................. 20 3.1.3 Spatial Data .................................................................................................... 22 3.2 Data Sources and Processing................................................................................. 23 3.2.1 Coordinate System ......................................................................................... 24 3.2.2 Terrain Data.................................................................................................... 24 3.2.3 Geometric Data .............................................................................................. 26 vi 3.2.4 Flow Data ....................................................................................................... 31 Chapter 4: Modeling Methods..................................................................................... 33 4.1 The MIKE 11 Model............................................................................................. 33 4.1.1 The MIKE 11 Hydrodynamic Model............................................................. 33 4.1.2 MIKE View.................................................................................................... 41 4.1.3 The MIKE 11 GIS Extension......................................................................... 41 4.2 The HEC RAS Model ........................................................................................... 42 4.2.1 The HEC RAS Unsteady Flow Model ........................................................... 42 4.2.2 The HEC GeoRAS Extension ........................................................................ 48 4.3 The HEC HMS Model........................................................................................... 49 4.3.1 Loss Determinations....................................................................................... 50 4.3.2 Runoff Transformations ................................................................................. 50 4.3.3 Routing........................................................................................................... 50 4.3.4 Parameter Optimization.................................................................................. 52 Chapter 5: Terrain Model Development ..................................................................... 53 5.1 Methodology of Terrain Model Development ...................................................... 54 5.1.1 Initial Terrain Model Development................................................................ 54 5.1.2 Limitations of Digital Terrain Data used for Hydraulic Modeling ................ 56 5.1.3 Integration of Streambed Geometry and Terrain Data................................... 59 5.2 Application of the Terrain Model to the MIKE 11 GIS Interface......................... 68 Chapter 6: Application of the MIKE 11 Model .......................................................... 71 vii 6.1 Geometric Processing............................................................................................ 71 6.1.1 Stream Network Development....................................................................... 71 6.1.2 Cross-section Data Development................................................................... 72 6.2 Bed Resistance Factors.......................................................................................... 74 6.3 Boundary Conditions............................................................................................. 75 6.3.1 Simulating Base Flow Conditions.................................................................. 76 6.3.2 Incorporating Hydrologic Data as Boundary Conditions............................... 76 6.4 Post Processing in MIKE 11 GIS.......................................................................... 80 6.4.1 Geo-referencing the Stream Network to the Terrain Model .......................... 80 6.4.2 Importing Q and h Data into MIKE 11 GIS................................................... 81 6.4.3 Generating Flood Maps and Animations from the Unsteady Flow Model.... 83 Chapter 7: Application of the HEC RAS Model......................................................... 86 7.1 Extracting Stream Geometry from the Terrain Model.......................................... 86 7.1.1 Developing the Stream Centerline and Main Channel Banks........................ 87 7.1.2 Developing Cross-section Cut Lines and Flow Paths .................................... 88 7.1.3 Generating the RAS GIS Import File from Terrain Data............................... 90 7.2 Geometric Processing............................................................................................ 91 7.2.1 Import GIS Stream Geometry Data................................................................ 92 7.2.2 Bed Resistance Factors................................................................................... 93 7.3 Development of Unsteady Flow Initial Conditions and Boundary Conditions .... 94 7.3.1 Establishing Initial Conditions as Base Flow................................................. 94 7.3.2 Boundary Conditions Derived from the Hydrologic Data ............................. 94 viii 7.4 Unsteady Flow Simulations in HEC RAS............................................................. 97 7.5 Post Processing in HEC GeoRAS ......................................................................... 99 7.5.1 Read RAS GIS Export File ............................................................................ 99 7.5.2 Water Surface TIN Generation .................................................................... 100 7.5.3 Delineating Flood Plains from Unsteady Flow Model Results.................... 101 Chapter 8: Results and Conclusions.......................................................................... 105 8.1 Model Results...................................................................................................... 105 8.1.1 MIKE 11 Model Results .............................................................................. 105 8.1.2 HEC RAS Model Results............................................................................. 108 8.1.3 Comparison of the Unsteady Flow Model Results....................................... 112 8.1.4 Comparison to Steady Flow Modeling ........................................................ 114 8.2 Conclusions ......................................................................................................... 117 8.2.1 Unsteady Flow Model Advantages and Limitations.................................... 120 8.2.2 Future Work ................................................................................................. 122 Appendix A: MIKE 11 Chainage - HEC-2 River Station Conversions.................... 123 Appendix B: Visual Fortran Program used for Cross-section Data Conversion....... 126 Appendix C: MIKE 11 Cross-section File ................................................................ 131 Appendix D: HEC RAS Cross-section Data............................................................. 151 Appendix E: HEC HMS Input for MIKE 11............................................................. 168 Appendix F: Data Dictionary.................................................................................... 186 ix Bibliography.............................................................................................................. 192 Vita............................................................................................................................ 195 x List of Tables Table 3-1. Base flows for the flow model stream network. ........................................ 31 Table 5-1. Stream definition points for the study area................................................ 65 Table 7-1. River ID data for each reach in the PDC stream network. ........................ 87 Table 7-2. Hydrograph sources for the HEC RAS model........................................... 96 Table 8-1. Time of peaks for the PDC study area boundary conditions. .................. 116 Table A-1. HEC-2 River Station conversion to MIKE 11 Chainages ...................... 123 Table E-1. Mill Creek PDC model?s upstream and downstream boundary data. ..... 168 Table E-2. Mill Creek PDC model?s lateral boundary data extracted from the HEC HMS model. ...................................................................................................... 182 xi List of Figures Figure 1-1. Location of the Mill Creek Watershed in Cincinnati, OH.......................... 4 Figure 1-2. Mill Creek location with respect to the Ohio River. .................................. 4 Figure 1-3. Location of the Primary Damage Center in the Mill Creek Watershed. .... 6 Figure 2-1. Channel geometry incorporated into a digital terrain model (Tate 1999).. 9 Figure 2-2. Flood visualization using AVRas and a TIN (Azagra-Camino 1999). .... 10 Figure 2-3. Finite element of a stream channel with force terms............................... 12 Figure 2-4. FLOOD WATCH applied to a region in India (Kjelds 1997).................. 15 Figure 3-1. 3-D depiction of a stream with cross-sections in HEC RAS.................... 17 Figure 3-2. Comparison of Chainage and River Station network referencing............ 18 Figure 3-3. Differentiation of streambed and flood plain resistance in MIKE 11. ..... 19 Figure 3-4. HEC RAS cross-section with Manning?s n values................................... 19 Figure 3-5. Schematic view of the HEC HMS model developed by Andrysiak......... 22 Figure 3-6. A triangular mesh and TIN theme in Arcview GIS.................................. 23 Figure 3-7. Portion of the 2-ft contour theme depicting the PDC............................... 25 Figure 3-8. Stream network digitized in Arcview GIS using a point theme............... 28 Figure 3-9. Example of cross-section data in a HEC-RAS .G01 text file................... 29 Figure 3-10. Cross-section text file readable by the MIKE 11 software..................... 30 Figure 3-11. Runoff hydrograph for the Mill Creek Watershed?s Basin 109. ............ 32 Figure 4-1. Input tab in a MIKE 11 Simulation File................................................... 34 Figure 4-2. Simulation file with a ?Hotstart? Initial Conditions Type........................ 35 xii Figure 4-3. River network file defined by XY coordinate data points........................ 36 Figure 4-4. Tabular view of a river network depicting XY coordinate data points. ... 37 Figure 4-5. Raw data view of a cross-section in MIKE 11......................................... 38 Figure 4-6. MIKE 11 boundary file. ........................................................................... 39 Figure 4-7. Bed resistance from chainage to chainage in the hydrodynamic file. ...... 41 Figure 4-8. Main menu of HEC RAS version 3.0, with the unsteady flow option. .... 43 Figure 4-9. HEC RAS version 3.0 geometric data file editor. .................................... 44 Figure 4-10. HEC RAS version 3.0 unsteady flow data file editor............................. 46 Figure 4-11. HEC RAS version 3.0 unsteady flow analysis file editor. ..................... 47 Figure 4-12. Bounding polygon derived from cross-sections using GeoRAS............ 49 Figure 4-13. Discontinuities between watersheds in a hydrologic model and the boundaries of the hydraulic model...................................................................... 51 Figure 5-1. Example of a TIN-based terrain model. ................................................... 55 Figure 5-2. Points, contours, and bounding polygon used for the PDC terrain model. ............................................................................................................................. 56 Figure 5-3. A surveyed cross-section of Mill Creek compared to terrain model data.57 Figure 5-4. Comparison of the Mill Creek streambed?s longitudinal profile developed from the terrain model and the HEC-2 surveyed data......................................... 58 Figure 5-5. Terraced streambed of Mill Creek created from the TIN data. ................ 59 Figure 5-6. Tate?s Method of incorporating flood plains into a terrain model. .......... 60 Figure 5-7. Comparison of the stream and a 3-D stream centerline and bank lines created by the Arcview GIS Floodmap utility. ................................................... 61 xiii Figure 5-8. A revised depiction of cross-sections and bank lines as compared to the stream centerline. ................................................................................................ 62 Figure 5-9. Cross-sections interpolated between existing cross-sections in HEC RAS. ............................................................................................................................. 63 Figure 5-10. Sharon Rd. used as an intermediate point for geo-referencing. ............. 64 Figure 5-11. PolylineZ themes of the stream channel and cross-sections................... 66 Figure 5-12. Section of Mill Creek with mass points data and stream geometry. ...... 67 Figure 5-13. TIN-based terrain model modified with surveyed stream geometry...... 68 Figure 5-14. The PDC Grid-based terrain model shown with hill shading effect. ..... 69 Figure 5-15. Rough edge created when delineating the water surface from the terrain using the MIKE 11 GIS grid-based delineation method..................................... 70 Figure 6-1. MIKE 11 Stream network created with the Define Branch tool, from point to point................................................................................................................. 72 Figure 6-2. Cross-section #19166 in MIKE 11........................................................... 73 Figure 6-3. The MIKE 11 Cross-section interpolation tool. ....................................... 74 Figure 6-4. The overall resistance factors in the MIKE 11 model............................. 75 Figure 6-5. A MIKE 11 time-series file extracted from the HEC HMS hydrologic model................................................................................................................... 77 Figure 6-6. The Mill Creek HEC HMS schematic imported as a background image into the MIKE 11 river network file.................................................................... 78 Figure 6-7. A MIKE 11 boundary file......................................................................... 79 Figure 6-8. A profile of Mill Creek in the PDC study area......................................... 80 xiv Figure 6-9. The MIKE 11 flow model inputs for MIKE 11 GIS: the river network file and the simulation data........................................................................................ 81 Figure 6-10. Q-points and h-points imported into MIKE 11 GIS............................... 82 Figure 6-11. MIKE 11 flow model results were imported into the Hpoints.txt attribute table. .................................................................................................................... 83 Figure 6-12. Flood map of the Mill Creek PDC developed from MIKE 11 model data. ............................................................................................................................. 84 Figure 6-13. Snapshot from a MIKE 11 ?Flyby? animation....................................... 85 Figure 6-14. 3-D animation of the Mill Creek PDC with buildings. .......................... 85 Figure 7-1. Stream centerline and main channel banks defined for East Fork on the TIN-based terrain model. .................................................................................... 88 Figure 7-2. The HEC-2 cross-sections and the GeoRAS cross-section cut lines shown along the stream network in the terrain model.................................................... 89 Figure 7-3. Flow paths, channel banks, and cross-section cut lines defined with respect to the PDC terrain model. ....................................................................... 90 Figure 7-4. Theme setup menu for GeoRAS pre-processing. ..................................... 91 Figure 7-5. The right bank location shown was shifted up and to the right to depicting the most natural transition from flood plain to streambed. ................................. 92 Figure 7-6. The HEC RAS geometry data schematic of the GIS imported data......... 93 Figure 7-7. Initial flow conditions used for the HEC RAS model, in m 3 /s................. 94 Figure 7-8. The DSS Path window in HEC RAS........................................................ 97 xv Figure 7-9. The HEC RAS Unsteady Flow Analysis plan shown for the Mill Creek PDC model. ......................................................................................................... 98 Figure 7-10. The X-Y-Z Perspective Plot in HEC RAS. ............................................. 99 Figure 7-11. For HEC GeoRAS post-processing, the inputs for Arcview GIS were defined............................................................................................................... 100 Figure 7-12. The water surface TIN created from HEC RAS input overlapping the terrain model of the PDC study area. ................................................................ 101 Figure 7-13. Maximum water surface for the April 1998 flood delineated from the terrain model. .................................................................................................... 102 Figure 7-14. Three-dimensional representation of the TIN-based terrain model and water surface using 3D Analyst......................................................................... 103 Figure 7-15. The view shows the distinction between water and terrain using TIN- based surfaces in HEC GeoRAS. ...................................................................... 104 Figure 8-1. The horizontal, red dotted line above the cross-section at Chainage 19.998 is the maximum water surface at that location for the MIKE 11 model. .......... 106 Figure 8-2. An example of a reversed cross-section shown in an XYZ plot in HEC RAS. .................................................................................................................. 110 Figure 8-3. The Arcview GIS view shows the polygon themes in the legend imported from the HEC RAS flow model for different time steps................................... 112 Figure 8-4. A visual comparison is shown of the maximum stage heights for the MIKE 11 model and the HEC RAS model. ...................................................... 113 xvi Figure 8-5. The MIKE 11 and HEC RAS cross-sections shown are approximately 12 meters from each other along the stream network. The flood plain conveyance is accounted for in the HEC RAS model, significantly slowing down flow as compared to the MIKE 11 model results. ......................................................... 114 Figure 8-6. Schematic of the watersheds contributing runoff to the Primary Damage Center. ............................................................................................................... 115 Figure 8-7. Comparison of maximum water surfaces for the HEC RAS unsteady flow model and the steady model for the 25-yr storm event..................................... 117 Figure 8-8. Schematics of the initial hydraulic models developed in MIKE 11 and HEC RAS. ......................................................................................................... 118 1 Chapter 1: Introduction Flood analysis assists decision makers with the prevention and prediction of flood events. Computer modeling techniques have assisted engineers with determining more accurately where and when flooding may occur. Computer models for the determination of flood effects require four parts: 1) the hydrologic model which develops rainfall-runoff from a design storm or historic storm event, and 2) the hydraulic model which routes the runoff through stream channels to determine water surface profiles at specific locations along the stream network, 3) a tool for floodplain mapping and visualization, and 4) the extraction of geospatial data for use in the model(s). Most of the previous hydraulic modeling techniques use one-dimensional (1-D) steady-state flows measured at a specified point in time. Since flows in streambeds are naturally random and unsteady, steady-state methods do not always accurately depict water surface profiles. The steady-state modeling technique is also limited by how the modeler spatially synchronizes the rainfall-runoff routing for multiple drainage basins at a specified point in time. Such methods are subject to human error and can be very time consuming. Developments in fully dynamic, unsteady models have provided engineers with highly accurate hydraulic modeling methods that result in graphical two- and three- dimensional visualizations for the purpose of analysis. The key to graphical visualizations in dynamic modeling is the inclusion of time-series data within a spatial interface, like a Geographic Information System (GIS). The Danish Hydraulic Institute (DHI) is one of the world-leading software developers for incorporating water resources related time-series data into modeling. DHI?s MIKE 11 hydrodynamic model uses 1-D implicit, dynamic wave routing based on the St. Venant equations for unsteady flow. Additionally, DHI?s MIKE 11 GIS extension to ESRI?s Arcview GIS interface allows the user to import MIKE 11 model simulations 2 in a time-series format into the Arcview GIS spatial environment. The Army Corps of Engineers? Hydrologic Engineering Center has recently revamped their widely used 1-D, steady-state HEC RAS modeling software. The HEC RAS 3.0 version can also run 1-D unsteady flow simulations. The unsteady flow is processed in HEC RAS using the UNET algorithm developed by Dr. Robert L. Barkau (UNET, 1997). Like DHI?s MIKE 11 model, UNET is a 1-D unsteady flow model that can simulate flow in a complex network of open channels. Unlike MIKE 11, the UNET algorithm can include off-channel storage and flood plain storage areas in the model. This study involved the development and application of the two unsteady flow models mentioned previously. The models were applied to a critical location within the study area. Discharge hydrographs from the HEC HMS hydrologic model were extracted and imported into both models. The time-series results from both unsteady flow models were imported into Arcview GIS using corresponding Arcview extensions to develop floodplain determination and visualization in a spatial environment. 1.1 Objectives The primary research objective was to develop flood visualization tools from the two modeling techniques of the Mill Creek Watershed for the Louisville District. To attain this objective, completion of the following steps was required: 1. Develop a MIKE 11 unsteady flow model for a section of the stream network within the Mill Creek Watershed using data obtained from the Louisville District?s Engineering Division. 2. Develop a HEC RAS unsteady flow model for the same section of stream network 3 as the MIKE 11 model. 3. Incorporate existing results of the Mill Creek Watershed?s HEC HMS model into both the MIKE 11 and HEC RAS models for the 25-yr flood event of April 1998. 4. Develop digital terrain models for the same portion of the Mill Creek Watershed in which the MIKE 11 and HEC RAS modeled stream network exists. Incorporate stream characteristics into both terrain models. 5. Create two- and three-dimensional flood animations of the April 1998 storm from both models for future analysis and public presentations. 6. Determine benefits and limitations of using the two modeling methods. To complete these tasks, an extensive amount of data stored in different formats was required. Current data processing and management practices were used in most cases. Otherwise, dissimilar data sources and modeling software required additional data processing solutions and conversions. 1.2 Study Area The Mill Creek Watershed is located in Butler and Hamilton Counties in southwestern Ohio. It flows from the southeastern part of the rural Butler County in a southerly direction across the highly urbanized Hamilton County and through the city of Cincinnati to its confluence with the Ohio River. The total fall in elevation from the headwaters of Mill Creek to the Ohio River is about 250 feet over an approximate distance of 28 stream miles, with an average gradient of 8.9 feet per mile (0.16%). The watershed is in the northeastern finger of the Hydrologic Unit Code (HUC) #05090203. In 1997, the environmental interest group, American Rivers, designated Mill Creek as ?the most threatened urban stream in North America? (Project Study 4 Plan, 1997). Figure 1-1. Location of the Mill Creek Watershed in Cincinnati, OH. Flooding has been a significant problem for the Mill Creek Watershed for some time. The most damaging flood occurred in January 1959. Since then, there have been numerous floods of lesser magnitude. Over bank flooding occurred in some areas as late as the spring of 1998. Figure 1-2. Mill Creek location with respect to the Ohio River. Based on a Local Cooperation Agreement in 1975, construction by the Corps of Engineers to reduce flooding in the watershed was initiated in 1981 and eventually suspended in 1992, with approximately 50% of the construction complete. The 5 construction was suspended for a number of reasons. The Assistant Secretary of the Army for Civil Works suspended the project because: 1) there were problems in acquiring real estate and relocations for the remaining sections of the creek requiring construction, 2) project costs had soared over 126% of the authorized amount, 3) there was likely contamination of the water from non-point source pollutants from old landfills along some of the uncompleted portions of the reach, and 4) there were problems maintaining and operating the sections where construction was completed (Project Study Plan, 1997). In 1997, a reevaluation study was performed. The effort showed that even with the partially completed plan in place that significant damage would occur from a flood with a 50% chance of occurrence. Total residual damage is estimated over $486 million for the 1% chance flood and over $910 million for the 0.2% chance flood. Total expected annual damage for the flood area is estimated over $32 million, almost 96% of the damage being commercial or industrial (Project Study Plan, 1997). Although completion of the previous plan is economically feasible, the Louisville District believes that a more cost effective and environmentally acceptable plan can be formulated. There is currently strong local support in Cincinnati to address the environmental needs of Mill Creek. This study models unsteady flow for a 25-yr storm event for a 3-mile section of Mill Creek referred to as the Primary Damage Center (PDC). After numerous flood events in recent years, approximately 90% of the overall damage from flooding in the watershed occurs within the PDC. The PDC is located in the northern part of the Mill Creek watershed and is a highly industrialized area. The average gradient of Mill Creek in the PDC is 0.017%. Since the PDC can almost be considered as level ground, the area acts almost like a reservoir after intense storms. Most of the facilities have tried to accommodate for the flood problems by building levees around 6 their property?s boundaries. For the unsteady flow model, the stream network in the PDC study area will have two streams and one tributary. In the northern portion of the PDC, East Fork flows southward from the northeast portion of the study area into Mill Creek. The stream flow from additional tributaries along Mill Creek in the PDC is accounted for as lateral inflow data from the hydrologic model. Figure 1-3. Location of the Primary Damage Center in the Mill Creek Watershed. 1.3 Structure of Report This report documents the data development and implementation of a MIKE 11 and HEC RAS unsteady flow model for flood visualization. The report is divided into eight chapters. Chapter 2 includes a review of previously used methods in 7 literature related to this research. Chapter 3 is a discussion of the data used for both models. The technical capabilities of the computer programs used during the research are outlined in Chapter 4. Chapter 5 discusses the development of the study area?s digital terrain models, which use different formats for the two models. Application of the data and program interface of the MIKE 11 model is documented in Chapter 6. Chapter 7 is the documentation of the HEC RAS model application, and Chapter 8 presents the results and conclusions of the project. Information supplemental to the results of this report are included as appendices. Appendix A includes the conversion of HEC-2 River Station identification numbers to MIKE 11 Chainages for the purposes of geo-referencing. Appendix B provides the Visual Fortran program used to convert HEC RAS cross- sections, in text format, into a MIKE 11 cross-section file. Appendix C provides the MIKE 11 cross-section file created by the Visual Fortran program previously discussed. Appendix D is the initial HEC RAS geometry file created from the HEC-2 data files. Appendix E shows the time-series data transferred from the HEC HMS hydrologic model into the MIKE 11 and HEC RAS flow model. Finally, Appendix F is a data dictionary describing the data used in the project. 8 Chapter 2: Literature Review 2.1 Flood Modeling Incorporating hydraulic model results into a GIS environment has improved flood analysis in recent years. Numerous modeling techniques have been interconnected in an attempt to find an optimum combination of various methods. In an attempt to connect hydraulic results to a spatial interface, Djokic (1994) developed an interface between the Hydrologic Engineer Center?s HEC-2 1-D, steady-state hydraulic model and the Arc/info spatial GIS. The interface, known as ARC/HEC2, exports the terrain data from Arc/info into HEC-2. The ARC/HEC2 interface converts HEC-2 water surface elevations into GIS coverages in Arc/info. Evans (1998) developed a data exchange format to transfer physical element descriptions between hydrologic and hydraulic software packages and GIS software. The package studied was HEC RAS, with the ability to import cross-section locations as XYZ coordinates from terrain models to develop channel and reach geometry. Upon completion of the hydraulic calculations, HEC RAS exports the data back to a GIS for comparison with the terrain model. In 1998, ESRI translated and improved Evans? code and added some utilities to facilitate its use. The result was an Arcview GIS extension called AVRas. Tate (1999) further investigated how to improve upon the HEC RAS model?s accuracy by incorporating field surveyed, stream geometry and control structures into a GIS-based terrain model. His research led to the development of Avenue scripts for Arcview GIS that integrate such data. The terrain model Tate used for his study was based on very accurate digital orthography. Andrysiak (2000) applied Tate?s Avenue scripts to a larger study area using a digital elevation model (DEM) with 30-meter accuracy as the terrain model. When studying both cases, one can deduce that terrain 9 model refinement is limited to the accuracy of the data. In addition, accuracy of the geo-referencing of the surveyed cross-sections and control structures is imperative in the development of an optimum terrain model. Figure 2-1. Channel geometry incorporated into a digital terrain model (Tate 1999). Azagra-Camino (1999) focused on a smaller study area using more precise terrain data from the development of a Triangulated Irregular Network (TIN) in Arcview GIS. The TIN was created from aerial photography, which resulted in a highly accurate terrain depiction of the study area. Using the AVRas extension, Azagra-Camino extracted topographic information from the TIN and imported it as channel and stream geometry for use in the HEC RAS model. The flood visualization results provided highly accurate 2-D and 3-D flood maps. Azagra-Camino?s method was limited to one output in time for each run from the steady state HEC RAS model, making the process of developing flood animations tedious. The animations he created required multiple runs of the HEC RAS model and importing the data into the TIN. Additionally, Azagra-Camino extracted the cross-section data directly from the 10 terrain model. Since the terrain data was based on aerial photography, the cross- section data did not account for existing water surfaces in the stream channel when the photographs were taken. Thus, results from his HEC RAS model may not have been accurate. Figure 2-2. Flood visualization using AVRas and a TIN (Azagra-Camino 1999). The previously mentioned 1-D flood modeling methods used steady state hydraulic modeling to determine stream water surface elevations and flows. The steady-state models do not take into account all of the hydrodynamic effects that more accurately depict actual flood events. The development of 2-D and 3-D animations from steady state models also requires numerous runs at different flow inputs. This makes flood animation development tedious and very time consuming. 11 2.2 Dynamic Models More complex methods of 1-D hydraulic modeling have become more accepted during recent years, as windows-based computer technology has emerged as the optimum graphical analysis tool. Dynamic wave routing was first used in the early 1950s, but was not widely accepted as a flood analysis method. Computer limitations and the complexity of solving methods initially made dynamic wave routing unpopular for practical applications. In 1871, Adhemar Jean Claude Barre de Saint-Venant derived the continuity and momentum equations for 1-D unsteady flow in an open channel, known as the St. Venant equations. The equations he derived assume uniform cross-sections and bed slope for a segment of open channel with no flow above the banks. Danny L. Fread (1976) further investigated the St. Venant equations and developed an implicit method of solving the dynamic wave for the modeling of meandering streams. He distinguished left and right flood plains from the flow channel in a stream?s cross- section. The method was used to solve for the unknowns h (water surface elevation) and Q (stream flow) for specified points along the stream over a series of time steps. Fread first approached the problem by dividing stream channels into two conceptual channels ? the stream channel and floodplain. He made four additional assumptions to simplify the 1-D flow problem: 1) the water surface at each cross-section is horizontal (normal to the direction of flow), 2) the momentum exchange between the stream channel and floodplain is negligible, 3) the flow is distributed to the stream channel and floodplain according to conveyance, and 4) the bed channel slope is small (denoting subcritical flow). These assumptions led Fread to an implicit method to solve the St. Venant equations using a finite difference solution. 12 Figure 2-3. Finite element of a stream channel with force terms. To better understand unsteady flow equation terms, consider a finite segment of the stream as shown in Figure 2-3. There are five acceleration and pressure terms that act on the control volume: convective acceleration, local acceleration, hydrostatic pressure, bed resistance, and gravity. The convective acceleration, local acceleration, and hydrostatic pressure terms are important to dynamic wave motion because they account for pressure and inertial forces which characterize the movement of a large flood wave in the stream (Chow et al 1988). The equations simplify to the following: Continuity equation ?Q + ?A = q (1) ?x ?t Momentum equation ?Q + ?(?Q 2 /A) + gA?h + gQIQI = 0 (2) ?t ?x ?x C 2 AR where Q: discharge A: flow area q: lateral inflow h: stage above datum C: Chezy resistance coefficient 13 R: hydraulic radius g: gravity constant ?: momentum coefficient For Fread?s methodology, the above equations were separated between stream channel and flood plains. The momentum coefficient, also known as the Boussinesq coefficient, accounts for uniform distribution of velocity at a cross-section. Its value ranges from 1.01 for straight prismatic channels to 1.33 for river valleys with flood plains (Chow et al 1988). Fread?s methodology led to the development of the U.S. National Weather Service?s (NWS) DWOPER (Dynamic Wave Operational Model) and DAMBRK models. The DWOPER and DAMBRK models use the implicit method for solving the St. Venant equations for unsteady flow. The DAMBRK model was used by the NWS to analyze floods resulting from dam breaks. The NWS models eventually led to the development of the FLDWAV model by Fread (1985). FLDWAV is a dynamic wave model for 1-D unsteady flows for a single stream or a stream network. Like the DWOPER and DAMBRK models, it is based on an implicit finite-difference solution of the St. Venant equations. Expanding on Fread?s work, Robert L. Barkau (1982) defined a new set of equations that were more convenient to solve by computation methods. He combined the convective terms for both the floodplain and channel using a velocity distribution factor. Barkau also replaced the friction slope (bed resistance term) with equivalent force terms. His work is the basis of the Hydrologic Engineering Center?s 1-D, unsteady flow model called UNET. HEC recently improved upon HEC RAS by including unsteady flow using the UNET program as an extension to the software. The unsteady flow option currently exists for HEC RAS version 3.0. Time-series water surface elevations results developed from a HEC RAS model can now be 14 imported into Arcview GIS using the HEC GeoRAS extension, a new version of AVRas. In Europe, the Danish Hydraulic Institute (DHI) developed the MIKE 11 hydraulic model in 1987 and it became a widely applied 1-D dynamic modeling tool for rivers and channels. Its ability to simulate unsteady stream flows for specified time durations and time steps currently make it a powerful graphical tool. When using the MIKE 11 GIS extension for Arcview GIS, time-series results from a MIKE 11 simulation can be imported into a GIS-based digital terrain model for flood visualization. Carr (1989) and Kjelds (1997) have previously incorporated a DHI-developed hydrologic model, MIKE SHE, with the MIKE 11 and MIKE 11 GIS interfaces for the presentation and analysis of flood impacts. Because of the commonality of the hydrologic and hydraulic models, DHI-based models have been successfully updated into a real-time flood-forecasting tool, known as FLOOD WATCH. 15 Figure 2-4. FLOOD WATCH applied to a region in India (Kjelds 1997). Flood visualization using the HEC RAS and MIKE 11 models are limited to the accuracy of the topographic data from the terrain model and the continuous availability from numerous gage stations. Further discussion of the multiple data sources used in this project are addressed in Chapter 3. If stream geometry and topographic data are obtained from different sources and are not included in the terrain model, then flood visualization results from the hydraulic model can be affected. Flood visualization can still provide some validity, especially when analyzing a complete watershed system where multiple rainfall-runoff inputs are sequenced in time. 16 Chapter 3: Data Discussion This chapter analyzes the data used in this project. The first section discusses the data requirements for the two unsteady flow models applied in this project, and the last section discusses the source of the data used and the processing of that data. The inclusion of the data in the models is described in Chapters 5 through 7. 3.1 Data Requirements The data used in this project is classified into three sections: hydraulic, hydrologic, and spatial data. Each section is examined below. Discussion of all data is applied to both the MIKE 11 and HEC RAS models, unless otherwise specified. 3.1.1 Hydraulic Data Unsteady 1-D flow models require, at a minimum, three forms of hydraulic data: 1) stream geometry, 2) streambed resistance factors, and 3) time-series flow and/or stage height boundary conditions. For both models, streambed cross-sections at locations along the network make up a significant portion of the overall geometry data. Cross-sections act as upstream and downstream boundaries for each finite element in the model. Cross-sections provide the cross-sectional area data required for unsteady flow computations. 17 Figure 3-1. 3-D depiction of a stream with cross-sections in HEC RAS. The network, or stream centerline, of a 1-D flow model can theoretically be modeled as a straight line since natural dispersive effects of flow are not considered. For this project, the stream network contains x- and y-coordinate data in a 2-D plane so as to spatially connect the unsteady flow models to the corresponding terrain models. To accurately depict historic flows in an unsteady flow model, cross-sections must b accurately referenced along the network. For the MIKE 11 model this reference system is referred to as Chainages, and starts from the most upstream location of a stream and heads downstream to its confluence. Chainage values are derived the same way for any additional branches within the hydraulic model. Chainage values are measured in meters. When using the HEC RAS model, the network referencing of the cross-sections is known as River Stations, and runs opposite of Chainages (starts at a stream?s confluence and goes upstream). Unlike Chainages, River Stations can use any sequential method to identify cross-sections, as long as downstream reach lengths from each cross-section to the next are known. 18 Figure 3-2. Comparison of Chainage and River Station network referencing. Bed resistance factors are also necessary when defining hydrodynamic parameters for unsteady flow models. The resistance factors are used in the bed resistance term in the St. Venant momentum equation. In MIKE 11, the bed resistance factors are differentiated between the streambed and flood plains. Thus, the location where the streambed ends and the left and right flood plains begin must be defined in each cross-section. Resistance factors can be defined in the MIKE 11 model from one chainage value to another for a segment of the reach, as well as locally per individual cross-section. Resistance factors can be inputted as Manning?s n, Manning?s M, or Chezy?s C values (MIKE 11 automatically converts resistance factors to Chezy?s C values). 19 Figure 3-3. Differentiation of streambed and flood plain resistance in MIKE 11. In the HEC RAS model, bed resistance is defined at each cross-section as Manning?s n values. Unlike the MIKE 11 model, defining the bed resistance for each cross-section is not limited to only the streambed and flood plains. Differences in resistance can be defined for additional portions of each cross-section as well. Figure 3-4. HEC RAS cross-section with Manning?s n values shown above the graph. 20 The final hydraulic data requirement for unsteady flow models is the boundary conditions. Unlike steady-state conditions, a boundary condition for unsteady flow may be in time-series format defined by a user-specified time range and time step. Time-series boundary types are discharge (Q) and stage heights (h). Another commonly used boundary type not in time-series format is a stage-discharge relationship known as a rating curve. For the MIKE 11 model, the boundary conditions are limited to Q hydrographs for upstream boundaries and h hydrograph for downstream boundaries. When h hydrographs do not exist, the data can be interpolated using the downstream cross-sections rating curve and the existing flow conditions. In HEC RAS, upstream boundaries are defined as Stage, Flow or Stage and Flow hydrographs; downstream boundaries are defined as Stage, Flow, Stage and Flow, Rating Curve, or Normal Depth. Boundary conditions usually depict a flood event for a specified design storm and are obtained from upstream and/or downstream gage station data. The boundary conditions can also be determined from hydrologic models as well. When hydrologic model data is incorporated, lateral runoff hydrographs at watershed outlets along the network provide a more accurate depiction of runoff for that specified storm event. Initial conditions depict base flow conditions prior to a storm event, and are used in MIKE 11 to optimize the model?s performance. When modeling a storm event, the MIKE 11 model can first be used to establish base flow conditions from the gage or hydrologic model data. The simulation is known as a hotstart and is explained in more detail in Chapter 5. 3.1.2 Hydrologic Data As previously discussed, hydrologic data is the output response of a precipitation (storm) hyetograph input to a watershed system. The output response is a flow (runoff) hydrograph for each individual watershed in the system. There are 21 numerous methods used to model hydrology for a specified watershed. In MIKE 11, a hydrologic model can be developed directly from the MIKE 11 software interface using the Rainfall Runoff file. The NAM (lumped, conceptual model), UHM (unit hydrograph method), or SMAP (soil moisture accounting model) modeling methods can be used. Limitations to the Rainfall Runoff file are hydrologic attributes, like a drainage basin?s area and Curve Number for example, must be inputted into the file by hand. For the HEC RAS model, hydrologic data can be imported into the model?s flow data from the HEC Hydrologic Modeling System (HMS). Results from the HEC HMS model are imported by using the HEC Data Storage System (DSS) utility. Further discussion and implementation of the DSS utility can be found in Chapter 7. The HEC HMS model has a wide range of hydrologic modeling methods. Loss rates can be determined using either the SCS Curve Number or the Green and Ampt method. Transformation of the rainfall into a runoff hydrograph can be accomplished using the UHM, Clark, Modified Clark, or Snyder hydrographs (HEC-HMS, 1998). When incorporating hydrologic model results into an unsteady flow model, the key is to accurately geo-reference each watershed outlet to the stream network. Most hydraulic models have means to import or geo-reference a hydrologic model?s results, as long as the flow model and hydrologic model were developed and packaged as supporting software tools. This is the case for both the MIKE 11 and HEC RAS models. Since this project?s focus is on unsteady flow modeling, the hydrologic results for both hydraulic models were derived from the same hydrologic model, previously developed by Andrysiak (2000). Andrysiak?s HEC HMS model results were imported directly into the HEC RAS model using the DSS utility. To integrate the hydrologic results into the MIKE 11 model, the resulting flow hydrograph at each 22 watershed outlet was geo-referenced by using the same x- and y- coordinate plane for both the MIKE 11 stream network and HEC HMS watershed schematic. Figure 3-5. Schematic view of the HEC HMS model developed by Andrysiak (2000). 3.1.3 Spatial Data Visualization of floods in Arcview GIS requires a detailed representation of the terrain to accurately depict flood inundation. As the study area?s size increases, computer memory requirements increase and software-processing speeds decrease substantially. The modeler must find a medium that best fits modeling requirements and computer capacity. The critical spatial data necessary for flood visualization are used to develop a terrain representation of the study area. The data is usually available for the 23 continental United States as grid- or vector-based GIS themes. At a minimum, a Digital Elevation Model (DEM) can be used to develop the terrain model, but is not the optimum data source. Availability of more accurate terrain depictions, like digital orthographic photo images, vector-based contour themes, or Triangulated Irregular Networks (TINs) usually provide more accurate terrain representations. TINs are 3-D GIS themes created by a random mesh of triangles that best fit the depiction of the terrain. An example of a TIN is shown in Figure 3-6. Additional themes in GIS like roads, buildings, levees, and railroads, can also be integrated into the spatial model to improve upon the accuracy of the terrain model. Figure 3-6. A triangular mesh and TIN theme in Arcview GIS. 3.2 Data Sources and Processing The first step in data processing for spatial modeling is to determine a common coordinate system for data sources. Once that is established, identification of data sources and initial processing can begin. The sources and processing of the data for 24 use in this project are categorized into three sections ? terrain data, geometric data, and flow data. For 1-D flow models, the processed data is organized and understood using stream network referencing. Network referencing is the key step to integrating unsteady flow model results with the terrain model in Arcview GIS. This section discusses this project?s data development. 3.2.1 Coordinate System The project required a common projection to spatially correspond the unsteady flow model results to the GIS environment. Since both of the unsteady flow models use an XYZ coordinate system, a Cartesian coordinate system is required. The Ohio State Plane (OSP) Coordinate System for southern Ohio was used throughout the project. All the GIS themes were projected into OSP system using Arc/info, with the following formatted text file as the output projection properties: output projection LAMBERT /* datum NAD83 zunits METERS spheroid GRS1980 xshift 0.0 yshift 0.0 parameters 38.733333 40.033333 -82.5 38.0 600000 end 3.2.2 Terrain Data The Louisville District provided the terrain data used in this study. The data included three vector-based Arcview GIS themes, depicting 1-ft contour lines for the 25 Primary Damage Center (the model area). The three themes were merged into one single theme in Arcview. The terrain model created from the 1-ft contour lines consisted of 6,028,127 triangles within the TIN mesh (240 MB of computer memory). Because of limitations with computer memory capacity, a new terrain model was required. Deleting every other contour line in the study area?s 1-ft contour theme revised the terrain data to a 2-ft contour theme. The new TIN-based terrain model was developed from the 2-ft contour theme. The development of the 2-ft contour theme and the TIN-based terrain model is explained in Chapter 5. The terrain model now consisted of 134,470 triangles in the TIN mesh, using 4.39 MB of computer memory. The result was an accurate terrain data depiction that could be effectively used within the processing constraints of the computer. A practical limit to the number of triangles to use in the TIN mesh is 500,000 triangles. Obviously this number can be adjusted based on computer speed, computer capacity, and modeler requirements. Figure 3-7. Portion of the 2-ft contour theme depicting the Primary Damage Center (study area). Additional Arcview GIS themes can be used to further improve the terrain data. The building and street themes of the study area were also provided by the Louisville 26 District. Existing buildings that lie within a flood plain can create a physical barrier to high stage flows. By incorporating buildings into the terrain model, the stream cross-sectional geometry used in the unsteady flow model can change accordingly. Buildings can divert water flow that may have an impact on the flow model?s results. Building themes can also provide a visual reference when delineating floods with the terrain model. The street theme also has a purpose for use in flood visualization, mainly as a reference tool. When the network referencing of cross-sections, control structures, and watershed outlets are not obvious to the modeler, a street theme can assist with referencing where the street theme intersects with the stream network. When visualizing the results of the flow model in Arcview GIS, streets can assist an observer unfamiliar with the study area by providing a spatial reference for the terrain model. The street theme was unnecessary in the development of the terrain model, since the contour data already contains the topography of the roads. 3.2.3 Geometric Data The geometric data used for the unsteady flow models consists of three basic data sets: 1) the stream network, 2) cross-sections of the stream network, and 3) channel and flood plain resistance factors. 3.2.3.1 The Stream Network The stream network for 1-D unsteady flow models can be created directly in the model or imported from another source. Since the model is 1-D, the model does not differentiate whether the stream is a straight line or has an x- and y-coordinate system related to the terrain model. As long as downstream reach lengths for the channel and flood plain flow paths from cross-section to cross-section are known, and all other geometric data is accurately referenced along the network, the flow model will 27 provide the same results. For this study, the x- and y-coordinates for the network are necessary to integrate the flow model?s simulation results into the GIS spatial environment. One method of developing the stream network is to digitize a polyline in Arcview GIS using orthographic photo images or U.S. Geological Survey (USGS) quadrangle maps in Arcview GIS. Another method is to clip a section of an existing river network theme that corresponds to the terrain model. Existing network themes can be downloaded from the Internet for use in Arcview GIS. One network theme, called an RF3 river reach file, is downloadable from the Environment Protection Agency?s (EPA) Office of Water web site (http://www.epa.gov/ow/soft.html) and contains all the river networks existing in maps of the continental United States at a 1:100,000 scale. An even more accurate network file can be found from the National Hydrography Dataset (NHD), which can be obtained from the USGS web site, http://nhd.usgs.gov/. When working with smaller study areas with more detailed data, RF3 and NHD data may require some editing to better fit the stream network to the terrain model?s stream channel. To create a stream network that fits the same coordinate system as the terrain data, the stream network was digitized from the terrain model in this study. An RF3 river reach file was initially used, but it did not correspond with the terrain model?s stream channel. A point theme was created from the RF3 river reach file and adjusted to fit the stream channel?s centerline. The stream network was digitized from point to point along the stream channel. The same stream network was used for both the MIKE 11 and HEC RAS unsteady flow models. 28 Figure 3-8. Stream network digitized in Arcview GIS using a point theme. 3.2.3.2 Cross-section Data The Louisville District provided two HEC-2 text files that contained cross- sectional data for the stream network. The HEC-2 files were imported into the HEC RAS model to develop geometry files. The geometry files contain x- and z- coordinate profiles of cross-sections at specified locations along the stream network. The resistance factors were also included in the files. The geometry files were saved as .G01 files in the HEC RAS model. 29 Figure 3-9. Example of cross-section data in a HEC-RAS .G01 text file. The HEC-2 files also contained downstream reach lengths and a River Station designation for each cross-section for network referencing. This was important in the conversion process to MIKE 11, to ensure the cross-sections were properly referenced as Chainages along the MIKE 11 stream network. The conversion of the River Station designations to Chainages in MIKE 11 is shown in Appendix A. Using a Visual Fortran program developed by Mr. Stefan Szylkarski from DHI, the .G01 files were converted into text files that the MIKE 11 software could read. The Visual Fortran developed is shown in Appendix B. The resistance factors were was not imported into the file, and are discussed in the next section. 30 Figure 3-10. Cross-section text file readable by the MIKE 11 software. The HEC-2 cross-sectional data was not used for the HEC RAS model. Flood visualization using the HEC GeoRAS extension requires the geometry data to be extracted from the terrain model in Arcview GIS. Using the stream network previously developed, cross-section locations along the stream were manually digitized. River Station referencing and downstream reach lengths were automatically calculated by the HEC GeoRAS extension. This process is discussed in Chapters 4 and 7. 31 3.2.3.3 Channel and Flood Plain Resistance Factors Channel and flood plain resistance factors for this study were also provided in the HEC-2 files as Manning?s n values. For this project, the resistance data was inputted into the MIKE 11 and HEC RAS models manually. HEC GeoRAS provides an option to extract the Manning?s n values from Arcview GIS. If an accurate Land Use theme is available, the HEC GeoRAS extension will automatically calculate Manning?s n values for each cross-section and export those values with the extracted geometry data into the HEC RAS flow model. 3.2.4 Flow Data Flow data for both of the flow models consisted of the stream network?s average base flows and runoff hydrographs derived from the hydrologic model. The average base flows for the stream network was provided by the Louisville District and was assumed constant for both flow models. The base flows were necessary to establish normal flow conditions. The base flow data was provided in cubic feet per second and was converted to cubic meters per second for use in both models. Table 3-1. Base flows for the flow model stream network. Stream ft 3 /s m 3 /s Mill Creek 200 5.663 East Fork 40 1.133 The Hydrologic flow data was extracted from Andrysiak?s HEC HMS model using precipitation data from a 25-yr storm event that occurred in April 1998. Since the HEC HMS model results were in a DSS format, the data could not easily be imported into the MIKE 11 interface. To make the data MIKE 11 readable, the runoff data derived from each drainage basin in the hydrologic model was converted 32 into an Adobe Acrobat file (.pdf file) using Adobe Distiller. The runoff data was copied and pasted into a MIKE 11 time-series file and identified by each drainage basin identification number. Figure 3-11. Runoff hydrograph for the Mill Creek Watershed?s Basin 109. Each watershed outlet was referenced to a location along the stream network. Thus, each runoff hydrograph was incorporated as lateral inflow into the stream network for both flow models. Accumulation of all the runoff data over a specified time range simulated the flood event for the model. For drainage basins not directly connected to the river network, runoff hydrographs were accumulated for corresponding drainage basins for connectivity purposes. The accumulated runoff data existed in the HEC HMS model as flow at junctions. The runoff hydrographs computed from the HEC HMS model are provided in Appendix E. 33 Chapter 4: Modeling Methods This chapter describes the modeling methodologies and capabilities of the computer software used in this study. The description discusses the hydraulic models, MIKE 11 and HEC RAS, and the hydrologic model, HEC HMS. The GIS- based applications, MIKE 11 GIS and HEC GeoRAS, which correspond to the MIKE 11 and HEC RAS models, respectively, are also discussed. Chapters 5 through 7 document the application of the computer models presented in this chapter using the data described in Chapter 3. 4.1 The MIKE 11 Model The MIKE 11 hydrodynamic model was created by DHI in 1987. It is one of the most widely applied 1-D dynamic modeling tools for rivers and channels (DHI, 1999). Along with the MIKE 11 GIS extension to MIKE 11 GIS, time-series results from the MIKE 11 model can be imported into a GIS spatial environment for 2-D and 3-D flood visualization. 4.1.1 The MIKE 11 Hydrodynamic Model The MIKE 11 model runs from a windows-based interface called MIKE Zero. To develop a MIKE 11 hydrodynamic model, five files are necessary: a River Network file, a Cross-section file, a Boundary file, a Hydrodynamic Parameter file, and a Simulation file. Implementation of the MIKE 11 model used in this study is discussed in Chapter 6. In additional to the previously mentioned files, the hydrodynamic model can be expanded to model Water Quality (advection and dispersion modeling), Sediment Transport, and Eutrophication. MIKE 11 can also incorporate a Flood Forecasting file designed to perform calculations required to predict the variation in water levels 34 and discharges in streams as a result of the Rainfall-Runoff hydrologic model implemented through the hydraulic model?s boundaries. The Water Quality, Sediment Transport, Eutrophication, and Flood Forecasting options were not used in this study. Hydrologic modeling results were incorporated into the hydrodynamic model as lateral inflows in the Boundary file. 4.1.1.1 The Simulation file The Simulation file acts as a ?simulation manager? for the other files and does not require any external data. It defines the model type under the Model tab. By defining all the input files of the model under the Input tab, it acts as the link between the Network file and the other MIKE 11 files. Figure 4-1. Input tab in a MIKE 11 Simulation File. The Simulation tab contains the simulation and computation control parameters. The modeler defines simulation start and end times and time step under this tab. Under the Initial Conditions on the Simulation tab, the user establishes the initial 35 conditions for the simulation. Options are Steady State, Parameter file, Hotstart, or Steady and Parameter. In the case of this study, the initial conditions were established using a hotstart file, as shown in Figure 4-2. A hotstart is a file that establishes base flow conditions for unsteady flow. The hotstart simulation is the steady-state solution for an unsteady flow model, which eliminates instability in the simulation created by initial conditions. Figure 4-2. Simulation file with a ?Hotstart? Initial Conditions Type. The Simulation file also allows the modeler to determine the name of the results file. Once all information is inputted into the file, the Simulation file identifies any errors with the established conditions before running a simulation, as well as running an unsteady flow simulation. 4.1.1.2 The River Network File The MIKE 11 model?s River Network file is the common link to the various 36 MIKE 11 files. It also has an XY coordinate system, allowing the model to import and export data to and from a GIS environment using the MIKE 11 GIS extension. The River Network file allows the modeler to 1) define the river network and reference cross-sections and control structures to the network; and 2) graphically obtains an overview of model information in the current simulation. Figure 4-3. River network file defined by XY coordinate data points. The River Network file can be digitized graphically, or inputted as XY coordinate data points, which are then manually connected. Chainage values along the network are automatically determined once the user defines the most upstream Chainage value(s). Control structures like dams, culverts, and weirs are added to the model in the River Network file, where the Chainage value referencing already exists. 37 Figure 4-4. Tabular view of a river network depicting XY coordinate data points. 4.1.1.3 The Cross-section File The Cross-section file contains streambed cross-sections as specified locations along the river network. The geometry of cross-sections usually is obtained from one of two sources - field-surveyed data or extracted from user-defined locations in a terrain model. 38 Figure 4-5. Raw data view of a cross-section in MIKE 11. There are two types of cross-section data in MIKE 11: the raw data, and the processed data. The raw data is the geometric data of each cross-section derived from the above-mentioned sources. It also includes the local variation in bed resistance specific to that cross-section. The processed data is derived from the raw data and contains the cross-section?s computational information used by the computer model. Cross-section raw data can be imported as a readable text file and can be edited directly from the Cross-section file editor. 4.1.1.4 The Boundary File The Boundary file consists of boundary conditions in time-series format for the river network?s boundaries. The file consists of four boundary condition options: Hydrodynamic, Advection Dispersion, Sediment Transport, and Rainfall Runoff. The Hydrodynamic option is the only boundary condition option used in this study. Boundary types include Water level (h), Discharge (Q), Q/h Relation, Wind 39 Field, Dambreak, and Resistance Factor. The Water level boundary must be applied to either the upstream or downstream boundary condition in the model. The Discharge boundary can be applied to either the upstream or downstream boundary condition, and can also be applied to side tributary flow (lateral inflow). The lateral inflow is used to depict runoff for this study. The Q/h Relation boundary can only be applied to the downstream boundary. The Wind Field boundary accounts for wind effects and can be applied globally or at specific branches in the river network. The Dambreak boundary simulates a dam?s failure on the river network. The Resistance Factor boundary accounts for a time varying bed resistance along the river network. Only hydrodynamic boundary conditions were applied to this research. Figure 4-6. MIKE 11 boundary file. Boundary types are linked to a time-series data file in the Boundary file. As 40 shown in Figure 4-6, the boundary at Chainage value 15407.15 is defined as a Discharge boundary and is linked to a Time Series File under the Discharge Specifications. 4.1.1.5 The Hydrodynamic Parameter File The Hydrodynamic Parameter file requires bed and flood plain resistance data for the river network. Differentiation between the streambed and flood plain along the river network is accomplished at each cross-section in the Cross-section file. Bed and flood plain resistance can be inputted as Chezy?s C, Manning?s M, or Manning?s n values. The resistance factors are inputted from one location to another along the river network (chainage to chainage), as resistance changes. Resistance for streambeds and flood plains is inputted separately. Any local differences in resistance may be incorporated into the Cross-section file at a specified cross-section. The overall resistance is then the product of the resistance factor from the Cross- section file and the Hydrodynamic Parameter file at that specified location. 41 Figure 4-7. Bed resistance from chainage to chainage in the hydrodynamic file. 4.1.2 MIKE View Results of MIKE 11 simulations can be observed using the MIKE View software. MIKE View displays longitudinal profile animations of both stage height and discharge resulting for a MIKE 11 model. It also can display stage height at any given cross-section, as well as provide rating curves at a specified location along the network. MIKE View can also provide time-series results of stage heights at cross-section locations and time-series results of discharge at midpoints between two cross-section locations. This tool has been beneficial for this research by providing a facility for creating new boundary conditions for the model, as the study area was refined from the entire extent of the Mill Creek reach to a smaller area defined as the Primary Damage Center. To incorporate the contour data into the model, limitations to computer capacity had to be accounted for by refining the model area. The refinement focused on the most critical location of flood damage in the Mill Creek Watershed. Thus, the study area was refined to the Primary Damage Center. 4.1.3 The MIKE 11 GIS Extension The MIKE 11 GIS extension integrates the MIKE 11 model with Arcview GIS. Like the MIKE 11 model, MIKE 11 GIS was developed by DHI. It acts as a bi- directional exchange between MIKE 11 and Arcview GIS. MIKE 11 GIS provides the following options to the modeler: ? Terrain model development in Arcview GIS using a grid-based mesh ? Extraction of geometric data from the terrain model for use in the MIKE 11 model ? Import MIKE 11 model time-series results into Arcview GIS for flood 42 visualization ? Develop 2-D and 3-D views and animations with the MIKE 11 model results and the corresponding terrain model (DHI, 1998) If the river network in the MIKE 11 model already has a corresponding XY coordinate system to the terrain model, extraction of geometry data using MIKE 11 GIS is not required to import MIKE 11 results into Arcview GIS. If this is the case, the modeler needs to be aware of the differing data sources and ensure the existing geometry data is accurately geo-referenced with the river network. 4.2 The HEC RAS Model HEC RAS is a hydraulic model created by the Hydrologic Engineering Center. The first version of HEC RAS was developed in 1990 and evolved from a steady flow model called HEC-2, first developed in 1966 (HEC-RAS, 1998). As computer capabilities improved, the HEC-2 software was converted to the windows-based HEC RAS software to better assist hydraulic modeling with a graphical user interface. In April 2000, the Hydrologic Engineering Center also developed the HEC GeoRAS extension of Arcview GIS, a pre- and post-processing tool for the HEC RAS model. HEC GeoRAS is an upgrade to the previously used AvRAS extension. 4.2.1 The HEC RAS Unsteady Flow Model The HEC RAS model was initially used for calculating water surface profiles for 1-D steady-state flow. The results from the model have been applied to flood management and flood insurance studies throughout the United States. Recently, HEC RAS has incorporated an unsteady flow model in its beta version 3.0 (the final 3.0 version should be available by the end of calendar year 2000). The HEC RAS 3.0 version provides the modeler with an option to use either the steady flow or unsteady flow option. The unsteady flow option runs the UNET algorithm from the software. Results from the UNET algorithm are then imported back into HEC RAS for viewing 43 of simulations. Figure 4-8. Main menu of HEC RAS version 3.0, with the unsteady flow option. Along with the unsteady and steady flow options, the HEC RAS model also provides the following capabilities: ? Modeling of open channel networks and single rivers (both unsteady and steady flow options) ? Analysis of bridges, weirs, and culverts (unsteady and steady flow options) ? Modeling storage areas, navigation dams, tunnels, pumping stations, and levee failures (unsteady flow option only) ? Handling of subcritical, supercritical, and mixed-flow regimes (steady flow option only) (HEC-RAS, 1998) The unsteady flow option was used for this project. To develop an unsteady flow model, three files are required: the Geometric Data file, the Unsteady Flow Data file, and the Unsteady Flow Analysis file. 4.2.1.1 The Geometric Data File The Geometric Data File contains all the pertinent geometry necessary for hydraulic modeling. It establishes the connectivity of the river network (using River 44 Stations for network referencing), cross-section data (to include Manning?s n resistance factors), stream junctions, and hydraulic structures. The file editor allows the importing of geometric data from previous HEC RAS versions, UNET models, and from Arcview GIS. Editing any of the geometric features can also be accomplished from this file. Figure 4-9. HEC RAS version 3.0 geometric data file editor. HEC RAS version 3.0 also includes a Storage Area editor, a Hydraulic Connectivity editor, and HTAB Parameters editor. The Storage Area editor provides the modeler the capability to add and edit storage areas within the river network 45 system. The Hydraulic Connectivity editor connects the river network and cross- sections with existing hydraulic structures and storage areas. The HTAB Parameters editor establishes the initial conditions for the unsteady flow option (initial water surface elevation at each cross-section in the network) and the incremental unit value (for the change in water surface elevations) used in the UNET algorithm. The incremental unit value is the incremental change of water surface elevation used by the UNET algorithm, and is set to a default of 0.1 meters. 4.2.1.2 The Unsteady Flow Data File The Unsteady Flow Data file consists of the boundary conditions and initial conditions for the model. The initial conditions contain the initial flow distribution for each reach within the river network. The time-series boundary conditions contain the upstream and downstream boundary conditions (at a minimum) defined as a Stage, Flow, or Stage and Flow hydrograph. Internal river network boundary condition options include Lateral Inflow, Uniform Lateral Inflow, and Groundwater Interflow hydrographs. The Lateral Inflow hydrograph option depicts tributary, point source, or watershed outlet (runoff) inflows. The uniform lateral inflow depicts overland inflow evenly distributed from one River Station location to another along the river network. Lastly, the Groundwater interflow hydrograph models inflow into the river network from groundwater recharge. 46 Figure 4-10. HEC RAS version 3.0 unsteady flow data file editor. Once the boundary and initial conditions are defined in the Unsteady Flow Data File editor, each boundary condition is linked to a user inputted time-series data editor. The time-series data can be linked to a HEC HMS or HEC RAS model results using the DSS interchange or inputted manually into the time-series data chart. The modeler also defines the time-series data?s time interval and reference starting time from this editor. 4.2.1.3 The Unsteady Flow Analysis File The Unsteady Flow Analysis file establishes the user specified conditions for the unsteady flow simulation. The modeler sets the starting and ending time for the simulation, and establishes the computational settings for running the UNET 47 algorithm. The computational settings include the computational interval, hydrograph output interval, and instantaneous profile interval. The instantaneous profile interval must be equal to or greater than the computational interval to run the simulation. Figure 4-11. HEC RAS version 3.0 unsteady flow analysis file editor. Once the unsteady flow model is simulated, errors in logic for the geometric, HTAB, and unsteady flow data are identified by the software. Once all errors have been resolved, the HEC RAS software runs an HTAB algorithm to establish the initial conditions for the entire river network, in preparation for running the UNET algorithm. Once that is accomplished, the computer executes the UNET algorithm for the simulation. Results include water surface profiles for each cross-section at 48 each time step within the starting and ending time ranges for the entire river network. 4.2.2 The HEC GeoRAS Extension The HEC GeoRAS extension integrates results from the HEC RAS model into Arcview GIS. It acts as a geometric data pre-processor and HEC RAS results data post-processor in Arcview GIS. HEC GeoRAS provides the following options to the modeler: ? Extraction of geometric data from a TIN-based terrain model for use in the HEC RAS model (pre-processing) ? Import of the HEC RAS model time-series results into Arcview GIS for flood visualization (post-processing) Unlike the MIKE 11 model, geometric data must be extracted from the terrain model into the HEC RAS model to develop flood visualization in Arcview GIS. This pre-processing step geo-references the unsteady flow model results to the terrain model. The GeoRAS extension also develops a bounding polygon in Arcview GIS, which establishes the limits of flooding in the terrain model. If the modeler is unaware of floodplain extents prior to developing the model, the bounding polygon may be too wide or too narrow when observing the HEC RAS results in Arcview GIS using the post-processor. By iteration, the optimum size of the bounding polygon can be determined. 49 Figure 4-12. Bounding polygon derived from cross-sections using GeoRAS. The terrain model is of Waller Creek flowing through the University of Texas Main Campus. 4.3 The HEC HMS Model HEC HMS is a hydrologic model developed by the Hydrologic Engineering Center of the U.S. Army Corps of Engineers. In 1968, HEC released the HEC-1 computer model to aid engineers in hydrologic analysis. The windows-based HEC HMS software was released in 1998. The program simulates a rainfall runoff response of a watershed system to a precipitation input by representing the entire watershed as an interconnected system of hydrologic and hydraulic components, which include watersheds, streams, and reservoirs. The results from a HEC HMS model can be used as input data for hydraulic modeling. The HEC HMS software provides the following computational options to deriving runoff responses to simulate precipitation-runoff processes: ? Several alternatives for loss determination ? Lumped or linearly distributed runoff transformation methods ? Routing options 50 ? An optimization system for calibration (HEC-HMS 1998) 4.3.1 Loss Determinations The term ?losses? refers to the amount of the rainfall from a storm event that is diverted from runoff, usually infiltrating to soil or flowing to other means of storage in the watershed system. The HEC HMS model supports the most common methods for calculating losses, like the initial/constant rates, Soil Conservation Services (SCS) Curve Number method, and the Green and Ampt method. These methods can be lumped or linearly distributed throughout the model. In a lumped analysis, losses are spatially averaged over a watershed within the watershed system. For a linearly distributed method, the rainfall is spatially defined for the entire watershed system, and losses are averaged for each watershed in the system. 4.3.2 Runoff Transformations Runoff transformations convert the precipitation from a storm event, minus the losses, to direct runoff for each watershed in the system. The runoff is computed as a hydrograph response at each watershed?s outlet. Like the loss determination, the HEC HMS software allows the modeler to use lumped or linearly distributed approaches to runoff transformation. In a lumped analysis, the amount of runoff is determined either using unit hydrographs like the Clark, Snyder, or SCS hydrographs, or the kinematic wave method. In a linearly distributed method, like the Modified Clark hydrograph, the watersheds in the watershed system are spatially interpreted as numerous grid cells within a user-defined grid mesh, and the time (known as lag time) for excess rainfall to move from that grid cell to the watershed?s outlet is determined. The hydrograph for the Modified Clark method is created from the sum of the all the grid cell?s lag times for each watershed in the system. 4.3.3 Routing 51 Routing is the movement of the runoff from the different watershed outlets throughout the system along the streambed, and ultimately to the outlet or sink of the entire watershed system. The HEC HMS model routing options include the Muskingum, Modified Puls, Kinematic Wave, and Muskingum-Cunge methods. Figure 4-13. Discontinuities between watersheds in a hydrologic model and the boundaries of the hydraulic model (shown in bold). Hydraulic models do not always model the entire stream network used in a corresponding hydrologic model, as shown in Figure 4-13. Some modelers may further refine the study area to a smaller range. In such cases, the routing methods provided in HEC HMS software can provide flow hydrographs at locations known as junctions along the stream network as well. This provision can compensate for discontinuities between the two models by providing upstream and downstream boundary conditions for the further refined hydraulic model. 52 4.3.4 Parameter Optimization To use the HEC HMS model as an engineering modeling tool, it requires calibration to the historic flow conditions of the actual watershed system. The process can be simple or complex and requires the adjustment of numerous parameters to optimize model results. The HEC HMS software provides an option for model optimization. The HEC HMS model used for this study was not calibrated, because of a number of complications existing in the actual watershed system. Combined sewer overflows, the unknown capacity for storage, and the diurnal effects of wastewaters all contribute to the on-going hydrologic problems with the Mill Creek Watershed. More information on the hydrologic model and its calibration is discussed in further detail in Andrysiak?s report. 53 Chapter 5: Terrain Model Development When delineating floods in a spatial environment, the accuracy of the terrain model is very critical. The most accurate terrain data currently used is obtained from photogrammetry. Photogrammetry is the science or art of obtaining reliable measurements by means of photographs (Tate, 1998). One of the most common uses of photogrammetry is the analysis of aerial photography to extract ground elevations to produce topographic maps. Digital terrain data is obtained from a plane traveling over a study area taking photographs. Photographs are taken from two passes of the study area, so that every point on the ground appears in at least two successive photographs. Digital terrain data, like a DEM or contour data, is obtained from the photographs using either an analog instrument called a stereoplotter, or by using digital image processing software (Tate, 1998). Photogrammetry data is limited to the many arbitrary surfaces that make up the terrain. So, if water exists in a streambed when the photographs are taken, the water surface elevation data (not the streambed?s geometry data) is included as part of the terrain data. In such cases, hydraulic modelers find themselves in a quandary ? how can one integrate accurate terrain data with existing streambed geometry (i.e. surveyed data of the streambed) to delineate flood events? As previously discussed, Tate created a terrain model from surveyed flood plain data and a DEM. Azagra-Camino developed a terrain model from accurate photogrammetry data, but did not compensate for water in the streambeds, making the streambed geometry inaccurate. For this study, both methods were examined to optimize the terrain model. Since the contour data was accurate to 2-ft for this study, using Tate?s method to integrate the entire flood plain of the study area?s hydraulic model into the terrain model was not the solution. Highly accurate contour data existed near the stream, like bridge embankments and 54 levees. Using Tate?s method may compromise the contour data. After numerous iterations and trials, the best option used for this study was to integrate only the streambed geometry, without the flood plain geometry, with the terrain model. 5.1 Methodology of Terrain Model Development Using the contour data provided by the Louisville District, the three 1-ft contour themes were merged in Arcview GIS to account for the entire PDC study area. As previously discussed, the 1-ft merged contour theme was modified to a 2-ft contour theme by deleting every other contour line in the file. The new contour theme was created and saved as pdc2ftcontrs.shp. No data was available for a small section on the west side of the study area (which was outside the extent of the flood plain). To compensate for this lack of data, point elevations were extracted from a 30-meter DEM. The section?s missing data was clipped from the point elevations and saved as a point shape theme called pdctmpts.shp. 5.1.1 Initial Terrain Model Development Using an algorithm known as Delaunay Triangulation, Arcview GIS optimizes a 3-D representation of the terrain by creating triangles that are as close to equilateral as possible. The result is a TIN-based terrain model. It is a terrain representation using points in three-dimensional space, with topological faces in two dimensions (ESRI, 1999). 55 Figure 5-1. Example of a TIN-based terrain model. The TIN represents a portion of Lake Austin in Austin, TX, developed by Kevin Donnelly at the Center for Research in Water Resources. Using the 3D Analyst extension in Arcview GIS, the terrain elevation data was extracted from the pdctmpts.shp and pdc2ftcontrs.shp file to develop a TIN of the study area. A bounding polygon, called theme1.shp, was used to define the study area?s boundaries, as shown in Figure 5-1. The point elevations were defined as mass points and the contour lines were defined as soft breaklines during the setup. Like mass points data, soft breaklines act as elevation input to the terrain model, but maintain continuous slope for the terrain?s surface. The TIN was created using the Create TIN from Features command in Arcview GIS. The initial TIN-based terrain model was saved as Crtin1. 56 Figure 5-2. Points, contours, and bounding polygon used for the PDC terrain model. 5.1.2 Limitations of Digital Terrain Data used for Hydraulic Modeling The digital terrain data did not contain an accurate geometric representation of the streambed for use in the unsteady flow models. To verify this, the geometric data of the streambed was extracted from the terrain model and imported into HEC RAS (this extraction was accomplished using HEC GeoRAS, and is explained further in Chapter 7). There were two problems with the digital terrain data that affected the overall hydraulics of the system. First, the digital terrain data streambed elevations are on average 2.25 meters higher along the length of Mill Creek when compared to the surveyed cross-section data, as shown for River Station 43982 in Figure 5-3. Thus, the photogrammetry data is accounting for water in the stream. The range of the elevation difference ranged from approximately 2.1 to 2.4 meters higher for the 57 extracted terrain data than the surveyed data along Mill Creek?s longitudinal profile. Figure 5-4 illustrates the difference in the two profiles. This is a difference of approximately 259,000 m 3 in water volume that the initial terrain model did not account for. River Station 43982 171 172 173 174 175 176 177 178 179 180 0 20406080 x (m) z (m) Surveyed Data Terrain Model Data Figure 5-3. A surveyed cross-section of Mill Creek compared to terrain model data. 58 Mill Creek Longitudinal Profile Comparison 168 169 170 171 172 173 174 175 176 0 2000 4000 6000 x (m) z (m) Terrain Model Surveyed Data Figure 5-4. Comparison of the Mill Creek streambed?s longitudinal profile developed from the terrain model and the HEC-2 surveyed data. Secondly, the longitudinal axis of Mill Creek, as viewed in HEC RAS, depicted a terraced streambed, as shown in Figures 5-4 and 5-5. The axis did not accurately represent the streambed of Mill Creek. The natural effects from erosion and deposition create a much smoother transition from upstream to downstream. The terraced effect also created supercritical and subcritical flow regimes along the stream, which was difficult to represent in an unsteady flow model based on the initial assumption of subcritical flow. The terraced streambed was created from the interpolated TIN data. Using contour line data as the input, the interpolation was not linear, but instead developed plateaus at each contour line. This may have been the result from defining the contour lines as soft breaklines instead of hard breaklines. 59 Figure 5-5. Terraced streambed of Mill Creek created from the TIN data. 5.1.3 Integration of Streambed Geometry and Terrain Data To integrate the geometric attributes of the streambed with the digitial terrain data, a Floodmap utility developed by Tate (1999) was used. Tate created the utility for the purpose of incorporating HEC RAS geometry data into a terrain model for floodplain delineation. The utility produces a modified TIN-based terrain model by: 1) Importing stream cross-sectional data from HEC RAS into Arcview GIS 2) Geo-referencing the cross-sections to the corresponding location along the stream in the terrain model 3) Converting the stream geometry to 3-D themes in Arcview GIS 4) Adding the 3-D stream geometry to the existing digital terrain data The floodmap utility first removes the spatial bounds defined by the digital terrain data before adding the 3-D stream geometry. Then the entire floodplain is incorporated into the terrain model. For this study, surveyed data of the streambed only was incorporated into the terrain model by modifying Tate?s methodology. 60 Figure 5-6. Tate?s Method of incorporating flood plains into a terrain model (Tate, 1999). 5.1.3.1 Importing Cross-sectional Surveyed Data into Arcview GIS The floodmap utility was limited to defining the 3-D stream centerline and bank lines from the imported cross-section locations, as a straight line from cross- section to cross-section, as shown in Figure 5-7. If the number of cross-sections is limited and the cross-sections do not account for every bend in the stream, then the stream centerline location with respect to the terrain model will be inaccurate. By increasing the number of cross-sections along the stream centerline, the straight line segments derived by the floodmap utility would get smaller and smaller, creating a more accurate depiction of curves in the stream for the model. More cross-sections were required, especially along curved sections of the stream centerline. To compensate for this, cross-sections between surveyed cross-section data were interpolated in the HEC RAS model before being imported into Arcview GIS. 61 Figure 5-7. Comparison of the stream (blue arrows) and a 3-D stream centerline and bank lines created by the Arcview GIS Floodmap utility. The development of interpolated cross-sections between the surveyed cross- sections in HEC RAS when defining the stream centerline and bank lines was an iterative process. Imported data were compared to the actual stream centerline in Arcview GIS for accuracy. If they did not match, then additional cross-sections were interpolated until the derived stream centerline overlapped the actual stream centerline. Spacing between interpolated cross-sections was typically around 25 meters in stream centerline length. 62 Figure 5-8. A revised depiction of cross-sections and bank lines as compared to the stream centerline (shown with blue arrows). A significant improvement is apparent when compared to the non-interpolated cross- sections shown in Figure 5-7. Figure 5-8 shows the addition of the interpolated cross-sections to the surveyed cross-section data. This method decreased straight line distances between cross- sections using the floodmap utility, thus improving the depiction of curvature for the stream centerline. A significant improvement is noticed when comparing the stream bed depiction to the stream centerline shown in Figure 5-8 to the previous depiction in Figure 5-7. 63 Figure 5-9. Cross-sections interpolated between existing cross-sections in HEC RAS. Once the interpolated cross-sections were finally developed, the data was exported into Arcview GIS by using the Generate Report command in HEC RAS. Tate?s Floodmap utility creates a text file in dBASE format from the HEC RAS report. The text file includes River Station identification numbers, water elevation (for steady-state profiles in HEC RAS), lateral and elevation coordinates of all cross- section points (stored in a global variable, not in the table), the width of the left and right flood plains with respect to the stream centerline, the elevation of the left and right banks and stream centerline, and downstream reach lengths between cross- sections. Once the data was imported into Arcview GIS, the stream centerline was geo-referenced to the digital terrain data prior to incorporating the stream geometry into the terrain model. 64 5.1.3.2 Cross-section Geo-referencing Locations along the stream network require accurate geo-referencing with the terrain data. It is possible that the digital stream centerline may have minor differences in length compared to the HEC RAS stream centerline. To compensate for these inconsistencies, the floodmap utility assigns upstream boundaries, downstream boundaries, and intermediate stream definition points along the stream. This is accomplished by assigning definition points at a cross-section located near a well-defined reference point in the terrain data, such as a bridge or culvert location. For this study, the corresponding road network, called rd3dclp.shp, was used to identify bridge locations along the stream network. Figure 5-10. Sharon Rd. used as an intermediate point for geo-referencing. For this study there are four intermediate points identified at the intersection of the roads and the stream centerline. The upstream boundary is defined as the Hamilton/Butler County line and the downstream boundary is defined as Glendale Road. 65 Table 5-1. Stream definition points for the study area. Type of Point Location RS Number Mill Creek Upstream Boundary County Line 200055 Intermediate Point Highway I-275 195540 Intermediate Point Kemper Road 194227 Intermediate Point Sharon Road 188635 Downstream Boundary Glendale Road 182205 East Fork Upstream Boundary County Line 388 Downstream Boundary Confluence with Mill Creek 0.0 5.1.3.3 Converting Stream Geometry Data into 3-D Themes The River Stations (RS) for the surveyed cross-sections that correspond with the stream definition points (as shown in Table 5-1) were labeled in the imported dBASE table. The geo-referencing process, as well as the subsequent 3-D theme development, is accomplished separately for Mill Creek and East Fork. The Floodmap utility creates a 3-D cross-section theme and a 3-D stream theme for the two streams in the study area using the Mapping HEC RAS Cross-sections command. The HEC RAS cross-section locations are geo-referenced to the terrain, defines the stream centerline and bank lines. The 3-D cross-section themes were saved as 3dxsectmc.shp and 3dxsectef.shp. The 3-D stream themes, consisting of a stream centerline and channel banks, were saved as Stream3dmc1.shp and Stream3def1.shp. The 3-D themes created in this process are polylineZ files. PolylineZ files contain an elevation attribute to form a three-dimensional line, or arc. A 3-D 66 depiction of the Mill Creek polylineZ files is shown in Figure 5-11. The next step in the process was to integrate the polylineZ themes into the terrain model. Figure 5-11. PolylineZ themes of the stream channel and cross-sections. 5.1.3.4 Incorporating Stream Geometry into the Terrain Model Prior to integrating the stream geometry into the terrain model from the existing polylineZ themes, the terrain model was converted to a mass points theme, with each point representing a point elevation. The purpose of the conversion was to create a depiction of the existing terrain model that can be edited in Arcview GIS. This was first accomplished by converting the existing terrain model, Crtin1, to a Grid-based model. By using the 3D Analysis extension, the TIN-based model was converted to a Grid-based model using the Convert to Grid command. The grid mesh was defined by 5-meter by 5-meter grids. The Grid-based terrain model was saved as Pdcgrid1. The Grid-based terrain model was converted to mass points using the Convert Grid to Points command in the Floodmap utility. The mass points were saved as Gridpts.shp. 67 In Tate?s method, a bounding polygon is developed from the 3-D cross-section themes, defining the extent of the flood plain. For this study, this step was modified. Instead of highlighting the 3-D cross section themes to define the bounding polygon, the 3-D stream themes were highlighted. This established the stream banks as the extent of the bounding polygon. The 3-D cross-sectional data was also limited to the stream channel as well, by clipping the Mill Creek and East Fork cross-section themes, saving them as Mcclip.shp and Efclip.shp. This process alleviated any overlap in the data, as shown in Figure 5-12, and then was used to develop a modified terrain model. Figure 5-12. Section of Mill Creek with mass points data and stream geometry. Defining Gridpts.shp as mass points and channel geometry as hard breaklines, a modified terrain model was developed, using the Create TIN from Features command from the 3D Analyst extension. The developed TIN-based terrain model was saved as Nwtin1. Figure 5-13 shows the depiction of the modified terrain model, with the surveyed stream geometry. 68 Figure 5-13. TIN-based terrain model modified with surveyed stream geometry. The modified TIN-based terrain model was used with the HEC GeoRAS interface. Unlike the MIKE 11 model, stream geometry data were extracted from the terrain model for use in the HEC RAS unsteady flow model, as discussed in Chapter 7. 5.2 Application of the Terrain Model to the MIKE 11 GIS Interface The MIKE 11 GIS extension uses a Grid-based terrain model instead of a TIN- based terrain model. The MIKE 11 GIS interface in Arcview GIS has the capability to edit the terrain model, but the modifications accomplished previously for this study remove the need for editing. The Grid-based terrain model was developed from Arcview GIS by converting the TIN theme to a Grid-based theme. The Grid mesh was defined as 5-meter by 5-meter cells. The Grid-based terrain model was called 69 Pdcdem. Figure 5-14. The PDC Grid-based terrain model shown with hill shading effect. A disadvantage of the Grid-based terrain model is poor resolution as compared to the TIN-based terrain model. As shown in Figure 5-15, the water surface delineation with the terrain creates a rough edge since a grid mesh accomplished the delineation. The Grid-based terrain model requires less computer memory as compared to a TIN-based terrain model. The Pdcdem was 450 kilobytes in computer memory size, whereas the TIN-based Nwtin1 was 4.4 megabytes. 70 Figure 5-15. Rough edge created when delineating the water surface from the terrain using the MIKE 11 GIS grid-based delineation method. 71 Chapter 6: Application of the MIKE 11 Model This chapter discusses the development of the MIKE 11 model as applied to the Mill Creek study area. The three steps to developing the model were processing of the geometric data, inclusion of bed resistance factors, and the integration of flow data from the hydrologic model. Upon completion of model development, simulation results were post-processed in MIKE 11 GIS. The results provided 2-D and 3-D flood animations for the Mill Creek Watershed?s 25-year flood event. 6.1 Geometric Processing As discussed in Chapter 3, the MIKE 11 model consists of two geometric files ? the network file and the cross-section file. This section explains how the processed data was incorporated into the MIKE 11 flow model. 6.1.1 Stream Network Development The stream network used for the MIKE 11 model was the network digitized and saved as stream1.shp in Arcview GIS. The X- and Y-coordinates were added to the databases of the Millpdcreachpts.shp and Eastpdcreachpts.shp point themes (stream points defining stream1.shp). The XY-coordinates in the databases were copied into the tabular view of the MIKE 11 network file editor. Using the Define Branch tool in MIKE 11, the data points were connected to create the network file. The network file was saved as pdc1model.nwk11. 72 Figure 6-1. MIKE 11 Stream network created with the Define Branch tool, from point to point. The figure shows the location where East Fork flows into Mill Creek. 6.1.2 Cross-section Data Development Upon conversion of the HEC-2 geometry files into readable text files for the MIKE 11 interface, the surveyed cross-section data was imported into the MIKE 11 cross-section file editor. The cross-section file required manual editing of the Chainage values for each cross-section (which was defined as River Stations in HEC- 2), and streambed and stream bank locations for each cross-section. The Chainage values were inputted for each cross-section using the conversion table in Appendix A. The stream bank and the streambed locations, as identified in the HEC-2 files, were defined in the cross-section editor using the MIKE 11 Mark tool. The Mark tool defined a number 1, 2, or 3 along the cross-section in the MIKE 11 cross-section editor. Mark 1 defined the left stream bank, Mark 2 defined the streambed (or centerline), and Mark 3 defined the right bank. Figure 6-2 shows an example of the MIKE 11 cross-section file?s streambed and stream bank locations. 73 Figure 6-2. Cross-section #19166 in MIKE 11. The Marks 1, 2, and 3 are identified on the cross-section?s graphical view as red ?X?s. Interpolation of cross-sections at the Primary Damage Center model?s upstream and downstream boundaries was required. The new bounding cross-sections were interpolated from corresponding upstream and downstream surveyed cross-sections from the HEC-2 files. The interpolated cross-sections were located at Chainage #15407.15 (Mill Creek?s upstream boundary), #11427.12 (East Fork?s upstream boundary), and #20732.45 (Mill Creek?s downstream boundary). Once all editing was completed, the MIKE cross-section file was saved as pdcXSec1.xns11. 74 Figure 6-3. The MIKE 11 Cross-section interpolation tool. The cross-section interpolation at the model?s boundaries was accomplished using cross- sections outside the PDC terrain model?s boundaries from previous MIKE 11 models. 6.2 Bed Resistance Factors Bed resistance is defined in two different files in the MIKE 11 model. Bed resistance values are defined for a segment of the stream network, from an upstream cross-section location to a downstream cross-section location, using the MIKE 11 hydrodynamic file editor. Bed resistance factors are also defined in the MIKE 11 cross-section file editor. The overall resistance for the model is the product of the resistance factors in the cross-section file and the hydrodynamic file. An example of the resistance factors defined in the two MIKE 11 files are shown in Figure 6-4. The resistance factor in the MIKE 11 cross-section file for each cross-section was set to a default of 1. The Manning?s n values were extracted from the HEC-2 geometry data and manually inputted as bed resistance and flood plain resistance values in the hydrodynamic file. The Marks tool in the MIKE 11 cross-section file editor 75 delineates the stream channel from the flood plains, defining where the bed resistance values change along the cross-section. Once the bed resistance factors were manually inputted into the MIKE 11 hydrodynamic file, the file was saved as HDPar1.hd11. Figure 6-4. The overall resistance factors in the MIKE 11 model are the product of a) the Cross-section File resistance factors, and b) the Hydrodynamic File resistance factors. 6.3 Boundary Conditions The PDC MIKE 11 model contained two separate boundary condition sets. The first boundary condition set established base flow conditions for the model. The 76 second boundary condition set modeled the 25-yr storm event for the Mill Creek Watershed. In essence, the first set was a steady-state solution of the unsteady algorithm, establishing mathematically stable initial conditions for the second boundary condition set. 6.3.1 Simulating Base Flow Conditions The first boundary file created a hotstart file (as explained in Chapter 4) for the flow model, establishing base flow conditions. The first MIKE 11 boundary file was Bnd1.bnd11. The time-series boundary conditions for Bnd1.bnd11 consisted of the upstream base flow conditions for Mill Creek and East Fork, and the downstream stage height conditions for Mill Creek. The Mill Creek stage height was set to 169.3 meters. The base flow conditions were run for a 10-day period using a 10-minute time step. The simulation was saved as pdc1hotstart.sim11, and was used as the initial conditions for the second set of boundary conditions. 6.3.2 Incorporating Hydrologic Data as Boundary Conditions The second set of boundary conditions simulated the runoff effects on the PDC study area for the 25-year storm event. The upstream, downstream, and lateral boundary conditions were obtained from the HEC HMS hydrologic model of the Mill Creek Watershed. The hydrologic data used is shown in Appendix E. The time- series data could not be exported directly from the HEC HMS model for use in the MIKE 11 model. The upstream and lateral boundaries defined as runoff and flow hydrographs from the hydrologic model were converted to an Adobe Acrobat file as explained in Chapter 3. From the Acrobat file, the data was copied into the MIKE 11 time-series file editor. The time step used in the HEC HMS model was 15-minutes, and the same time step was used for the runoff hydrograph inflows in the MIKE 11 77 model. Figure 6-5. A MIKE 11 time-series file extracted from the HEC HMS hydrologic model. The time step used is 15-minutes. The Chainage location for each lateral inflow hydrograph was determined by importing the HEC HMS model schematic into the MIKE 11 river network file. By overlapping the network file on top of the watershed schematic, the Chainage location of each watershed outlet was determined and established as a lateral boundary condition in the MIKE 11 boundary file. 78 Figure 6-6. The Mill Creek HEC HMS schematic imported as a background image into the MIKE 11 river network file. The schematic was used to identify Chainage values at watershed outlets. The downstream boundary condition, a time-series stage hydrograph, was not available. Successive runs of the model at different steady-state flows were used to determine the downstream hydrograph. The stage height values were interpolated for intermediate time steps. Further modifications of the stage hydrograph were required to fit the stage height corresponding to the inflow, by viewing the longitudinal profile results in MIKE View. Since the PDC study area was a smaller section of the initial study area, upstream and downstream boundary conditions were extracted from the results of previous models. Previous model simulation results used a 4-minute time step, thus the time-series data was set to a 4-minute time step as well. The difference in time steps for the upstream and downstream boundaries as compared to the lateral boundaries did not affect the MIKE 11 model results. 79 Figure 6-7. A MIKE 11 boundary file. The boundary file connects the upstream, downstream, and lateral inflow hydrographs to Chainage values along the network. Setting the hotstart file as the initial condition and the time-series runoff and flow hydrographs from the HEC HMS model as boundary conditions, the MIKE 11 model was run using a 4-minute time step over a 31-hour time range. Results of the model were observed in MIKE View for any necessary editing. Using the longitudinal profile in MIKE View for stage height and discharge, time-series changes transitioned smoothly between time steps. Some random fluctuation in stream flow was observed at the East Fork tributary. Additional cross-sections were interpolated there to provide less severe jumps in streambed elevations. This alleviated some of the stage height fluctuation at that location. 80 Figure 6-8. A profile of Mill Creek in the PDC study area. The red dotted line denotes maximum stage height; the green dotted line denotes base flow. Initially, stage fluctuation occurred at the East Fork tributary (Chainage #16401). 6.4 Post Processing in MIKE 11 GIS Once the MIKE 11 model of the Mill Creek PDC was run simulating the 25-yr storm event (April 1998 storm), the data was imported into Arcview GIS for flood visualization purposes. The MIKE 11 model accomplished this by linking the unsteady flow results with the terrain model through the Branch Route System, which is the MIKE 11 river network file. The MIKE 11 river network file linked the MIKE 11 simulation data (saved as pdc1.msd) to corresponding XY-coordinate locations on the terrain model. 6.4.1 Geo-referencing the Stream Network to the Terrain Model Since the MIKE 11 river network file was initially created from the terrain model, the network was already geo-referenced, making the link between the unsteady flow simulation and Arcview GIS effortless. When opening the MIKE 11 GIS Flood Management Tool, the interface automatically asked the user for the MIKE 11 river network file and the MIKE 11 simulation data results. 81 Figure 6-9. The MIKE 11 flow model inputs for MIKE 11 GIS: the river network file and the simulation data. 6.4.2 Importing Q and h Data into MIKE 11 GIS The Q- and h-points were imported into the Arcview GIS interface from the MIKE 11 network file data. The Q-points are average flows at the midpoint of each finite segment within the model (half the distance between successive cross-sections). The h-points are stage heights at upstream and downstream finite segment boundaries (cross-section locations). The simulation data (pdc1.msd) was spatially imported to each corresponding Q- or h-point along the stream network, using the Chainage values for geo-referencing. The result was the creation of two point themes in Arcview GIS, Qpoints.txt and Hpoints.txt. 82 Figure 6-10. Q-points and h-points imported into MIKE 11 GIS. Q-points are located between two corresponding cross-sections; h-points are located at each cross-section. The Hpoints.txt theme is the required MIKE 11 flow model data for flood delineation. MIKE 11 GIS linked the pdc1.msd data to the corresponding record in the Hpoints.txt theme?s attribute table. As shown in Figure 6-11, water surface elevations for cross-section at each time step from the MIKE 11 flow model were imported into the Hpoints.txt attribute table. 83 Figure 6-11. MIKE 11 flow model results were imported into the Hpoints.txt attribute table. Water surface elevations at each cross-section are represented for each time step. 6.4.3 Generating Flood Maps and Animations from the Unsteady Flow Model Using the Hpoints.txt data, flood maps were developed in MIKE 11 GIS for user-specified time steps. A water level surface grid was interpolated using inverse distance-weighted interpolation of the nearest h-points. The difference between the water level surface grid and the terrain model grid created flood maps. Figure 6-12 shows the water surface elevation at 10:00 am on April 16, 1998. 84 Figure 6-12. Flood map of the Mill Creek PDC developed from MIKE 11 model data. 3-D animations and ?fly-bys? were also developed in MIKE 11 GIS. Buildings were added to the animations for reference purposes. An advantage to using MIKE 11 GIS for flood visualization is the simplicity of low memory, grid-based models for processing. The major disadvantage is that the 2-D and 3-D grid-based images depict a rough edge where the water surface is delineated from the terrain model. 85 Figure 6-13. Snapshot from a MIKE 11 ?Flyby? animation. Notice the rough edge where the water surface is delineated from the terrain. Figure 6-14. 3-D animation of the Mill Creek PDC with buildings. The image shows the peak stage height for the 25-yr storm event. 86 Chapter 7: Application of the HEC RAS Model The four steps to flood visualization using the HEC RAS flow model and the HEC GeoRAS extension were 1) extraction of the stream geometry data from the modified terrain model for use in the HEC RAS unsteady flow model, 2) processing the geometry data in HEC RAS, 3) integration of hydrologic data as initial conditions and boundary conditions in the HEC RAS unsteady flow data file, and 4) post- processing (i.e. flood visualization) of HEC RAS model results in Arcview GIS. Unlike the MIKE 11 model, the stream geometry was extracted from the terrain model and incorporated into the unsteady flow model, maintaining spatial referencing between the model and the Arcview GIS environment. Flood delineation with the terrain model was limited by the bounding polygon created by HEC GeoRAS pre- processing, which required several iterations of the stream geometry extraction to attain an optimum solution. 7.1 Extracting Stream Geometry from the Terrain Model Geometry data extracted from the modified terrain model is similar to having a ?virtual? surveying team on the surface of the terrain model. The modeler identifies what stream data is needed, and the HEC GeoRAS extension extracts the data from user-defined locations on the terrain model. The data locations required are the stream?s centerline, stream banks, stream cross-sections, stream channel flow path, and flood plain flow paths. To assist in the process, digital orthographic photo images or USGS quadrangle sheets can assist the modeler when defining the stream geometry with respect to the terrain model. For this study, the TIN-based terrain model was used to differentiate stream banks from the rest of the terrain. The stream centerline was already defined, using the stream1.shp theme. An iterative process was used to define flood plain 87 flow paths and the extent of cross-sections. Importing the geometry data into HEC RAS, running a simulation, and then viewing the results in Arcview GIS using the postRAS menu accomplished this process. If the cross-sections limited the extent of the flooding, then the cross-sections were extended and the process was repeated. After six iterations, the optimum results were developed. 7.1.1 Developing the Stream Centerline and Main Channel Banks The stream centerline theme was copied from the previously developed stream1.shp theme. The stream centerline theme was saved as Pdcstream.shp. Using the River ID tool, each section of the stream centerline was defined with a Stream_ID and Reach_ID. Based on the terrain data, lengths of each section in the stream centerline were calculated. Results from using the River_ID tool are shown in Table 7-1. The Nodes shown in the table are defined accordingly: Node #1 ? upstream boundary of East Fork, Node #2 ? East Fork tributary connection with Mill Creek, Node #3 ? upstream boundary of Mill Creek, and Node #4 ? downstream boundary of Mill Creek. Table 7-1. River ID data for each reach in the PDC stream network. Stream_ID Reach_ID From Node To Node Length (ft) From RS# To RS# Eastfk Eastfk 1 2 1217.381 1217.381 0.0 Millcrk MillcrkUS 3 2 1029.274 5190.737 4161.464 Millcrk MillcrkDS 2 4 4161.464 4161.464 0.0 The main channel banks were digitized based on the terrain model. Differences in slope found in the TIN mesh were identified and used to distinguish the extent of the stream banks. Once the digitizing was complete for both the Mill Creek and East 88 Fork stream banks, the theme was saved as Pdcbanks.shp. Any significant irregularities with defining the main channel banks were adjusted in HEC RAS by redefining the boundary between the flood plains and the stream channel. Figure 7-1. Stream centerline and main channel banks defined for East Fork on the TIN-based terrain model. Changes in the TIN mesh?s slope assisted with digitizing the main channel banks. 7.1.2 Developing Cross-section Cut Lines and Flow Paths The cross-section cut line locations in HEC GeoRAS were initially established as the cross-section locations defined in the HEC-2 files. Through an iterative process, it was determined that the HEC- 2 cross-section locations limited the extent of the flood plain and required to be extended well beyond the initial surveyed cross- section extents. To also minimize overlapping of cross-sections, the cross-section cut lines were shifted to different locations along the stream network. The cross-section cut lines theme was called Xscutlines.shp. 89 Figure 7-2. The HEC-2 cross-sections (blue) and the GeoRAS cross-section cut lines (green, with arrows) shown along the stream network in the terrain model. The cross-section cut lines were extended beyond the extent of the flood plain and shifted to prevent cross-section overlap. Flow paths were defined for the stream centerline, and the left and right flood plains. Flow paths were used in HEC RAS to determine downstream reach lengths. Using the Label flowpaths tool, the flow path for the stream centerline was identified as Channel, the left flood plain as Left, and the right flood plain as Right. The flow path theme was called Pdcflowpath.shp. 90 Figure 7-3. Flow paths (shown in blue), channel banks, and cross-section cut lines defined with respect to the PDC terrain model. 7.1.3 Generating the RAS GIS Import File from Terrain Data HEC GeoRAS extracts 3-D features from the terrain model corresponding to the stream centerline, main channel banks, cross-section cut lines, and flow path themes. The digitized themes were selected for input into the HEC GeoRAS pre-processing. Each digitized theme was identified in the Theme setup menu. As shown in Figure 7- 4, there was no Land use theme identified for this study. The land use theme is an optional step in the GeoRAS pre-processing which allows the modeler to extract Manning?s n values based on a spatial land use corresponding to the terrain model. For this study, the Manning?s resistance factors were inputted into the HEC RAS geometry file manually. 91 Figure 7-4. Theme setup menu for GeoRAS pre-processing. The intermediate data shown in Figure 7-4, the Stream Centerline (3D) and the XS Surface Line (3D), was created during the HEC GeoRAS pre-processing. The 3-D themes created from the pre-processing were called Pdcstream3D1.shp and Xscutlines3D1.shp, respectively. Once the pre-processing was completed, the RAS GIS Import file (defined as pdcinput.geo) was processed and imported into HEC RAS. The import file developed was a text file containing the pertinent geometry data for use in the HEC RAS unsteady flow model. 7.2 Geometric Processing Once the geometry data from HEC GeoRAS was imported into the HEC RAS geometry data editor, two additional edits were required to further refine the geometry data. Each cross-section?s bank station locations required verification and 92 bed resistance factors required input into the model. Bank stations may have not been placed correctly in each cross-section from the digitized main channel banks using HEC GeoRAS. In such cases, the bank stations were adjusted to best define the stream channel for each cross-section. As shown in Figure 7-5, the right bank station was shifted up and to the right to the best location defining the natural stream channel in the cross-section. Figure 7-5. The right bank location shown was shifted up and to the right to depicting the most natural transition from flood plain to streambed. 7.2.1 Import GIS Stream Geometry Data The data extracted from the HEC GeoRAS pre-processing was imported into the HEC RAS geometry data editor. Under the Import Geometry data command in the HEC RAS geometry data editor, the GIS Format option was chosen and the pdcinput1.geo file was highlighted. The schematic of the imported geometry data is 93 shown in Figure 7-6. Since the geometry data was extracted in unit of meters, the River Stationing was also in meters. HEC GeoRAS automatically determined the River Stationing, thus there was no correlation with the previous HEC-2 River Stations. Figure 7-6. The HEC RAS geometry data schematic of the GIS imported data. The numbers are the River Stations for each cross-section. 7.2.2 Bed Resistance Factors Bed resistance factors in HEC RAS are inputted for each cross-section in the geometry data editor. Since the Manning resistance factors were not imported from the RAS GIS import file, the Manning?s n values were manually inputted for each cross-section, using the data included in the HEC-2 files. The Manning?s n values stayed constant for the streambed and flood plains for each reach in the stream 94 network, thus no interpolation of resistance factors at any cross-section was required. 7.3 Development of Unsteady Flow Initial Conditions and Boundary Conditions Initial conditions and boundary conditions for the HEC RAS model were extracted from flow, stage, and/or hydrologic time-series data corresponding to the specific model area. For the unsteady flow model, the time-series data is inputted into the Unsteady Flow Data editor. The data inputted into the editor are Initial Conditions and Boundary Conditions. 7.3.1 Establishing Initial Conditions as Base Flow The initial flow conditions were inputted into the Unsteady Flow Data editor using the base flow conditions for Mill Creek and East Fork. For continuity purposes, the initial flow for the Mill Creek reach downstream of the East Fork tributary was 2.43 m 3 /s, the sum of the two upstream base flows (as shown in Figure 7-7). Figure 7-7. Initial flow conditions used for the HEC RAS model, in m 3 /s. 7.3.2 Boundary Conditions Derived from the Hydrologic Data 95 The boundary conditions were obtained from the HEC HMS model of the Mill Creek Watershed. The HEC RAS model linked with the HEC HMS model results saved in a DSS file. The HEC RAS model interface extracted pertinent time-series data from the specified DSS file. The HEC HMS model interface automatically saved the results as a DSS file called MllCreek_CSO.dss. Unlike the MIKE 11 model, where lateral inflows (at watershed outlets) can be entered at any location along the stream network, lateral inflows in the HEC RAS model can only be entered at a cross-section location. Thus, the runoff hydrographs at the watershed outlets were connected to the nearest downstream cross-section along the stream network. 7.3.2.1 Corresponding Stream Flow and Runoff Hydrographs Since the MIKE 11 model size was decreased from previously developed flow models, the upstream and downstream flow and stage hydrographs were copied from the previous models into the current HEC RAS model. All watershed hydrographs were extracted from the HEC HMS model via the DSS utility. One watershed outlet along the HEC RAS model included the inflow from five watersheds, so the hydrologic data was imported from the DSS file as an Outflow hydrograph at Junction #23 in the HEC HMS model. Table 7-2 shows the source of the hydrograph data used for the HEC RAS model, along with the watershed outlet referencing that corresponded with the MIKE 11 model. 96 Table 7-2. Hydrograph sources for the HEC RAS model Description River Station (m) Corresponding MIKE 11 Chainage (m) Data Source Mill Creek Upstream Boundary 5179.47 15407.15 MIKE 11 model Basin 109 runoff 4822.088 15829.00 DSS file Basin 115 runoff 525.691 20000.00 DSS file Basin 110 runoff 4043.303 16443.00 DSS file Basin 111 runoff 4577.873 15850.00 DSS file Basins 112 thru 117 runoff (Junction #23 outflow) 336.56 20248.00 DSS file Downstream Boundary 18.83 20732.45 MIKE 11 model East Fork Upstream Boundary 1173.84 11427.12 MIKE 11 model 7.3.2.2 Extracting Hydrographs using the DSS Utility When defining a boundary condition hydrograph, the time-series data can either be entered directly into the editor, or read from a DSS file. The DSS file data was imported into the HEC RAS model by defining the boundary condition as Lateral Inflow in the Unsteady Flow Data editor. Highlighting the Read from DSS file option, the HEC HMS Mllcreek_CSO.dss file was opened. From the DSS file, the hydrograph pertaining to the watershed outlet in the HEC RAS stream network was highlighted, making the connection between the HEC RAS model and the HEC HMS hydrograph data. An example of the DSS connection is shown in Figure 7-8. The figure depicts the connection with the Flow hydrograph for Basin #109, with a 15- minute time step, for Run #16 of the HEC HMS model. The DSS utility imported the 97 hydrograph into the HEC RAS model for River Station #4722.088. From the DSS Path window, the hydrograph was graphically plotted to ensure the correct data was extracted from the HEC HMS model. Figure 7-8. The DSS Path window in HEC RAS. The window imports hydrograph data from a HEC HMS DSS file into the HEC RAS Unsteady Flow Data file. 7.4 Unsteady Flow Simulations in HEC RAS The simulation plan for the HEC RAS model was the same as for the MIKE 11 model. The plan is shown in Figure 7-9. Using a 4-minute time step, the range of the simulation ran from 12:00 pm on April 15, 1998 to 7:00 pm on April 16, 1998 (31 hour time duration). The hydrograph output interval was set to 30-minutes to decrease the overall processing time. 98 Figure 7-9. The HEC RAS Unsteady Flow Analysis plan shown for the Mill Creek PDC model. The simulation results were graphically displayed a number of ways in the HEC RAS user interface. Simulations were displayed as longitudinal profiles, X-Y-Z perspective plots, and as cross-section profiles. As previously discussed, the geometry extraction process was repeated numerous times until the optimum simulation results were obtained. If the extent of the cross-sections limited the extent of flooding in the HEC RAS model, the process was repeated. Fortunately, additional editing of the flow data was not required. 99 Figure 7-10. The X-Y-Z Perspective Plot in HEC RAS. The water level shown is the maximum water surface elevation for the PDC area from the 25- year storm event. 7.5 Post Processing in HEC GeoRAS Once the optimum simulation was obtained, the data from the simulation was ready for exporting into Arcview GIS for flood visualization. This was accomplished through the HEC GeoRAS post-RAS menu. Water surface elevation data created from the HEC RAS model was connected to each corresponding cross-section location for each time step. Since the cross-section and stream channel was created from the HEC GeoRAS pre-processor, the unsteady flow data was already geo- referenced to the modified terrain model. 7.5.1 Read RAS GIS Export File 100 Once the simulation was complete, the unsteady flow data was exported into Arcview GIS. Time steps from the simulation data were selected for exporting. The HEC GeoRAS Theme Setup command in the postRAS menu defined the GIS export file created from the HEC RAS model, the modified terrain model, the output directory, and the rasterization cell size used for post-processing. As shown in Figure 7-11, the cell size of 5 was selected, thus the grid-based water surface output had 5-m by 5-m grid cell sizes. Once the RAS GIS export file was inputted into GeoRAS, delineation of the water surfaces with the terrain model was the next step. Figure 7-11. For HEC GeoRAS post-processing, the inputs for Arcview GIS were defined. 7.5.2 Water Surface TIN Generation To accomplish water surface delineation, the shape themes depicting each water surface required conversion to a TIN-based surface. A TIN-based surface was created by interpolating elevations between cross-sections, based on the imported water surface elevations along each cross-section?s length. The result was a 3-D, TIN-based surface depicting the water surface at the time step defined in HEC RAS. 101 Figure 7-12. The water surface TIN created from HEC RAS input overlapping the terrain model of the PDC study area. The TIN-based water surface still required three-dimensional delineation with the terrain model surface to create flood visualization. The view shown in Figure 7- 12 shows the overlapping of the two TIN-based surfaces. Notice how the cross- sections act as boundaries for the water surface. The subsequent step develops the flood plain. 7.5.3 Delineating Flood Plains from Unsteady Flow Model Results Once the water surface was created, the flood plain was delineated from the terrain model in the next step. In the two-dimensional plane, the delineation resulted in grid-based themes and shape themes depicting the water surface. The grid-based theme showed the spatial difference in water depth with respect to the terrain model, as shown in Figure 7-13 of the maximum water surface. 102 Figure 7-13. Maximum water surface for the April 1998 flood delineated from the terrain model. Using the delineated shape theme, editing can be accomplished in Arcview GIS to remove water pits or ponds, which can be seen in Figure 7-13. Obviously such editing would not change the overall model, to do so would require either modifications to the cross-sections using the GeoRAS pre-processor, or the establishment of ineffective flow areas for specific cross-sections in the HEC RAS geometry data. Delineation of the TIN-based water surface from the terrain model was also observed using the 3D Scene from the Arcview GIS 3D Analyst extension. The 3D Scene showed the three-dimensional attributes of the Arcview GIS themes in a three dimensional plane. Figure 7-14 displays the delineation of the water surface profile from the terrain model. The entire water surface TIN actually exists in the 3-D view, where the water surface elevations less than the terrain elevation fall underneath the terrain surface and cannot be observed from a perspective above the terrain. 103 Figure 7-14. Three-dimensional representation of the TIN-based terrain model and water surface using 3D Analyst. A significant difference when viewing the results of the HEC GeoRAS interface versus MIKE 11 GIS is along the lines of water surface delineation, which is clearly better defined in HEC GeoRAS. As shown in Figure 7-15, there is a clearer distinction of where the water intersects the terrain, creating better graphical representations of flood delineation. 104 Figure 7-15. The view shows the distinction between water and terrain using TIN-based surfaces in HEC GeoRAS. The maximum water surface elevation developed from the HEC RAS model of the PDC study area is shown. 105 Chapter 8: Results and Conclusions This chapter discusses the overall results of the research and the conclusions leading from the application of the two unsteady flow models. The analysis focuses on the applicability of the unsteady models and their connectivity with the spatial GIS environment. 8.1 Model Results The limited number of gage stations in the Mill Creek watershed (one existing station for the entire watershed) led to both flow models not being properly calibrated. The accuracy of each model could not be validated. Without the model validation, this study?s results can be analyzed qualitatively to assess the efficiency of flood modeling technologies. The significance of flood visualization is the ability to portray a model?s results to community members, planners, and officials in a way that is understandable to everyone. Unlike the steady flow models, the unsteady flow models can portray the effects of flood duration, which also have an important role in flood prevention planning. The model results section of this chapter summarizes the results of the models used in the study, and compare the results to steady flow modeling. 8.1.1 MIKE 11 Model Results Importing water surface elevations derived from the MIKE 11 model into Arcview GIS was accomplished effortlessly since the stream network was accurately geo-referenced to the terrain model. The flood delineation process was faster using MIKE 11 GIS than using the HEC GeoRAS extension. The MIKE 11 GIS delineation process finds the difference between the water surface elevation and the ground elevation for each grid cell in the model. The delineation is accomplished 106 using inverse distance-weighted interpolation from known water surface points (known as h-points) located at the center of each cross-section along the stream network, whereas the TIN-based delineation (used for the HEC RAS model) interpolates using 3-D water surface lines along the extent of each cross-section. One would presume that the HEC GeoRAS interpolation method would achieve more accurate results, because the flood plain was delineated using two surfaces (the terrain model and water surface TIN coverages) instead of by interpolation based on one h- point elevation value at each cross-section, as in the case for MIKE 11 GIS. Surveyed data is the most accurate stream geometry data source. Using surveyed cross-section data in the flow model removes the iterative stream geometry extraction process required for the HEC RAS model. Unfortunately, the HEC-2 surveyed data did not cover the entire flood plain. An example is shown in Figure 8- 1. The maximum water stage heights for the 25-yr storm event were well above the stream banks, and in some cases extended beyond the flood plains as well. Figure 8-1. The horizontal, red dotted line above the cross-section at Chainage 19.998 is the maximum water surface at that location for the MIKE 11 model. In this case, the model does not account for the total conveyance in the flood plains. 107 Since the extent of the surveyed cross-sections was limited, the MIKE 11 model?s flow characteristics did not account for the entire flood plain resistance or flood conveyance that actually occurs. This resulted in higher maximum water surface elevations and shorter flood durations than for the HEC RAS model. To improve the MIKE 11 model, the stream geometry data could be extracted from the terrain model, as was accomplished with the HEC RAS model. Another option is to re-survey the cross-sections to expand the left and right flood plains for each cross- section. Obviously the second option would be a more costly alternative. An issue with the MIKE 11 model is the use of grid-based coverages (terrain model and water surface) in MIKE 11 GIS. An advantage to the grid-based method is it minimizes the use of computer memory and processing. The limitation to grid- based models, especially for smaller study areas, is the intersection of the terrain model and water surface coverages does not accurately represent flood delineation as well as using TIN-based coverages (this is discussed in Chapters 6 and 7). Based on this study, the MIKE 11 GIS post-processing tool (known as the Flood Management tool) is not the optimum choice for a study area with the size of the Primary Damage Center, which has an area of approximately 13.5 km 2 (5 km in length by 2.7 km in width). The MIKE 11 GIS post-processing tool would provide better images of flood delineation for study areas larger than the Primary Damage Center, where resolution becomes less important as area increases. An advantage of the MIKE 11 model is its graphical user interface. Editing data is simple and easy to accomplish. The interface provides graphical representations for the geometric data and the time-series boundary conditions. Instead of creating a separate GIS export file for the MIKE 11 GIS post-processor, the interface automatically connects the GIS spatial data to the hydraulic model results. This is accomplished by the interconnectivity of the river network file to the flow model and the terrain model. As long as the XY-coordinates of the MIKE 11 river network file 108 correspond to the terrain model coordinates, the flow data is easily imported and delineated. Once the flow model results are imported into MIKE 11 GIS, the user effortlessly develops 2-D and 3-D flood map animations directly from Arcview GIS. The process eliminates the need to obtain screen captured images and subsequently copy them into an external animation software tool to accomplish the task as required by HEC GeoRAS. 8.1.2 HEC RAS Model Results The HEC RAS model?s stream geometry data is extracted from the terrain using the HEC GeoRAS extension. This difference in the two modeling methods is significant to flood visualization results. Unlike the MIKE 11 model, the stream cross-sections were extended beyond the extent of overbank flows, ensuring the flood plain?s bed resistance covered the entire flow in the model. Unlike the HEC RAS model, the overall flood plain conveyance is not accounted for in the MIKE 11 model results. The HEC RAS model?s overall flooding extent was less than what was found in the MIKE 11 model. Lower maximum water surface elevations and longer flood durations as compared to the MIKE 11 model were also observed. A significant difference in flood visualization for the two models was also noticed. The TIN-based delineation method creates a more realistic delineation of flood levels from the terrain model. The TIN-based delineation works well for smaller study areas because of its high resolution, but can become cumbersome as the study area increases. The initial TIN-based terrain model of the Primary Damage Center (Crtin1) developed from the 1-ft contour data was cumbersome to use, because its TIN mesh consisted of 6,028,127 triangles (240 MB of computer memory capacity). Loading the Crtin1 file into an Arcview GIS view takes 3-5 minutes to accomplish. Using 2-ft contours to develop the terrain model (Nwtin1) resulted in the 109 new model loading quicker (less than 10 seconds) than the initial terrain model because the TIN mesh consists of 134,470 triangles (4.39 MB of computer memory capacity) ? a significant decrease in computer memory and processing requirements. The water surface TIN developed in HEC GeoRAS was not an issue regarding computer memory and processing, since the TIN mesh contained around 500 triangles for each water surface developed. Obviously the processing is dependent on the data sources used to develop the terrain model, computer speed and capacity, and what accuracy the modeler expects for his or her results. A limitation to the HEC GeoRAS model is the requirement to pre-process, or extract, stream geometry data from the terrain model to develop flood visualization images. There is no certainty that independent stream cross-sections can perfectly fit a terrain model accurately. If some or all of the cross-sections can be accurately geo- referenced to the terrain model, then the option to extract or not extract cross-sections from the terrain should be provided to the modeler. For flood visualization, an accurate depiction of the stream channel is of greater importance for the hydraulic model than for the terrain model. Most flood event models focus on the flow above the stream channel, so if the hydraulic model contains the best geometric data of the stream and flood plains, and the terrain model contains the best ground surface elevation beyond the stream channel, then the visualization tool should be valid. But when using HEC GeoRAS, pre-processing is necessary because the stream geometry data used in HEC RAS can only be extracted from the terrain model for ultimately developing flood maps in the HEC GeoRAS post-processor. The HEC GeoRAS interface should provide the pre-processing step as an option, not a requirement, to its users. Some difficulties lie in importing GIS data from the terrain model into the HEC RAS geometry data editor. When data is unavailable, the HEC GeoRAS iterative process can derive cross-sections for a stream network from a terrain model in an area 110 that has no cross-section data available. Sometimes the data exported into HEC RAS does not always import accurately. This occurs near junction locations (where tributaries connect with the main stream in the stream network). For this study, cross- section directions were occasionally reversed near junctions when imported from HEC GeoRAS preprocessor into the HEC RAS geometry data editor, not allowing the HEC RAS unsteady flow option to run properly. An example is shown in Figure 8-2. When this problem arises, the direction of the cross-section cut lines in the HEC GeoRAS pre-processor can first be verified and flipped as necessary, using the Flip Polyline command. If that is not the problem, then the cross-section?s direction can be reversed in the geometry data editor in the HEC RAS interface, using the Move Object command. Figure 8-2. An example of a reversed cross-section shown in an XYZ plot in HEC RAS. Importing GIS data from HEC GeoRAS will occasionally reverse cross-section orders near junctions. 111 An advantage to using the HEC GeoRAS post-processing for flood delineation is the development of high resolution images for small areas (like the PDC study area). The TIN-based delineation method creates clearer flood map images as compared to the MIKE 11 grid-based delineation method. A disadvantage to the TIN-based method is the increase in computer processing time and computer memory requirements. Flood delineation in the HEC GeoRAS post-processor is simple, but animation processing is tedious. When reading a GIS export file created from the HEC RAS model results, the HEC GeoRAS post-processor truncates the name of the data file for each time step. When this occurs, the water surfaces created for the different time steps cannot be differentiated by the computer, as shown in Figure 8-3. To resolve this problem, water surface profiles for individual time steps were imported as separate GIS export files into HEC GeoRAS. This procedure required numerous GIS export file development iterations from the HEC RAS interface. Once accomplished, each time step was copied with a screen captured image and pasted into an animation software tool to develop an animated GIF of the flood event. 112 Figure 8-3. The Arcview GIS view shows the polygon themes (called ?Bpw16apr199.shp?) in the legend imported from the HEC RAS flow model for different time steps. Each polygon theme was imported with the same name, thus Arcview GIS could not differentiate between the different time steps. 8.1.3 Comparison of the Unsteady Flow Model Results As previously discussed, a significant difference occurred with maximum flood stage, time of peak stage, and flood duration for the two flow models. The time of the peak stage differed by 3 hours, occurring at 08:32 am for the MIKE 11 model and 11:00 am for the HEC RAS model. The HEC RAS model?s flow attenuated more rapidly, with a lower maximum stage height and a longer flood duration. The MIKE 11 model did not attenuate as quickly, resulting in a higher maximum stage height and shorter flood duration. 113 (a) (b) Figure 8-4. A visual comparison is shown of the maximum stage heights for (a) the MIKE 11 model and (b) the HEC RAS model. Extracting the stream geometry data from the terrain model for the HEC RAS model initially did not seem important, since overbank flow is usually the focus for flood analysis. But the survey cross-section data did not accommodate the extent of inundation in the flood plains. An example of the difference in the HEC RAS and MIKE 11 model cross-sections are shown in Figure 8-4. Adding the flood plain extents to the HEC RAS model affected the model results in three ways: 1) maximum stage was reduced, 2) flood duration increased, and 3) the time of peak stage was delayed. The factor causing the changes to the two models is the inclusion of the flood plain conveyance to the overall flow. Since the flood plains are limited in the MIKE 11 model, the results are a higher maximum stage, a more rapid time of peak, 114 and a shorter flood duration. Comparison of HEC RAS and MIKE 11 Cross-sections 170 172 174 176 178 180 182 0 500 1000 1500 x (m) z (m) RS 3443.06 Chainage 17276 MIKE 11 WSE HEC RAS WSE Figure 8-5. The MIKE 11 (in dark blue) and HEC RAS (in red) cross- sections shown are approximately 12 meters from each other along the stream network. The total flood plain conveyance is accounted for in the HEC RAS model, significantly slowing down flow as compared to the MIKE 11 model results. The figure also depicts the maximum water surface elevations for the MIKE 11 (dashed line) and HEC RAS (dotted line) models, which are affected by the flood plain conveyance included or not included in the model(s). 8.1.4 Comparison to Steady Flow Modeling An additional analysis of the study area was conducted using the HEC RAS steady-state model to compare steady flow modeling to unsteady flow modeling. When using a steady flow model, most modelers consider the peak runoff flows at the boundary conditions for a specified storm event, resulting in water stage height being significantly higher than one for the unsteady flow model. This occurs because the steady flow model does not account for the timing differences in the runoff hydrograph rainfall responses into the system, the differences being depicted in Table 8-1. Figure 8-6 is provided to understand the relation of the contributing runoff from 115 the watersheds. Using the peak runoff flows for storm events in a steady flow model will result in over design. Figure 8-6. Schematic of the watersheds contributing runoff to the Primary Damage Center. The extent of the hydraulically modeled stream system is bolded in blue. Any upstream watersheds contributing flow into this portion of the streams is accounted for in the upstream boundaries. 116 Table 8-1. Time of peaks for the PDC study area boundary conditions. Boundary Condition Peak Value Time of Peak Mill Creek Upstream flow boundary 97.069 m 3 /s 08:56 am Basin 109 runoff 32.505 m 3 /s 08:00 am Basin 110 runoff 6.236 m 3 /s 07:45 am Basin 111 runoff 26.565 m 3 /s 07:45 am Basin 115 runoff 43.274 m 3 /s 08:15 am Basins 112-117 runoff 34.615 m 3 /s 06:45 am Downstream stage boundary 174.24 m 08:32 am East Fork Upstream flow boundary 53.347 m 3 /s 07:45 am HEC RAS Unsteady Flow Model 11:00 am MIKE 11 Unsteady Flow Model 08:32 am A comparison of the maximum stage height of the steady and unsteady HEC RAS flow models is shown in Figure 8-7. Based on this comparison, the unsteady flow model provides two significant points to consider for future design and modeling. For most cases, the unsteady flow model will provide a maximum water stage height less than the stage height found from the steady flow model since most steady flow models consider the peak discharges as occurring simultaneously everywhere, which may not peak at the same time. Secondly, the unsteady flow model also considers flood duration as a factor in flood analysis. Real property can significantly be affected by the difference in time of inundation. 117 Figure 8-7. Comparison of maximum water surfaces for the HEC RAS unsteady flow model (on the left) and the steady model (on the right) for the 25-yr storm event. Because of timing differences in peak flows, the steady flow results show a greater portion of inundation for the PDC study area. 8.2 Conclusions Using unsteady flow models to develop flood visualizations is complicated and lengthy, depending on the size of the study area. Many factors can affect the results, especially if the data sources are inaccurate or incomplete. The amount of stream geometry data can become very substantial as the size of the stream network increases. It is best to choose a modeling method that best accommodates the processing of the geometry data. Many factors become problematic in the model developing process for unsteady flow models that are not an issue for steady flow models. The best approach is to initially gain an understanding of how the unsteady flow algorithm(s) work, and obtain some experience working with existing unsteady flow models. For this study, development of the MIKE 11 model was the initial focus. After approximately six months of HEC-2 and HEC HMS data conversions, understanding the nuances of unsteady flow, and resolving errors with the flow simulation, a MIKE 11 hydraulic model was developed for approximately 17.3 kilometers of Mill Creek, with two 118 branching streams. The HEC RAS model was easier to develop, since the unsteady flow learning curve was minimized during the MIKE 11 model development, and the HEC-2 and HEC HMS data was easier to incorporate into the HEC RAS model. A model similar to the MIKE 11 model using the HEC RAS interface was developed within two weeks. Once the terrain model was created, the process of developing flood maps with the MIKE 11 GIS and HEC GeoRAS extensions was simple. (a) (b) Figure 8-8. Schematics of the initial hydraulic models developed in (a) MIKE 11 and (b) HEC RAS. The initial models covered over 17.3 kilometers of Mill Creek as well as two additional branching streams. The unsteady flow algorithms are not as mathematically stable as steady flow models. When a water stage height is calculated at a value less than the streambed elevation, the flow simulation crashes. This calculation may be mathematically accurate. Natural systems do not always follow the rules of mathematics. In such 119 cases, additional cross-sections may be added to the model, which decreases the incremental step in the stage difference from element to element in the system. Another option is to decrease the model?s simulation time step, as was the case for this study. 10 and 30-minute time steps were initially used for both the MIKE 11 and HEC RAS models, leading to both models crashing. A 4-minute time step was the optimum time increment used for both models. The unsteady flow model has the powerful capability to model the characteristics of watershed runoff responses from a storm event over time. This makes flood animations more accurate than for those created from steady flow models. To minimize data processing, it is recommended to use an unsteady flow model that can import results from a linked hydrologic model. The process of importing the runoff hydrographs from the HEC HMS model into the HEC RAS model was simple because of the DSS utility. Exporting the HEC HMS model results into the MIKE 11 interface was not easy to accomplish. The Danish Hydraulic Institute has created a hydrologic model, called NAM, which the MIKE 11 model can be linked to. The final point to consider in unsteady flow model applications in Arcview GIS is the depiction of the flood delineated from the terrain model. A lot of research has been conducted on how to integrate separate data sources into one modified terrain model to show accurate flood maps and visualizations. Since flood visualization looks at flow over the stream bank, the concern should not be for the stream channel, but for what occurs in the flood plains. If the terrain data is accurate (as was the case for this study), then inclusion of surveyed stream geometry into the terrain model may not be necessary. As found within this study, the surveyed stream geometry data could not accommodate the flow derived from the 25-yr storm event, thus the terrain model was necessary for developing the stream geometry data, as in the case of the HEC RAS model. 120 8.2.1 Unsteady Flow Model Advantages and Limitations When applying the two methodologies of unsteady flow to the same study area, it was difficult to determine which model was more advantageous to use. Both methods use unsteady flow algorithms that are valid and widely accepted techniques used in the United States and abroad. This section summarizes the quality-based findings when using both modeling methodologies; most points being previously addressed in this report. The purpose of compiling the key points from this research is to provide future unsteady flow modeling a better approach to save on time and resources. The MIKE 11 Model Advantages ? The interface is easy to use. Editing is simple and easy to accomplish. ? The conversion of flood map to 2-D and 3-D animations in Arcview GIS requires no additional animation software. Limitations ? The software package is expensive, currently running approximately 6,000 U.S. dollars. ? The software is currently limited to using metric units. Chainage values can only be inputted in units of meters. ? The Grid-based surfaces used by MIKE 11 GIS depict a jagged flood plain boundary where the water stage is delineated from the terrain. Graphical images of smaller study areas, that require a higher resolution image, are affected more than larger study areas. ? The stream network referencing method for the MIKE 11 model starts from the most upstream location and increases as you move downstream (Chainage values). Not all upstream stream sources can easily be defined to begin at a specific location. 121 ? Since the MIKE 11 model is not yet widely used in the United States, current U.S. hydraulic model data are not easily imported into the interface. The HEC RAS Model Advantages ? The HEC RAS software is available to anyone over the internet. ? The River Station stream network referencing method accommodates both U.S. customary units and metric units. The referencing method starts from the most downstream location of the stream and increases as you move upstream, unlike the MIKE 11 model. This method is easier to define since the most downstream location of a stream is easy to spatially define. ? The HEC RAS model accommodates either U.S. customary units or metric units for all values defined in the model. ? Existing HEC-2, HEC RAS, and UNET flow model data are easily imported into the HEC RAS interface. ? The TIN-based surfaces used in the HEC GeoRAS post-processor depict more accurate looking flood delineations, regardless of study area size. Limitations ? The development of flood animations from HEC GeoRAS requires additional animation software. The process of obtaining screen captures and including the images into an animation software interface is tedious and time consuming. ? Modelers are forced to use the stream geometry data extraction pre- processing in HEC GeoRAS to ultimately use the post-processing visualization tools. Even when surveyed data is accurate and geo-referenced by the stream network, the geometry extraction from the terrain model is still required. 122 8.2.2 Future Work As for most flow visualization techniques, additional modifications to the existing model can still be improved upon for future studies. Adding the man-made structures within the study area into the terrain model would affect the overall results of the unsteady flow models. Azagra (1999) developed a method to include the buildings into a TIN-based terrain model. If using the HEC GeoRAS pre-processor, buildings and structures can be incorporated into the flow model?s geometric data. Another improvement to the current model is the inclusion of bridges and other hydraulic structures into the flow model. The PDC study area has eight bridges (roadway and railway bridges) that have not been added to the flow model. The integration of the bridges into the model would be simpler for HEC RAS since the bridge data can be obtained from HEC-2 files. Based on the modeled characteristics of the study area?s flood plains, adding bridges into the model would amplify flood inundation through backwater effects from piers and abutments. The bridges would require extensive analysis to determine an optimum modeling method for high (flow over the bridge?s roadway) or low (flow under the bridge?s roadway) bridge flows (Bonner, 2000). 123 Appendix A: MIKE 11 Chainage - HEC-2 River Station Conversions The cross-section data for this study was initially available as a HEC-2 geometry file. The file was imported into HEC RAS, and converted into a text file readable by the MIKE 11 software. Unfortunately, the river network referencing for HEC RAS and MIKE 11 required two conversions: 1) Movement of the initial point of reference from the most downstream location (HEC RAS) to the most upstream location (MIKE 11) 2) The conversion of units of feet (HEC-2 files) to units of meters (MIKE 11) This was accomplished by developing a spreadsheet for the conversion of the initial HEC-2 River Stations to MIKE 11 Chainages. The Chainage values in the MIKE 11 model were inputted manually from the spreadsheet results. MIKE 11 Chainages values were initially based on a stream network for the entire extent of Mill Creek. Table A-1. HEC-2 River Station conversion to MIKE 11 Chainages HEC-2 River Stations (ft) Downstream Length (ft) Downstream Length (m) MIKE 11 Chainages (m) Mill Creek 200332 292 89.00 15779 200040 1220 371.86 15496 198820 1130 344.42 15868 197690 960 292.61 16213 Interpolated Cross-section at the confluence of East Fork into Mill Creek 16401.453 196730 730.00 222.50 16505 196000 170.00 51.82 16728 195830 60.00 18.29 16780 124 HEC-2 River Stations (ft) Downstream Length (ft) Downstream Length (m) MIKE 11 Chainages (m) 195770 150.00 45.72 16798 195620 10.00 3.05 16844 195610 210.00 64.01 16847 195400 170.00 51.82 16911 195230 365.00 111.25 16962 194865 550.00 167.64 17074 194315 275.00 83.82 17241 194040 620.00 188.98 17325 193420 2320.00 707.14 17514 191100 200.00 60.96 18221 190900 1285.00 391.67 18282 189615 865.00 263.65 18674 188750 340.00 103.63 18938 188410 410.00 124.97 19041 188000 500.00 152.40 19166 187500 350.00 106.68 19319 187150 1290.00 393.19 19425 185860 590.00 179.83 19818 185270 230.00 70.10 19998 185040 500.00 152.40 20068 184540 610.00 185.93 20221 183930 220.00 67.06 20407 183710 15.00 4.57 20474 125 HEC-2 River Stations (ft) Downstream Length (ft) Downstream Length (m) MIKE 11 Chainages (m) 183695 95.00 28.96 20478 183600 20.00 6.10 20507 183580 320.00 97.54 20513 183260 925.00 281.94 20611 182335 0.00 0.00 20732.45 East Fork 1246.63 169.16 51.56 11296 1077.47 190.50 58.06 11465 886.97 185.93 56.67 11656 701.04 390.14 118.91 11842 310.90 310.90 94.76 12232 0.00 25.00 7.62 12543 -25.00 0.00 0.00 12550 126 Appendix B: Visual Fortran Program used for Cross-section Data Conversion Prepared by Stefan Szylkarski Danish Hydraulic Institute 11 October 1999 Content-Type: application/octet-stream; name="HEC2M11.for" Content-Transfer-Encoding: 7bit Content-Disposition: attachment; filename="HEC2M11.for" PROGRAM hec2m11 C ********************************************** C Program reads HEC-RASv2.1 GO1 files and extracts cross C section information and write to MIKE11 inport text file. C IMPORTANT:- Please check all cross sections converted. C Errors may occur as the program has not C been fully tested. C C Stefan Szylkarski - Danish Hydraulic Institute C - sps@dhi.dk 127 C - 11 October 1999 C ********************************************** CHARACTER*8 chain CHARACTER*50 fin,fut CHARACTER*80 line REAL*4 xz(20,10) INTEGER*2 npts c** Open Files WRITE(*,'('' HECRAS G01 File name? : ''\)') READ(*,'(A)') fin WRITE(*,'('' M11 Output file name? : ''\)') READ(*,'(A)') fut WRITE(*,'(/)') OPEN (UNIT=10, FILE=fin) OPEN (UNIT=20, FILE=fut) c********Search for Chainage Lines 128 10 CONTINUE READ (10,'(A80)',END=9000) line IF ( line(1:7) .EQ. 'Type RM' ) THEN 11 chain = line(28:35) 12 READ (10,'(A80)',END=9000) line c********Search for Station Elevation lists associated with chainage IF (line(1:9) .EQ. '#Sta/Elev' ) THEN READ(line(12:14),'(I3)') npts ELSEIF( line(1:7) .EQ. 'Type RM' ) THEN GOTO 11 ELSE GOTO 12 ENDIF ELSE GOTO 10 ENDIF c********Read up the cross section X,Z pairs 129 nrows = ANINT((REAL(npts) / 5.0 ) + 0.5) DO I = 1, nrows IF ( I.EQ.nrows) THEN nvals = (npts - (nrows-1)*5)*2 ELSE nvals = 10 ENDIF READ(10,*) (xz(i,j),j=1,nvals) ENDDO c** WRITE out Cross Section in Mike11 format WRITE(20,'(''HECRAS'')') WRITE(20,'(''RIVER1'')') WRITE(20,'(14X,A8)') chain WRITE(20,'(''COORDINATES'')') WRITE(20,'(4X,''0'')') WRITE(20,'(''FLOW DIRECTION'')') WRITE(20,'(4X,''0'')') 130 WRITE(20,'(''DATUM'')') WRITE(20,'(6X,''0.000'')') WRITE(20,'(''RADIUS TYPE'')') WRITE(20,'(4X,''0'')') WRITE(20,'(''DIVIDE X-Section'')') WRITE(20,'(''0'')') WRITE(20,'(''PROFILE'',9X,i3)') npts n = 0 DO K = 1,nrows DO L = 1,5 n = n+1 IF (n .LE. npts ) THEN WRITE(20,30) xz(k, (l*2)-1 ),xz(k,l*2) 30 FORMAT(3X,F7.2,4X,F6.2,6X,'1.00') ENDIF ENDDO ENDDO WRITE(20,*)'******************************' GOTO 10 9000 CONTINUE STOP END 131 Appendix C: MIKE 11 Cross-section File The MIKE 11 cross-section file data is read as input in column form. Each cross-section is identified with a TOPO identification number, branch identification, and Chainage number. The TOPO identification differentiates different cross-section to be processed during the simulation. A default TOPO identification number of 100 was used for the entire river network. Interpolated cross-sections are identified with a ?1? value. In the profile data, the first two columns are the X and Z coordinates for the cross-section. The third column is the local resistance factor for each cross- section, and is multiplied by the global resistance factors in the hydrodynamic file (the default being 1). The fourth column identifies the differentiates the stream channel from the flood plains. The number 1 identifies the left bank, 2 identifies the stream bed, and 3 identifies the right bank. 100 East Fork 11427.124 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 1 ANGLE 0.00 PROFILE 37 4.51 182.06 1.00 <#0> 7.44 181.57 1.00 <#0> 8.69 181.09 1.00 <#0> 10.43 180.61 1.00 <#0> 16.55 179.64 1.00 <#0> 132 19.72 179.15 1.00 <#0> 23.31 178.66 1.00 <#0> 29.05 178.16 1.00 <#0> 35.13 177.95 1.00 <#0> 44.72 177.61 1.00 <#0> 57.69 177.53 1.00 <#0> 58.50 177.51 1.00 <#1> 58.50 177.48 1.00 <#0> 59.49 176.86 1.00 <#0> 62.01 175.00 1.00 <#2> 66.68 175.00 1.00 <#0> 67.23 175.11 1.00 <#0> 67.34 175.13 1.00 <#0> 69.46 176.23 1.00 <#0> 69.97 176.43 1.00 <#0> 71.67 176.99 1.00 <#0> 73.14 177.55 1.00 <#3> 73.42 178.27 1.00 <#0> 76.31 178.68 1.00 <#0> 80.64 178.21 1.00 <#0> 86.90 177.74 1.00 <#0> 119.09 177.89 1.00 <#0> 124.11 177.30 1.00 <#0> 151.12 177.16 1.00 <#0> 163.65 177.35 1.00 <#0> 163.92 177.49 1.00 <#0> 165.04 178.11 1.00 <#0> 185.61 177.84 1.00 <#0> 199.02 177.97 1.00 <#0> 202.54 178.07 1.00 <#0> 223.68 178.54 1.00 <#0> 240.79 178.54 1.00 <#0> ******************************* 100 East Fork 11465.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 133 PROFILE 24 0.00 182.88 1.00 <#0> 3.14 182.27 1.00 <#0> 4.48 181.66 1.00 <#0> 6.34 181.05 1.00 <#0> 12.89 179.83 1.00 <#0> 16.28 179.22 1.00 <#0> 20.12 178.61 1.00 <#0> 26.27 178.00 1.00 <#0> 43.04 177.39 1.00 <#0> 57.79 177.39 1.00 <#1> 57.79 177.36 1.00 <#0> 58.64 176.78 1.00 <#0> 60.81 174.96 1.00 <#2> 65.87 174.96 1.00 <#0> 68.37 176.17 1.00 <#0> 69.98 176.78 1.00 <#0> 71.38 177.42 1.00 <#3> 74.46 178.00 1.00 <#0> 78.67 177.39 1.00 <#0> 84.76 176.78 1.00 <#0> 180.78 177.39 1.00 <#0> 197.24 178.00 1.00 <#0> 217.81 178.61 1.00 <#0> 234.45 178.61 1.00 <#0> ******************************* 100 East Fork 11656.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 22 0.00 179.83 1.00 <#0> 0.18 179.22 1.00 <#0> 24.87 178.61 1.00 <#0> 27.95 178.00 1.00 <#0> 29.08 177.39 1.00 <#1> 30.45 176.78 1.00 <#0> 134 31.30 176.17 1.00 <#0> 32.77 175.57 1.00 <#0> 37.92 174.44 1.00 <#2> 39.53 175.57 1.00 <#0> 41.15 176.17 1.00 <#0> 42.00 176.78 1.00 <#0> 44.32 178.00 1.00 <#3> 44.50 178.03 1.00 <#0> 47.27 178.61 1.00 <#0> 51.66 178.61 1.00 <#0> 55.02 177.39 1.00 <#0> 65.01 176.78 1.00 <#0> 132.47 176.78 1.00 <#0> 218.05 176.78 1.00 <#0> 249.75 178.00 1.00 <#0> 263.29 178.00 1.00 <#0> ******************************* 100 East Fork 11842.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 16 0.00 179.83 1.00 <#0> 0.12 178.61 1.00 <#0> 0.49 178.00 1.00 <#0> 12.13 177.39 1.00 <#0> 25.48 176.69 1.00 <#1> 26.55 176.17 1.00 <#0> 27.77 175.57 1.00 <#0> 29.84 174.96 1.00 <#0> 33.74 174.35 1.00 <#2> 35.69 174.96 1.00 <#0> 37.31 175.57 1.00 <#0> 38.04 176.17 1.00 <#3> 41.45 176.88 1.00 <#0> 42.37 177.39 1.00 <#0> 51.18 177.39 1.00 <#0> 135 53.43 176.78 1.00 <#0> ******************************* 100 East Fork 12232.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 10 0.00 177.55 1.00 <#0> 54.86 177.55 1.00 <#0> 59.44 178.77 1.00 <#0> 61.57 178.77 1.00 <#0> 70.10 175.12 1.00 <#1> 71.63 173.90 1.00 <#2> 73.15 173.90 1.00 <#0> 77.72 175.12 1.00 <#3> 91.44 176.64 1.00 <#0> 182.88 176.64 1.00 <#0> ******************************* 100 East Fork 12534.439 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 136 PROFILE 8 0.00 176.11 1.00 <#0> 30.48 175.81 1.00 <#1> 33.53 173.98 1.00 <#0> 41.15 173.16 1.00 <#2> 51.82 174.59 1.00 <#0> 56.39 175.20 1.00 <#3> 70.10 175.81 1.00 <#0> 79.25 176.11 1.00 <#0> ******************************* 100 Mill Creek 15407.150 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 1 ANGLE 0.00 PROFILE 62 17.27 180.80 1.00 <#0> 17.60 178.49 1.00 <#0> 18.33 178.38 1.00 <#0> 20.16 178.16 1.00 <#0> 29.89 178.11 1.00 <#0> 53.80 178.08 1.00 <#0> 81.66 177.99 1.00 <#0> 99.53 177.96 1.00 <#0> 154.19 177.85 1.00 <#0> 180.73 177.83 1.00 <#0> 196.85 177.85 1.00 <#0> 211.21 177.82 1.00 <#0> 221.38 177.72 1.00 <#0> 221.99 177.69 1.00 <#0> 223.30 177.56 1.00 <#0> 225.41 177.55 1.00 <#0> 228.03 177.46 1.00 <#0> 229.61 177.26 1.00 <#1> 229.79 177.22 1.00 <#0> 231.39 176.47 1.00 <#0> 232.65 175.91 1.00 <#0> 232.88 175.83 1.00 <#0> 137 234.02 174.54 1.00 <#0> 234.16 174.50 1.00 <#0> 234.82 174.38 1.00 <#0> 236.19 174.02 1.00 <#0> 236.21 174.01 1.00 <#0> 236.55 173.96 1.00 <#0> 236.64 173.96 1.00 <#0> 238.72 173.88 1.00 <#2> 240.65 174.31 1.00 <#0> 240.82 174.36 1.00 <#0> 241.27 174.75 1.00 <#0> 242.96 174.89 1.00 <#0> 244.47 174.99 1.00 <#0> 244.89 175.08 1.00 <#0> 246.04 175.37 1.00 <#0> 246.71 175.60 1.00 <#0> 246.82 175.61 1.00 <#0> 247.20 175.71 1.00 <#0> 247.27 175.72 1.00 <#0> 247.30 175.73 1.00 <#0> 249.51 176.34 1.00 <#0> 251.82 176.60 1.00 <#0> 251.89 176.61 1.00 <#0> 253.75 176.95 1.00 <#0> 255.57 177.36 1.00 <#0> 255.68 177.37 1.00 <#3> 258.55 177.55 1.00 <#0> 260.57 177.46 1.00 <#0> 261.43 177.52 1.00 <#0> 263.16 177.62 1.00 <#0> 264.88 177.63 1.00 <#0> 266.03 177.57 1.00 <#0> 269.48 177.64 1.00 <#0> 278.98 177.78 1.00 <#0> 319.25 178.00 1.00 <#0> 346.00 178.03 1.00 <#0> 374.19 178.11 1.00 <#0> 417.06 178.33 1.00 <#0> 458.74 178.49 1.00 <#0> 459.05 180.77 1.00 <#0> ******************************* 100 Mill Creek 15496.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 138 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 27 0.00 181.36 1.00 <#0> 0.30 178.16 1.00 <#0> 167.55 178.00 1.00 <#0> 190.44 177.85 1.00 <#0> 198.12 177.36 1.00 <#1> 198.36 177.36 1.00 <#0> 200.50 176.78 1.00 <#0> 202.48 176.30 1.00 <#0> 204.00 174.65 1.00 <#0> 205.07 174.47 1.00 <#0> 206.90 174.01 1.00 <#0> 206.93 174.01 1.00 <#0> 207.39 173.95 1.00 <#0> 207.51 173.95 1.00 <#0> 210.28 173.92 1.00 <#2> 212.57 174.53 1.00 <#0> 213.06 175.05 1.00 <#0> 216.53 175.20 1.00 <#0> 218.97 175.78 1.00 <#0> 219.09 175.78 1.00 <#0> 219.58 175.84 1.00 <#0> 219.61 175.84 1.00 <#0> 224.61 176.66 1.00 <#0> 228.60 177.55 1.00 <#0> 228.72 177.55 1.00 <#3> 426.72 178.13 1.00 <#0> 427.02 181.36 1.00 <#0> ******************************* 100 Mill Creek 15868.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID 139 INTERPOLATED 0 ANGLE 0.00 PROFILE 12 0.00 178.00 1.00 <#0> 3.05 176.78 1.00 <#0> 30.48 176.48 1.00 <#0> 109.73 176.78 1.00 <#0> 194.46 176.78 1.00 <#0> 196.60 176.17 1.00 <#1> 198.12 174.96 1.00 <#0> 201.17 173.74 1.00 <#0> 202.69 173.74 1.00 <#2> 210.31 176.78 1.00 <#3> 323.09 176.78 1.00 <#0> 329.18 178.00 1.00 <#0> ******************************* 100 Mill Creek 16213.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 12 295.66 176.17 1.00 <#0> 335.28 176.17 1.00 <#0> 396.24 176.48 1.00 <#0> 457.20 176.48 1.00 <#0> 490.73 176.17 1.00 <#1> 492.25 174.35 1.00 <#0> 496.82 173.43 1.00 <#2> 498.35 173.43 1.00 <#0> 502.92 174.35 1.00 <#0> 506.88 176.78 1.00 <#3> 513.89 177.39 1.00 <#0> 515.11 178.00 1.00 <#0> ******************************* 100 140 Mill Creek 16728.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 9 0.00 175.87 1.00 <#0> 30.48 175.57 1.00 <#1> 33.53 173.74 1.00 <#0> 41.15 172.82 1.00 <#2> 49.99 173.74 1.00 <#0> 51.82 174.35 1.00 <#0> 56.39 174.96 1.00 <#3> 70.10 175.57 1.00 <#0> 79.25 175.87 1.00 <#0> ******************************* 100 Mill Creek 17074.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 8 0.00 176.78 1.00 <#0> 73.15 176.78 1.00 <#1> 82.30 173.74 1.00 <#0> 141 91.44 172.36 1.00 <#2> 96.01 173.74 1.00 <#0> 115.21 174.35 1.00 <#0> 117.35 176.48 1.00 <#3> 138.68 176.78 1.00 <#0> ******************************* 100 Mill Creek 17276.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 18 0.09 177.52 1.00 <#0> 15.97 177.64 1.00 <#0> 16.00 175.02 1.00 <#1> 21.64 172.79 1.00 <#0> 26.34 172.64 1.00 <#0> 26.36 172.64 1.00 <#0> 26.64 172.64 1.00 <#0> 26.70 172.64 1.00 <#2> 29.87 173.13 1.00 <#0> 43.37 173.43 1.00 <#0> 43.43 173.43 1.00 <#0> 43.62 173.43 1.00 <#0> 43.68 173.43 1.00 <#0> 45.87 173.74 1.00 <#0> 51.57 175.47 1.00 <#0> 54.44 175.53 1.00 <#3> 54.47 177.61 1.00 <#0> 70.17 177.46 1.00 <#0> ******************************* 100 Mill Creek 17514.000 COORDINATES 0 FLOW DIRECTION 0 142 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 13 140.21 174.96 1.00 <#0> 166.12 174.96 1.00 <#0> 173.74 176.78 1.00 <#1> 182.88 173.74 1.00 <#0> 190.50 173.13 1.00 <#0> 196.60 173.13 1.00 <#0> 198.12 172.52 1.00 <#0> 204.22 172.21 1.00 <#2> 210.92 172.52 1.00 <#0> 213.36 173.74 1.00 <#0> 222.50 175.57 1.00 <#3> 233.17 176.17 1.00 <#0> 265.18 176.17 1.00 <#0> ******************************* 100 Mill Creek 17971.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 12 365.76 176.78 1.00 <#1> 370.33 174.96 1.00 <#0> 376.43 174.35 1.00 <#0> 377.95 173.74 1.00 <#0> 382.52 173.13 1.00 <#0> 143 388.62 172.52 1.00 <#0> 391.06 172.36 1.00 <#0> 404.47 171.72 1.00 <#2> 405.38 172.52 1.00 <#0> 411.48 173.74 1.00 <#0> 432.82 176.78 1.00 <#3> 509.02 176.78 1.00 <#0> ******************************* 100 Mill Creek 18247.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 24 15.24 178.31 1.00 <#0> 18.29 176.08 1.00 <#0> 30.51 176.08 1.00 <#0> 47.06 174.44 1.00 <#0> 47.09 174.32 1.00 <#1> 48.98 174.19 1.00 <#0> 51.24 172.09 1.00 <#0> 52.70 171.42 1.00 <#2> 56.08 171.51 1.00 <#0> 59.01 172.30 1.00 <#0> 59.07 172.24 1.00 <#0> 60.35 172.30 1.00 <#0> 60.50 172.30 1.00 <#0> 64.89 171.66 1.00 <#0> 67.06 174.04 1.00 <#0> 69.95 174.16 1.00 <#0> 70.81 174.22 1.00 <#0> 71.29 174.22 1.00 <#0> 74.25 174.22 1.00 <#0> 74.26 174.26 1.00 <#3> 74.28 174.29 1.00 <#0> 74.31 174.35 1.00 <#0> 91.44 176.78 1.00 <#0> 94.49 178.31 1.00 <#0> 144 ******************************* 100 Mill Creek 18674.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 11 124.97 176.78 1.00 <#0> 143.26 174.96 1.00 <#0> 149.96 173.74 1.00 <#1> 160.02 171.91 1.00 <#0> 164.90 171.24 1.00 <#2> 176.78 171.91 1.00 <#0> 182.88 173.74 1.00 <#0> 186.23 174.80 1.00 <#3> 189.89 174.83 1.00 <#0> 198.12 175.57 1.00 <#0> 225.55 176.17 1.00 <#0> ******************************* 100 Mill Creek 18983.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 145 PROFILE 22 0.00 175.50 1.00 <#0> 31.21 175.84 1.00 <#0> 31.27 174.32 1.00 <#1> 40.63 173.19 1.00 <#0> 43.56 172.00 1.00 <#0> 43.59 172.00 1.00 <#0> 43.80 171.88 1.00 <#0> 43.89 171.94 1.00 <#0> 45.81 171.63 1.00 <#0> 50.48 171.30 1.00 <#0> 53.46 171.18 1.00 <#2> 59.38 171.76 1.00 <#0> 59.47 171.69 1.00 <#0> 59.68 171.69 1.00 <#0> 59.71 171.69 1.00 <#0> 61.57 171.60 1.00 <#0> 66.05 173.43 1.00 <#0> 71.78 174.44 1.00 <#3> 71.81 175.96 1.00 <#0> 87.63 175.99 1.00 <#0> 137.16 174.96 1.00 <#0> 198.12 174.96 1.00 <#0> ******************************* 100 Mill Creek 19166.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 12 77.72 176.78 1.00 <#0> 85.34 174.35 1.00 <#0> 98.15 173.74 1.00 <#0> 106.07 173.13 1.00 <#1> 111.56 171.30 1.00 <#0> 115.82 170.87 1.00 <#2> 119.79 171.30 1.00 <#0> 123.44 173.13 1.00 <#3> 146 124.36 173.74 1.00 <#0> 144.78 174.35 1.00 <#0> 213.36 174.35 1.00 <#0> 219.46 176.78 1.00 <#0> ******************************* 100 Mill Creek 19998.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 20 128.02 173.04 1.00 <#0> 128.32 172.79 1.00 <#0> 128.63 172.49 1.00 <#0> 148.38 172.36 1.00 <#0> 155.48 172.24 1.00 <#0> 162.12 171.88 1.00 <#1> 162.31 171.88 1.00 <#0> 169.62 169.87 1.00 <#0> 171.85 169.65 1.00 <#0> 173.74 169.56 1.00 <#0> 175.35 169.44 1.00 <#0> 176.11 169.01 1.00 <#0> 176.39 169.01 1.00 <#2> 178.92 169.71 1.00 <#0> 178.95 170.90 1.00 <#0> 178.95 171.39 1.00 <#3> 193.97 173.92 1.00 <#0> 195.35 174.32 1.00 <#0> 199.92 174.32 1.00 <#0> 204.06 173.10 1.00 <#0> ******************************* 100 Mill Creek 20221.000 COORDINATES 0 FLOW DIRECTION 147 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 18 24.38 173.13 1.00 <#0> 54.86 173.13 1.00 <#0> 59.44 174.35 1.00 <#0> 70.10 174.35 1.00 <#0> 76.20 173.74 1.00 <#0> 79.25 173.13 1.00 <#1> 82.30 172.52 1.00 <#0> 83.21 171.91 1.00 <#0> 85.34 170.69 1.00 <#0> 85.95 170.38 1.00 <#0> 87.17 169.62 1.00 <#0> 91.44 169.38 1.00 <#2> 96.01 169.62 1.00 <#0> 99.06 170.69 1.00 <#0> 103.63 171.45 1.00 <#0> 107.90 172.21 1.00 <#0> 109.73 172.52 1.00 <#3> 152.40 172.82 1.00 <#0> ******************************* 100 Mill Creek 20446.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 148 PROFILE 18 23.96 175.02 1.00 <#0> 43.46 172.91 1.00 <#1> 43.49 172.91 1.00 <#0> 53.95 171.48 1.00 <#0> 54.10 171.48 1.00 <#0> 55.35 171.48 1.00 <#0> 55.44 171.42 1.00 <#0> 58.61 171.39 1.00 <#0> 60.99 169.68 1.00 <#0> 66.39 169.04 1.00 <#2> 66.54 169.10 1.00 <#0> 67.91 169.16 1.00 <#0> 68.00 169.16 1.00 <#0> 70.29 169.71 1.00 <#0> 73.06 172.43 1.00 <#0> 76.90 173.52 1.00 <#0> 76.93 173.52 1.00 <#3> 95.71 175.44 1.00 <#0> ******************************* 100 Mill Creek 20526.000 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 0 ANGLE 0.00 PROFILE 21 0.00 175.17 1.00 <#0> 11.25 175.17 1.00 <#0> 22.07 173.46 1.00 <#0> 30.30 172.88 1.00 <#1> 30.72 172.85 1.00 <#0> 38.37 172.49 1.00 <#0> 40.20 170.78 1.00 <#0> 42.03 171.05 1.00 <#0> 44.62 169.53 1.00 <#0> 45.54 168.80 1.00 <#0> 47.21 168.71 1.00 <#2> 50.26 169.01 1.00 <#0> 149 52.09 169.56 1.00 <#0> 55.14 170.63 1.00 <#0> 56.81 171.60 1.00 <#0> 59.41 172.18 1.00 <#0> 65.50 172.70 1.00 <#0> 65.62 172.43 1.00 <#3> 76.17 172.85 1.00 <#0> 81.96 175.17 1.00 <#0> 97.35 175.20 1.00 <#0> ******************************* 100 Mill Creek 20732.448 COORDINATES 0 FLOW DIRECTION 0 DATUM 0.00 RADIUS TYPE 0 DIVIDE X-Section 0 SECTION ID INTERPOLATED 1 ANGLE 0.00 PROFILE 36 98.90 174.11 1.00 <#0> 108.95 173.91 1.00 <#0> 118.61 173.27 1.00 <#0> 121.19 173.16 1.00 <#0> 122.14 172.92 1.00 <#0> 122.78 172.68 1.00 <#0> 123.42 172.22 1.00 <#0> 124.37 171.97 1.00 <#0> 125.01 171.73 1.00 <#0> 125.96 171.26 1.00 <#1> 126.39 171.10 1.00 <#0> 126.58 171.03 1.00 <#0> 127.49 170.79 1.00 <#0> 128.41 170.56 1.00 <#0> 129.02 170.44 1.00 <#0> 133.99 170.07 1.00 <#0> 135.80 169.51 1.00 <#0> 137.62 169.47 1.00 <#0> 138.19 169.35 1.00 <#0> 140.20 168.98 1.00 <#0> 141.10 168.76 1.00 <#0> 142.77 168.68 1.00 <#2> 150 144.35 168.81 1.00 <#0> 145.30 168.98 1.00 <#0> 146.88 169.31 1.00 <#0> 147.32 169.45 1.00 <#0> 147.75 169.69 1.00 <#0> 149.10 170.17 1.00 <#0> 149.59 170.31 1.00 <#0> 152.26 171.20 1.00 <#0> 152.32 171.14 1.00 <#3> 154.43 171.84 1.00 <#0> 155.03 172.97 1.00 <#0> 163.24 173.05 1.00 <#0> 169.23 173.66 1.00 <#0> 185.15 173.67 1.00 <#0> ******************************* 151 Appendix D: HEC RAS Cross-section Data The HEC RAS cross-section data was imported from various HEC-2 text files and combined into one .G01 geometry file. The geometry file was the initial file used for the HEC RAS 3.0 flow model. For accurate depiction of the stream channel in the terrain model (as explained in the terrain model refinement process in Chapter 5), interpolated cross-sections were included to successive geometry files until an optimum number of cross-sections were attained. XY-coordinates were digitized from the modified terrain model and included in this file. To better understand the data, the geometry file first provides the geometry file title and extent of the XY-coordinates used for the file. The second section describes the junctions and reaches within the geometry file. The rest of the geometry is broken down by reach, first defining the XY-coordinate points for each reach, then each cross-section within the reach. Each cross-section in the file is defined by a River Station identification number and downstream reach lengths (for left overbank, stream centerline, and right overbank). The next section of data is the X- and Z- coordinates in space-delimited format (sequenced horizontally) defining the cross-section (unlike the columnar format for MIKE 11 cross-section files). The number of times Manning?s n changes across the cross-section, and at what location follows the XZ-coordinate data. Lastly, left and right river bank coordinates, initial and incremental HTAB data (for unsteady flow calculations), whether the cross-section has been identified to provide a rating curve after processing (0 for no, 1 for yes), and expansion/contraction coefficients are shown. 152 HEC RAS 3.0 Geometry File from HEC-2 Data Geom Title=pdc geometry from HEC02 cross-sections Version=Version 3.0 Beta April 15, 2000 Viewing Rectangle= 432951.853815298, 433870.269332472 , 146027.514925005, 140851.356231991 Junct Name=one Junct Desc=, 0, 0, -1 Junct X Y & Text X Y=433158.8981556,144927.5088831,433158.8981556,144927.5088831 Up River,Reach=PDC ,Mill Creek Up River,Reach=PDC ,East Fork Dn River,Reach=PDC ,Mill Creek DS Junc L&A=326,0 Junc L&A=0,0 River Reach=PDC ,East Fork Reach XY= 44 433568.87 145914.24 433558.61 145864.87 433551.56 145828.97 433541.3 145794.35 433540.66 145750.76 433543.22 145702.68 433550.27 145661.01 433549.63 145622.54 433540.02 145564.2 433532.82 145530.7 433531.19 145485.41 433529.24 145475.31 433524.68 145465.21 433523.05 145445.34 433518.81 145411.78 433511.32 145378.22 433503.82 145347.59 433501.22 145326.09 433495.68 145306.54 433487.86 145297.41 433470.27 145288.94 433451.37 145281.12 433389.46 145268.09 433346.13 145257.34 433326.9 145248.54 433314.2 145236.49 433304.42 145221.82 433301.49 145205.53 433300.51 145184.68 433300.51 145151.45 433298.56 145107.14 433297.25 145067.39 433296.6 145049.79 433294. 145035.78 433295.95 145018.19 433292.69 144995.7 433284.55 144976.81 433275.1 144965.4 433260.44 144967.36 433244.8 144971.27 433223.94 144968.01 433198.86 144964.75 433180.28 144957.91 433158.8981556 144927.5088831 Rch Text X Y=433466.3770389,145667.5572208 Reverse River Text= 0 Type RM Length L Ch R = 1 ,388 ,52.02,52.02,52.02 BEGIN DESCRIPTION: 5.1 The East Fork Mill Creek HEC-2 model was developed by Water Resources & Coastal Engineering, Inc. under contract = END DESCRIPTION: Node Name= #Sta/Elev= 18 153 20.12 179.22 43.28 178.61 60.35 178 60.96 177.91 66.17 175.14 71.66 175.14 72.3 175.63 74.92 177.24 79.25 178 79.55 181.05 129.54 181.05 135.03 178.31 164.59 177.09 178.31 177.7 178.61 178.31 179.83 181.05 217.02 178.31 262.74 178.31 #Mann= 4 ,-1 , 0 20.12 .06 0 60.96 .03 0 79.25 .045 0 79.55 .113 0 Bank Sta=60.35,79.25 XS Rating Curve= 0 XS HTab Starting El and Incr=175.438,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,336 ,58,58,58 BEGIN DESCRIPTION: 199250 East Fork Mill Creek at Mill Creek station 199250 END DESCRIPTION: Node Name= #Sta/Elev= 24 0 182.88 3.14 182.27 4.48 181.66 6.34 181.05 12.89 179.83 16.28 179.22 20.12 178.61 26.27 178 43.04 177.39 57.79 177.39 57.79 177.36 58.64 176.78 60.81 174.96 65.87 174.96 68.37 176.17 69.98 176.78 71.38 177.42 74.46 178 78.67 177.39 84.77 176.78 180.78 177.39 197.24 178 217.81 178.61 234.45 178.61 #Mann= 3 , 0 , 0 0 .15 0 57.79 .05625 0 71.38 .15 0 Bank Sta=57.79,71.38 XS Rating Curve= 0 XS HTab Starting El and Incr=175.255,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,278 ,56.96,56.96,56.96 BEGIN DESCRIPTION: 198820 East Fork Mill Creek at Mill Creek station 198820 END DESCRIPTION: Node Name= #Sta/Elev= 22 0 179.83 .18 179.22 24.87 178.61 27.95 178 29.08 177.39 30.45 176.78 31.3 176.17 32.77 175.57 37.92 174.44 39.53 175.57 41.15 176.17 42 176.78 44.32 178 44.5 178.03 47.27 178.61 51.66 178.61 55.02 177.39 65.01 176.78 132.47 176.78 154 218.05 176.78 249.75 178 263.29 178 #Mann= 3 , 0 , 0 0 .15 0 29.08 .05625 0 44.32 .15 0 Bank Sta=29.08,44.32 XS Rating Curve= 0 XS HTab Starting El and Incr=174.737,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,221 ,119,119,119 BEGIN DESCRIPTION: 197690 East Fork Mill Creek at Mill Creek station 197690 END DESCRIPTION: Node Name= #Sta/Elev= 16 0 179.83 .12 178.61 .49 178 12.13 177.39 25.48 176.69 26.55 176.17 27.77 175.57 29.84 174.96 33.74 174.35 35.69 174.96 37.31 175.57 38.04 176.17 41.45 176.88 42.37 177.39 51.17 177.39 53.43 176.78 #Mann= 3 , 0 , 0 0 .15 0 25.48 .05625 0 38.04 .15 0 Bank Sta=25.48,38.04 XS Rating Curve= 0 XS HTab Starting El and Incr=174.646,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,102 ,93.995,93.995,93.995 BEGIN DESCRIPTION: 196730 (Total flow reduced - Flow crosses from Mill Creek to East Fork Mill = Mill Creek confluence with East Fork Mill Creek at Mill Creek station = END DESCRIPTION: Node Name= #Sta/Elev= 10 0 176.78 54.86 176.78 59.44 178 61.57 178 70.1 174.35 71.63 173.13 73.15 173.13 77.72 174.35 91.44 175.87 182.88 175.87 #Mann= 3 , 0 , 0 0 .15 0 70.1 .05625 0 77.72 .15 0 Bank Sta=70.1,77.72 XS Rating Curve= 0 XS HTab Starting El and Incr=173.426,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,8 ,8,8,8 155 BEGIN DESCRIPTION: 196000 Mill Creek total flow from CofE HEC-1 Model Mill Creek (Main Stem) END DESCRIPTION: Node Name= #Sta/Elev= 8 0 175.87 30.48 175.57 33.53 173.74 41.14 172.822 51.82 174.35 56.39 174.96 70.1 175.57 79.25 175.87 #Mann= 3 , 0 , 0 0 .15 0 30.48 .05625 0 56.39 .15 0 Bank Sta=30.48,56.39 XS Rating Curve= 0 XS HTab Starting El and Incr=173.122,.1 Exp/Cntr=.5,.3 Type RM Length L Ch R = 1 ,0 ,0,0,0 BEGIN DESCRIPTION: 196000 Mill Creek total flow from CofE HEC-1 Model Mill Creek (Main Stem) END DESCRIPTION: Node Name= #Sta/Elev= 8 0 175.87 30.48 175.57 33.53 173.74 41.15 172.82 51.82 174.35 56.39 174.96 70.1 175.57 79.25 175.87 #Mann= 3 , 0 , 0 0 .15 0 30.48 .05625 0 56.39 .15 0 Bank Sta=30.48,56.39 XS Rating Curve= 0 XS HTab Starting El and Incr=173.122,.1 Exp/Cntr=.5,.3 River Reach=PDC ,Mill Creek Reach XY= 26 433142.53 145849.3 433134.11 145797.91 433126.58 145728.37 433116.39 145689.39 433073.42 145615.41 433054.82 145576.43 433021.16 145533.02 433020.27 145507.77 433024.7 145487.4 433037.1 145463.92 433039.76 145451.96 433033.56 145409.44 433041.09 145373.56 433045.52 145301.35 433049.5 145284.52 433058.81 145270.79 433064.12 145225.16 433064.12 145194.15 433054.82 145173.78 433062.35 145152.96 433065.01 145124.17 433067.67 145080.31 433078.74 145044.88 433088.93 145003.24 433126.14 144966.03 433158.8981556 144927.5088831 Rch Text X Y=433146.6220389,145618.8522208 Reverse River Text= 0 156 Type RM Length L Ch R = 1 ,45485 ,89.01,89.01,89.01 Node Name= #Sta/Elev= 46 145.09 178.9 145.53 178.63 146.31 178.24 147.34 178.05 149.6 177.61 150.44 177.6 160.61 177.59 172.44 177.51 180.03 177.48 203.26 177.39 214.54 177.39 227.49 177.46 232.07 177.39 232.63 177.3 233.52 177.39 234.64 177.42 235.31 177.27 237 175.68 237.84 175.06 238.54 174.67 240.39 173.96 241.4 173.96 242.49 174.1 243.79 174.36 244.88 174.54 245.53 174.69 246.18 174.95 247.48 175.46 247.89 175.49 248.78 175.82 249.87 176.28 250.95 176.84 252.11 177.06 252.92 176.96 253.27 177.03 253.97 177.16 254.66 177.17 255.13 177.11 256.52 177.2 260.35 177.4 275.55 177.81 276.58 177.82 287.37 177.78 298.73 177.81 316.01 177.97 332.94 178.05 #Mann= 3 , 0 , 0 145.09 .15 0 235.31 .052 0 250.95 .15 0 Bank Sta=235.31,250.95 XS Rating Curve= 0 XS HTab Starting El and Incr=174.258,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,45396 ,371,371,371 Node Name= #Sta/Elev= 27 0 181.36 .31 178.16 167.55 178 190.44 177.85 198.12 177.36 198.36 177.36 200.5 176.78 202.48 176.3 204 174.65 205.07 174.47 206.9 174.01 206.93 174.01 207.39 173.95 207.51 173.95 210.28 173.92 212.57 174.53 213.06 175.05 216.53 175.2 218.97 175.78 219.09 175.78 219.58 175.84 219.61 175.84 224.61 176.66 228.6 177.55 228.72 177.55 426.72 178.13 427.03 181.36 #Mann= 3 , 0 , 0 0 .15 0 198.12 .05625 0 228.6 .15 0 Bank Sta=198.12,228.6 XS Rating Curve= 0 XS HTab Starting El and Incr=174.2189,.1 Exp/Cntr=.5,.3 157 Type RM Length L Ch R = 1 ,45025 ,341.38,344.42,344.42 Node Name= #Sta/Elev= 12 0 178 3.05 176.78 30.48 176.48 109.73 176.78 194.46 176.78 196.6 176.17 198.12 174.96 201.17 173.74 202.69 173.74 210.31 176.78 323.09 176.78 329.18 178 #Mann= 3 , 0 , 0 0 .15 0 196.6 .05625 0 210.31 .15 0 Bank Sta=196.6,210.31 XS Rating Curve= 0 XS HTab Starting El and Incr=174.036,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,44680 ,189,189,189 Node Name= #Sta/Elev= 12 295.66 176.17 335.28 176.17 396.24 176.48 457.2 176.48 490.73 176.17 492.25 174.35 496.82 173.43 498.35 173.43 502.92 174.35 506.88 176.78 513.89 177.39 515.11 178 #Mann= 3 , 0 , 0 295.66 .15 0 490.73 .05625 0 506.88 .15 0 Bank Sta=490.73,506.88 XS Rating Curve= 0 XS HTab Starting El and Incr=173.7309,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,44491 ,326,326,326 Node Name= #Sta/Elev= 16 187.47 176.06 214.85 176.04 257 176.2 299.13 176.16 322.31 175.95 324.25 174.21 324.53 174.1 330.08 173.21 331.89 173.3 337.01 174.09 337.33 174.17 338.45 174.72 342.03 176.12 350.18 176.61 353.61 176.8 355.62 177.22 #Mann= 3 , 0 , 0 187.47 .15 0 322.31 .05625 0 342.03 .15 0 Bank Sta=322.31,342.03 XS Rating Curve= 0 XS HTab Starting El and Incr=173.508,.1 Exp/Cntr=.3,.1 River Reach=PDC ,Mill Creek DS Reach XY= 71 433158.8981556 144927.5088831 433158.92 144927.49 433177.52 144896.93 433175.31 144872.56 158 433220.05 144763.15 433234.22 144725.5 433250.17 144647.98 433259.91 144552.3 433263.01 144452.19 433276.75 144363.15 433269.21 144257.73 433278.07 144197.93 433266.11 144121.3 433254.15 144092.5 433255.48 144037.13 433254.6 143960.94 433239.09 143886.08 433244.85 143816.09 433239.98 143718.64 433235.55 143520.64 433220.49 143465.71 433228.46 143429.39 433247.07 143392.18 433252.38 143345.22 433252.38 143295.17 433252.38 143260.62 433262.57 143231.82 433267.89 143163.61 433264.34 143135.26 433269.21 143082.54 433276.75 143041.35 433285.16 142976.23 433282.06 142905.36 433274.97 142848.22 433278.07 142783.1 433283.83 142694.95 433278.52 142660.4 433275.86 142585.54 433279.4 142543.9 433267.44 142409.24 433245.74 142333.93 433235.55 142283.44 433237.76 142244.01 433235.99 142152.76 433244.41 142060.18 433243.52 141985.76 433260.36 141949.44 433280.29 141889.64 433312.18 141828.07 433339.65 141776.24 433418.05 141684.99 433445.51 141664.62 433508.86 141605.7 433523.03 141587.98 433558.91 141566.28 433614.28 141509.58 433643.52 141496.73 433668.33 141489.65 433697.12 141466.17 433726.8 141448.89 433760.46 141430.73 433813.62 141385.11 433830.01 141358.97 433837.1 141290.31 433833.11 141250. 433814.95 141194.63 433807.86 141116.67 433802.99 141041.37 433798.56 140958.09 433788.81 140928.85 433786.6 140903.6 Rch Text X Y=433315.8236167,143921.5316623 Reverse River Text= 0 Type RM Length L Ch R = 1 ,44165 ,52,52,52 Node Name= #Sta/Elev= 9 0 175.87 30.48 175.57 33.53 173.74 41.15 172.82 49.99 173.74 51.82 174.35 56.39 174.96 70.1 175.57 79.25 175.87 #Mann= 3 , 0 , 0 0 .15 0 30.48 .05625 0 56.39 .15 0 Bank Sta=30.48,56.39 XS Rating Curve= 0 XS HTab Starting El and Incr=173.1219,.1 Exp/Cntr=.5,.3 Type RM Length L Ch R = 1 ,44113 ,15.24,17.68,21.34 Node Name= 159 #Sta/Elev= 20 33.22 178.31 44.2 176.78 49.99 175.26 51.82 174.65 54.56 174.35 56.69 173.43 57.3 173.37 58.83 172.82 60.96 172.82 63.4 172.82 64.31 173.37 64.92 173.74 66.45 174.35 71.63 174.65 72.54 175.26 78.64 175.87 81.69 175.87 87.78 175.57 112.17 176.17 148.74 179.83 #Mann= 3 , 0 , 0 33.22 .15 0 49.99 .05625 0 72.54 .15 0 Bank Sta=49.99,72.54 XS Rating Curve= 0 XS HTab Starting El and Incr=173.1219,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,44095 ,46,46,46 Node Name= #Sta/Elev= 21 28.96 178.31 37.19 176.78 46.03 175.26 47.85 174.65 50.29 174.35 54.86 174.35 55.78 174.04 56.69 173.74 58.22 173.37 58.83 172.82 60.96 172.82 62.48 172.82 63.7 173.37 65.23 173.43 66.14 173.73 68.28 175.26 74.37 175.87 80.47 175.87 104.85 175.57 129.24 176.17 165.81 179.83 #Mann= 3 , 0 , 0 28.96 .15 0 46.03 .05625 0 68.28 .15 0 Bank Sta=46.03,68.28 XS Rating Curve= 0 XS HTab Starting El and Incr=173.1219,.1 Exp/Cntr=.5,.3 Type RM Length L Ch R = 1 ,44049 ,3,3,3 Node Name= #Sta/Elev= 26 15.03 184.4 22.16 184.53 22.19 181.78 27.13 180.23 42.52 178.95 44.07 177.79 46.85 176.78 48.86 174.86 49.99 174.74 49.99 174.8 50.63 174.53 50.63 174.59 53.52 172.82 61.05 172.58 65.68 172.76 67.61 174.5 71.6 174.59 71.63 174.59 72.15 174.71 72.18 174.71 76.26 175.99 79.68 177.49 95.8 180.96 100.04 182.15 100.07 185.14 107.23 185.2 #Mann= 3 , 0 , 0 15.03 .15 0 22.19 .05625 0 100.04 .15 0 Bank Sta=22.19,100.04 160 XS Rating Curve= 0 XS HTab Starting El and Incr=172.8781,.1 Exp/Cntr=.5,.3 Type RM Length L Ch R = 1 ,44046 ,64,64,64 Node Name= #Sta/Elev= 26 15.03 184.4 22.16 184.53 22.19 181.78 27.13 180.23 42.52 178.95 44.07 177.79 46.85 176.78 48.86 174.86 49.99 174.74 49.99 174.8 50.63 174.53 50.63 174.59 53.52 172.82 61.05 172.58 65.68 172.76 67.61 174.51 71.6 174.59 71.63 174.59 72.15 174.71 72.18 174.71 76.26 175.99 79.68 177.49 95.8 180.96 100.04 182.15 100.07 185.14 107.23 185.2 #Mann= 3 , 0 , 0 15.03 .15 0 22.19 .05625 0 100.04 .15 0 Bank Sta=22.19,100.04 XS Rating Curve= 0 XS HTab Starting El and Incr=172.8781,.1 Exp/Cntr=.5,.3 Type RM Length L Ch R = 1 ,43982 ,52,52,52 Node Name= #Sta/Elev= 7 313.94 176.78 320.04 176.78 331.01 173.74 343.21 172.33 352.04 173.74 359.66 176.17 371.86 176.48 #Mann= 3 , 0 , 0 313.94 .15 0 320.04 .05625 0 359.66 .15 0 Bank Sta=320.04,359.66 XS Rating Curve= 0 XS HTab Starting El and Incr=172.6339,.1 Exp/Cntr=.5,.3 Type RM Length L Ch R = 1 ,43930 ,108.81,110.64,112.47 Node Name= #Sta/Elev= 7 313.94 176.78 320.04 176.78 331.01 173.74 343.21 172.33 352.04 173.74 359.66 176.17 371.86 176.48 #Mann= 3 , 0 , 0 313.94 .15 0 320.04 .05625 0 359.66 .15 0 Bank Sta=320.04,359.66 XS Rating Curve= 0 XS HTab Starting El and Incr=172.6339,.1 Exp/Cntr=.3,.1 161 Type RM Length L Ch R = 1 ,43819 ,167.64,167.64,167.64 Node Name= #Sta/Elev= 8 0 176.78 73.15 176.78 82.3 173.74 91.44 172.36 96.01 173.74 115.21 174.35 117.35 176.48 138.68 176.78 #Mann= 3 , 0 , 0 0 .15 0 73.15 .05625 0 117.35 .15 0 Bank Sta=73.15,117.35 XS Rating Curve= 0 XS HTab Starting El and Incr=172.6641,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,43652 ,84,84,84 Node Name= #Sta/Elev= 10 0 176.17 53.34 176.48 57.91 173.74 67.06 173.74 73.15 172.33 79.25 173.74 85.34 174.35 91.44 176.48 106.68 176.78 121.92 176.78 #Mann= 3 , 0 , 0 0 .15 0 53.34 .05625 0 91.44 .15 0 Bank Sta=53.34,91.44 XS Rating Curve= 0 XS HTab Starting El and Incr=172.6339,.1 Exp/Cntr=.5,.3 Type RM Length L Ch R = 1 ,43568 ,189,189,189 Node Name= #Sta/Elev= 10 0 175.57 36.58 175.57 44.2 176.78 48.77 176.17 57.91 173.74 68.58 172.21 79.25 173.74 89 174.35 97.54 176.78 115.82 176.78 #Mann= 3 , 0 , 0 0 .15 0 48.77 .05625 0 97.54 .15 0 Bank Sta=48.77,97.54 XS Rating Curve= 0 XS HTab Starting El and Incr=172.512,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,43379 ,706.95,706.95,706.95 Node Name= #Sta/Elev= 13 140.21 174.96 166.12 174.96 173.74 176.78 182.88 173.74 190.5 173.13 196.6 173.13 198.12 172.52 204.22 172.21 210.92 172.52 213.36 173.74 222.5 175.57 233.17 176.17 265.18 176.17 #Mann= 3 , 0 , 0 140.21 .15 0 173.74 .0525 0 222.5 .15 0 Bank Sta=173.74,222.5 162 XS Rating Curve= 0 XS HTab Starting El and Incr=172.512,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,42672 ,452.97,452.97,452.97 Node Name= #Sta/Elev= 12 373.69 176.48 373.99 176.48 374.29 176.48 374.6 176.48 374.9 176.48 384.05 176.17 396.85 171.91 405.69 171.45 409.04 171.6 411.48 173.74 421.23 173.74 425.81 175.26 #Mann= 3 , 0 , 0 373.69 .15 0 384.05 .0525 0 411.48 .15 0 Bank Sta=384.05,411.48 XS Rating Curve= 0 XS HTab Starting El and Incr=171.75,.1 Exp/Cntr=.5,.3 Type RM Length L Ch R = 1 ,42219 ,265.18,263.96,262.13 Node Name= #Sta/Elev= 11 124.97 176.78 143.26 174.96 149.96 173.74 160.02 171.91 164.9 171.24 176.78 171.91 182.88 173.74 186.23 174.8 189.89 174.83 198.12 175.57 225.55 176.17 #Mann= 3 , 0 , 0 124.97 .15 0 149.96 .0525 0 186.23 .15 0 Bank Sta=149.96,186.23 XS Rating Curve= 0 XS HTab Starting El and Incr=171.537,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,41955 ,103,103,103 Node Name= #Sta/Elev= 17 42.67 176.78 48.77 176.17 67.06 175.57 79.25 174.35 81.99 173.74 83.97 172.21 84.73 171.91 85.34 171.6 86.87 171.3 91.44 171.15 96.01 171.3 97.54 171.6 98.45 172.21 100.28 173.74 106.68 174.35 108.2 174.96 121.92 174.96 #Mann= 3 , 0 , 0 42.67 .15 0 81.99 .0525 0 100.28 .15 0 Bank Sta=81.99,100.28 XS Rating Curve= 0 XS HTab Starting El and Incr=171.4449,.1 Exp/Cntr=.5,.3 Type RM Length L Ch R = 1 ,41852 ,121.92,125.28,126.48 163 Node Name= #Sta/Elev= 15 91.44 175.57 94.49 174.96 99.06 174.36 100.89 173.74 102.72 172.21 104.24 171.51 112.78 170.99 115.82 170.99 118.26 170.99 122.23 171.51 124.97 173.13 126.8 173.74 131.06 175.57 152.4 175.87 167.64 175.87 #Mann= 3 , 0 , 0 91.44 .15 0 99.06 .05625 0 124.97 .15 0 Bank Sta=99.06,124.97 XS Rating Curve= 0 XS HTab Starting El and Incr=171.2931,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,41727 ,152.4,152.4,152.4 Node Name= #Sta/Elev= 12 77.72 176.78 85.34 174.35 98.15 173.74 106.07 173.13 111.56 171.3 115.82 170.87 119.79 171.3 123.44 173.13 124.36 173.74 144.78 174.35 213.36 174.35 219.46 176.78 #Mann= 3 , 0 , 0 77.72 .15 0 106.07 .05625 0 123.44 .15 0 Bank Sta=106.07,123.44 XS Rating Curve= 0 XS HTab Starting El and Incr=171.1709,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,41574 ,106,106,106 Node Name= #Sta/Elev= 19 60.96 176.17 76.2 174.96 80.16 173.74 82.91 172.52 83.82 172.21 85.04 171.91 86.87 171.3 87.78 171.08 89 170.69 91.44 170.6 93.88 170.69 95.1 171.08 95.71 171.6 97.23 172.21 108.2 172.52 126.5 173.13 129.54 173.74 134.11 174.96 146.3 175.57 #Mann= 3 , 0 , 0 60.96 .15 0 83.82 .05625 0 97.23 .15 0 Bank Sta=83.82,97.23 XS Rating Curve= 0 XS HTab Starting El and Incr=170.8969,.1 Exp/Cntr=.5,.3 Type RM Length L Ch R = 1 ,41468 ,393.21,393.21,393.21 Node Name= #Sta/Elev= 19 60.96 176.17 76.2 174.96 80.16 173.74 82.91 172.52 83.82 172.21 164 85.04 171.91 86.87 171.3 87.78 171.08 89 170.69 91.44 170.6 93.88 170.69 95.1 171.08 95.71 171.6 97.23 172.21 108.2 172.52 126.49 173.13 129.54 173.74 134.11 174.96 146.3 175.57 #Mann= 3 , 0 , 0 60.96 .15 0 83.82 .05625 0 97.23 .15 0 Bank Sta=83.82,97.23 XS Rating Curve= 0 XS HTab Starting El and Incr=170.8969,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,41074 ,179.83,179.83,179.83 Node Name= #Sta/Elev= 18 0 173.43 .03 173.43 45.72 173.43 82.3 173.13 84.13 172.52 85.65 172.21 87.78 170.69 88.39 170.57 89.31 170.08 91.44 169.84 93.27 170.08 94.49 170.57 96.93 170.69 99.06 171.91 100.58 172.52 155.45 173 182.88 173.13 228.6 173.13 #Mann= 3 , 0 , 0 0 .15 0 84.13 .05625 0 99.06 .15 0 Bank Sta=84.13,99.06 XS Rating Curve= 0 XS HTab Starting El and Incr=170.1349,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,40895 ,223.41,223.41,223.41 Node Name= #Sta/Elev= 20 128.02 173.04 128.32 172.79 128.63 172.49 148.38 172.36 155.48 172.24 162.12 171.88 162.31 171.88 169.62 169.87 171.85 169.65 173.74 169.45 175.35 169.44 176.11 169.01 176.39 169.01 178.92 169.71 178.95 170.9 178.95 171.39 193.98 173.92 195.35 174.32 199.92 174.32 204.06 173.1 #Mann= 3 , 0 , 0 128.02 .15 0 162.12 .05625 0 178.95 .15 0 Bank Sta=162.12,178.95 XS Rating Curve= 0 XS HTab Starting El and Incr=169.3119,.1 Exp/Cntr=.5,.3 Type RM Length L Ch R = 1 ,40672 ,187.44,186.54,185.94 Node Name= #Sta/Elev= 18 24.38 173.13 54.86 173.13 59.44 174.35 70.1 174.35 76.2 173.74 165 79.25 173.13 82.3 172.52 83.21 171.91 85.34 170.69 85.95 170.38 87.17 169.62 91.44 169.38 96.01 169.62 99.06 170.69 103.63 171.45 107.9 172.21 109.73 172.52 152.4 172.82 #Mann= 3 , 0 , 0 24.38 .15 0 79.25 .05625 0 109.73 .15 0 Bank Sta=79.25,109.73 XS Rating Curve= 0 XS HTab Starting El and Incr=169.677,.1 Exp/Cntr=.3,.1 Type RM Length L Ch R = 1 ,40486 ,67,67,67 Node Name= #Sta/Elev= 20 51.82 172.52 64.01 172.52 70.1 173.13 74.37 174.35 77.72 174.35 78.64 174.04 79.86 173.74 82.91 172.21 85.04 170.69 85.65 170.08 86.87 169.47 91.44 169.16 96.01 169.47 97.54 170.08 98.45 170.69 102.72 172.21 104.85 172.82 106.07 173.13 115.82 173.74 137.16 173.74 #Mann= 3 , 0 , 0 51.82 .15 0 82.91 .05625 0 102.72 .15 0 Bank Sta=82.91,102.72 XS Rating Curve= 0 XS HTab Starting El and Incr=169.464,.1 Exp/Cntr=.7,.5 Type RM Length L Ch R = 1 ,40419 ,3.35,3.35,3.35 Node Name= #Sta/Elev= 21 52.43 176.78 52.73 175.26 67.67 174.96 71.02 174.04 71.93 173.74 75.9 172.52 82.91 171.3 85.65 170.69 86.56 170.08 87.48 169.16 91.44 169.16 94.49 169.16 96.01 170.08 96.62 170.38 7.23 170.69 100.28 170.99 103.94 171.3 108.2 171.6 109.73 172.21 112.78 173.74 113.08 176.78 #Mann= 3 , 0 , 0 52.43 .15 0 82.91 .05625 0 100.28 .15 0 Bank Sta=82.91,100.28 XS Rating Curve= 0 XS HTab Starting El and Incr=169.464,.1 Exp/Cntr=.7,.5 Type RM Length L Ch R = 1 ,40415 ,29,29,29 Node Name= 166 #Sta/Elev= 21 52.43 176.78 52.73 175.26 67.67 174.96 71.02 174.04 71.93 173.74 75.9 172.52 82.91 171.3 85.65 170.69 86.56 170.08 87.48 169.16 91.44 169.16 94.49 169.16 96.01 170.08 96.62 170.38 97.23 170.69 100.28 170.99 103.94 171.3 108.2 171.6 109.73 172.21 112.78 173.74 113.08 176.78 #Mann= 3 , 0 , 0 52.43 .15 0 82.91 .05625 0 100.28 .15 0 Bank Sta=82.91,100.28 XS Rating Curve= 0 XS HTab Starting El and Incr=169.464,.1 Exp/Cntr=.7,.5 Type RM Length L Ch R = 1 ,40386 ,6,6,6 Node Name= #Sta/Elev= 25 24.9 177.64 42.92 177.85 42.98 172.52 46.09 171.88 48.25 171.48 50.9 171.12 53.71 170.72 53.8 170.66 55.57 170.38 55.57 170.32 57.85 169.07 58.74 169.07 61.14 169.07 63.55 169.07 65.23 169.07 66.6 170.2 66.66 170.26 68.28 170.6 68.34 170.66 71.48 171.05 73.88 171.3 76.26 171.63 79.34 171.91 79.37 178.1 95.1 178.28 #Mann= 3 , 0 , 0 24.9 .15 0 42.98 .05625 0 79.34 .15 0 Bank Sta=42.98,79.34 XS Rating Curve= 0 XS HTab Starting El and Incr=169.3729,.1 Exp/Cntr=.7,.5 Type RM Length L Ch R = 1 ,40380 ,98,98,98 Node Name= #Sta/Elev= 25 24.9 177.64 42.92 177.85 42.98 172.52 46.09 171.88 48.25 171.48 50.9 171.12 53.71 170.72 53.8 170.66 55.57 170.38 55.57 170.32 57.85 168.86 58.74 168.92 61.14 168.95 63.55 168.92 65.23 168.92 66.6 170.2 66.66 170.26 68.28 170.6 68.34 170.66 71.48 171.05 73.88 171.3 76.26 171.63 79.34 171.91 79.37 178.1 95.1 178.28 #Mann= 3 , 0 , 0 24.9 .15 0 42.98 .05625 0 79.34 .15 0 167 Bank Sta=42.98,79.34 XS Rating Curve= 0 XS HTab Starting El and Incr=169.1589,.1 Exp/Cntr=.7,.5 Type RM Length L Ch R = 1 ,40282 ,121.5,121.5,121.5 Node Name= #Sta/Elev= 17 70.1 172.52 82.91 171.91 84.73 171.91 85.95 171 86.87 170.69 87.78 169.71 90.83 169.16 92.96 169.16 96.01 169.16 98.15 169.71 100.58 170.69 102.41 171.3 106.68 172.21 117.04 172.52 149.35 172.52 155.45 173.74 161.54 174.96 #Mann= 3 , 0 , 0 70.1 .15 0 84.73 .05625 0 102.41 .15 0 Bank Sta=84.73,102.41 XS Rating Curve= 0 XS HTab Starting El and Incr=169.464,.1 Exp/Cntr=.5,.3 Type RM Length L Ch R = 1 ,40160.5 ,105.92,102.49,100.58 Node Name= #Sta/Elev= 31 102.11 173.13 118.8 172.53 119.52 172.37 119.84 172.26 119.99 172.21 120.47 171.91 121.19 171.76 121.66 171.6 122.38 171.3 122.79 171.06 123.42 170.79 124.04 170.51 124.46 170.35 124.66 170.29 126.38 170.04 128.09 169.45 130.69 169.16 133.81 168.92 134.87 168.92 136.4 168.92 138.53 169.26 139.45 169.47 140.97 170.15 142.8 170.99 145.76 171.86 146.13 172.24 146.61 172.68 154.22 172.82 179.46 172.82 184.22 173.43 188.98 174.04 #Mann= 3 , 0 , 0 102.11 .15 0 122.38 .056 0 142.8 .15 0 Bank Sta=122.38,142.8 XS Rating Curve= 0 XS HTab Starting El and Incr=169.22,.1 Exp/Cntr=.5,.3 168 Appendix E: HEC HMS Input for MIKE 11 The hydrograph data used for both the HEC HMS and MIKE 11 models is the same. The data is displayed in two sections. The first section shown is the upstream (for East Fork and Mill Creek) and downstream (for Mill Creek) boundary data in 4- minute time steps. The upstream data is flow hydrographs and the downstream data is stage hydrographs. The second section is flow data derived from the HEC HMS model. It was inputted into both models at 15-minute time steps. The flow data was extracted from the hydrologic model from the DSS utility for the HEC RAS model. For both sections, corresponding HEC RAS River Stations and MIKE 11 Chainages are provided for each boundary input. Table E-1. Mill Creek PDC model?s upstream and downstream boundary data. Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 1 4/15/1998 12:00 169.324 1.300 1.132 2 4/15/1998 12:04 169.324 1.300 1.134 3 4/15/1998 12:08 169.324 1.300 1.151 4 4/15/1998 12:12 169.324 1.300 1.138 5 4/15/1998 12:16 169.324 1.300 1.129 6 4/15/1998 12:20 169.324 1.300 1.130 7 4/15/1998 12:24 169.324 1.300 1.130 8 4/15/1998 12:28 169.324 1.300 1.133 9 4/15/1998 12:32 169.324 1.300 1.136 10 4/15/1998 12:36 169.324 1.300 1.139 11 4/15/1998 12:40 169.324 1.300 1.141 12 4/15/1998 12:44 169.324 1.300 1.141 13 4/15/1998 12:48 169.324 1.300 1.141 14 4/15/1998 12:52 169.324 1.300 1.141 15 4/15/1998 12:56 169.324 1.300 1.140 16 4/15/1998 13:00 169.324 1.300 1.139 17 4/15/1998 13:04 169.324 1.300 1.138 169 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 18 4/15/1998 13:08 169.324 1.300 1.137 19 4/15/1998 13:12 169.324 1.300 1.137 20 4/15/1998 13:16 169.324 1.300 1.136 21 4/15/1998 13:20 169.324 1.300 1.135 22 4/15/1998 13:24 169.324 1.300 1.135 23 4/15/1998 13:28 169.324 1.300 1.134 24 4/15/1998 13:32 169.324 1.300 1.134 25 4/15/1998 13:36 169.324 1.300 1.134 26 4/15/1998 13:40 169.324 1.300 1.134 27 4/15/1998 13:44 169.324 1.300 1.133 28 4/15/1998 13:48 169.324 1.300 1.133 29 4/15/1998 13:52 169.324 1.300 1.133 30 4/15/1998 13:56 169.324 1.300 1.133 31 4/15/1998 14:00 169.324 1.300 1.133 32 4/15/1998 14:04 169.324 1.300 1.133 33 4/15/1998 14:08 169.324 1.300 1.133 34 4/15/1998 14:12 169.324 1.300 1.133 35 4/15/1998 14:16 169.324 1.300 1.133 36 4/15/1998 14:20 169.324 1.300 1.133 37 4/15/1998 14:24 169.324 1.300 1.133 38 4/15/1998 14:28 169.324 1.300 1.133 39 4/15/1998 14:32 169.324 1.300 1.133 40 4/15/1998 14:36 169.324 1.300 1.133 41 4/15/1998 14:40 169.324 1.300 1.133 42 4/15/1998 14:44 169.324 1.300 1.133 43 4/15/1998 14:48 169.324 1.300 1.133 44 4/15/1998 14:52 169.324 1.300 1.133 45 4/15/1998 14:56 169.324 1.300 1.133 46 4/15/1998 15:00 169.324 1.300 1.133 47 4/15/1998 15:04 169.324 1.300 1.133 48 4/15/1998 15:08 169.324 1.300 1.133 49 4/15/1998 15:12 169.324 1.300 1.133 50 4/15/1998 15:16 169.324 1.300 1.133 51 4/15/1998 15:20 169.324 1.300 1.133 52 4/15/1998 15:24 169.324 1.300 1.133 53 4/15/1998 15:28 169.324 1.300 1.133 170 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 54 4/15/1998 15:32 169.324 1.300 1.133 55 4/15/1998 15:36 169.324 1.300 1.133 56 4/15/1998 15:40 169.324 1.300 1.133 57 4/15/1998 15:44 169.324 1.300 1.133 58 4/15/1998 15:48 169.324 1.300 1.133 59 4/15/1998 15:52 169.324 1.300 1.133 60 4/15/1998 15:56 169.324 1.300 1.133 61 4/15/1998 16:00 169.324 1.300 1.133 62 4/15/1998 16:04 169.324 1.300 1.133 63 4/15/1998 16:08 169.324 1.300 1.133 64 4/15/1998 16:12 169.324 1.300 1.133 65 4/15/1998 16:16 169.324 1.300 1.133 66 4/15/1998 16:20 169.324 1.300 1.133 67 4/15/1998 16:24 169.324 1.300 1.133 68 4/15/1998 16:28 169.324 1.300 1.133 69 4/15/1998 16:32 169.324 1.300 1.133 70 4/15/1998 16:36 169.324 1.300 1.133 71 4/15/1998 16:40 169.324 1.300 1.133 72 4/15/1998 16:44 169.324 1.300 1.133 73 4/15/1998 16:48 169.324 1.300 1.133 74 4/15/1998 16:52 169.324 1.300 1.133 75 4/15/1998 16:56 169.324 1.300 1.133 76 4/15/1998 17:00 169.324 1.300 1.133 77 4/15/1998 17:04 169.324 1.300 1.133 78 4/15/1998 17:08 169.324 1.300 1.133 79 4/15/1998 17:12 169.324 1.300 1.133 80 4/15/1998 17:16 169.324 1.300 1.133 81 4/15/1998 17:20 169.324 1.300 1.133 82 4/15/1998 17:24 169.324 1.300 1.133 83 4/15/1998 17:28 169.324 1.300 1.133 84 4/15/1998 17:32 169.324 1.300 1.133 85 4/15/1998 17:36 169.324 1.300 1.133 86 4/15/1998 17:40 169.324 1.300 1.133 87 4/15/1998 17:44 169.324 1.300 1.133 88 4/15/1998 17:48 169.324 1.300 1.133 89 4/15/1998 17:52 169.324 1.300 1.133 171 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 90 4/15/1998 17:56 169.324 1.300 1.133 91 4/15/1998 18:00 169.324 1.300 1.133 92 4/15/1998 18:04 169.324 1.300 1.133 93 4/15/1998 18:08 169.324 1.300 1.133 94 4/15/1998 18:12 169.324 1.300 1.133 95 4/15/1998 18:16 169.324 1.300 1.133 96 4/15/1998 18:20 169.324 1.300 1.133 97 4/15/1998 18:24 169.324 1.300 1.133 98 4/15/1998 18:28 169.324 1.300 1.133 99 4/15/1998 18:32 169.324 1.300 1.133 100 4/15/1998 18:36 169.324 1.300 1.133 101 4/15/1998 18:40 169.324 1.300 1.133 102 4/15/1998 18:44 169.324 1.300 1.133 103 4/15/1998 18:48 169.324 1.300 1.133 104 4/15/1998 18:52 169.324 1.300 1.133 105 4/15/1998 18:56 169.324 1.300 1.133 106 4/15/1998 19:00 169.324 1.300 1.133 107 4/15/1998 19:04 169.324 1.300 1.133 108 4/15/1998 19:08 169.324 1.300 1.133 109 4/15/1998 19:12 169.324 1.300 1.133 110 4/15/1998 19:16 169.324 1.300 1.133 111 4/15/1998 19:20 169.324 1.300 1.133 112 4/15/1998 19:24 169.324 1.300 1.133 113 4/15/1998 19:28 169.324 1.300 1.133 114 4/15/1998 19:32 169.324 1.300 1.133 115 4/15/1998 19:36 169.324 1.300 1.133 116 4/15/1998 19:40 169.324 1.300 1.133 117 4/15/1998 19:44 169.324 1.300 1.133 118 4/15/1998 19:48 169.324 1.300 1.133 119 4/15/1998 19:52 169.324 1.300 1.133 120 4/15/1998 19:56 169.324 1.300 1.133 121 4/15/1998 20:00 169.324 1.300 1.133 122 4/15/1998 20:04 169.324 1.300 1.133 123 4/15/1998 20:08 169.324 1.300 1.133 124 4/15/1998 20:12 169.324 1.300 1.133 125 4/15/1998 20:16 169.324 1.300 1.133 172 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 126 4/15/1998 20:20 169.324 1.300 1.133 127 4/15/1998 20:24 169.324 1.300 1.133 128 4/15/1998 20:28 169.324 1.300 1.133 129 4/15/1998 20:32 169.324 1.300 1.133 130 4/15/1998 20:36 169.324 1.300 1.133 131 4/15/1998 20:40 169.324 1.300 1.133 132 4/15/1998 20:44 169.324 1.300 1.133 133 4/15/1998 20:48 169.324 1.300 1.133 134 4/15/1998 20:52 169.324 1.300 1.133 135 4/15/1998 20:56 169.324 1.300 1.133 136 4/15/1998 21:00 169.324 1.300 1.133 137 4/15/1998 21:04 169.324 1.300 1.133 138 4/15/1998 21:08 169.324 1.300 1.133 139 4/15/1998 21:12 169.324 1.300 1.133 140 4/15/1998 21:16 169.324 1.300 1.133 141 4/15/1998 21:20 169.324 1.300 1.133 142 4/15/1998 21:24 169.324 1.300 1.133 143 4/15/1998 21:28 169.324 1.300 1.133 144 4/15/1998 21:32 169.324 1.300 1.133 145 4/15/1998 21:36 169.324 1.300 1.133 146 4/15/1998 21:40 169.324 1.300 1.133 147 4/15/1998 21:44 169.324 1.300 1.133 148 4/15/1998 21:48 169.324 1.300 1.133 149 4/15/1998 21:52 169.324 1.300 1.133 150 4/15/1998 21:56 169.324 1.300 1.133 151 4/15/1998 22:00 169.324 1.300 1.133 152 4/15/1998 22:04 169.324 1.300 1.133 153 4/15/1998 22:08 169.324 1.300 1.133 154 4/15/1998 22:12 169.324 1.300 1.133 155 4/15/1998 22:16 169.324 1.300 1.133 156 4/15/1998 22:20 169.324 1.300 1.133 157 4/15/1998 22:24 169.324 1.300 1.133 158 4/15/1998 22:28 169.324 1.300 1.133 159 4/15/1998 22:32 169.324 1.300 1.133 160 4/15/1998 22:36 169.324 1.300 1.133 161 4/15/1998 22:40 169.324 1.300 1.133 173 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 162 4/15/1998 22:44 169.324 1.300 1.133 163 4/15/1998 22:48 169.324 1.300 1.133 164 4/15/1998 22:52 169.324 1.300 1.133 165 4/15/1998 22:56 169.324 1.300 1.133 166 4/15/1998 23:00 169.324 1.300 1.133 167 4/15/1998 23:04 169.324 1.300 1.133 168 4/15/1998 23:08 169.324 1.300 1.133 169 4/15/1998 23:12 169.324 1.300 1.133 170 4/15/1998 23:16 169.324 1.300 1.133 171 4/15/1998 23:20 169.324 1.300 1.133 172 4/15/1998 23:24 169.324 1.300 1.133 173 4/15/1998 23:28 169.324 1.300 1.133 174 4/15/1998 23:32 169.324 1.300 1.133 175 4/15/1998 23:36 169.324 1.300 1.133 176 4/15/1998 23:40 169.324 1.300 1.133 177 4/15/1998 23:44 169.324 1.300 1.133 178 4/15/1998 23:48 169.324 1.300 1.133 179 4/15/1998 23:52 169.324 1.300 1.133 180 4/15/1998 23:56 169.324 1.300 1.133 181 4/15/1998 0:00 169.324 1.300 1.133 182 4/16/1998 0:04 169.324 1.300 1.133 183 4/16/1998 0:08 169.324 1.300 1.133 184 4/16/1998 0:12 169.324 1.300 1.133 185 4/16/1998 0:16 169.324 1.300 1.133 186 4/16/1998 0:20 169.324 1.300 1.133 187 4/16/1998 0:24 169.324 1.300 1.133 188 4/16/1998 0:28 169.324 1.300 1.133 189 4/16/1998 0:32 169.324 1.300 1.133 190 4/16/1998 0:36 169.324 1.300 1.133 191 4/16/1998 0:40 169.324 1.300 1.133 192 4/16/1998 0:44 169.324 1.300 1.133 193 4/16/1998 0:48 169.324 1.300 1.133 194 4/16/1998 0:52 169.324 1.300 1.133 195 4/16/1998 0:56 169.324 1.300 1.133 196 4/16/1998 1:00 169.324 1.300 1.133 197 4/16/1998 1:04 169.324 1.300 1.133 174 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 198 4/16/1998 1:08 169.324 1.300 1.133 199 4/16/1998 1:12 169.324 1.300 1.133 200 4/16/1998 1:16 169.324 1.300 1.133 201 4/16/1998 1:20 169.324 1.300 1.133 202 4/16/1998 1:24 169.324 1.300 1.133 203 4/16/1998 1:28 169.324 1.300 1.133 204 4/16/1998 1:32 169.324 1.300 1.133 205 4/16/1998 1:36 169.324 1.300 1.133 206 4/16/1998 1:40 169.324 1.300 1.133 207 4/16/1998 1:44 169.324 1.300 1.133 208 4/16/1998 1:48 169.324 1.300 1.133 209 4/16/1998 1:52 169.324 1.300 1.133 210 4/16/1998 1:56 169.324 1.300 1.133 211 4/16/1998 2:00 169.324 1.300 1.133 212 4/16/1998 2:04 169.324 1.300 1.133 213 4/16/1998 2:08 169.324 1.300 1.133 214 4/16/1998 2:12 169.324 1.300 1.133 215 4/16/1998 2:16 169.324 1.300 1.133 216 4/16/1998 2:20 169.324 1.300 1.133 217 4/16/1998 2:24 169.324 1.300 1.133 218 4/16/1998 2:28 169.324 1.300 1.133 219 4/16/1998 2:32 169.324 1.300 1.133 220 4/16/1998 2:36 169.324 1.300 1.133 221 4/16/1998 2:40 169.324 1.300 1.133 222 4/16/1998 2:44 169.324 1.300 1.133 223 4/16/1998 2:48 169.324 1.300 1.133 224 4/16/1998 2:52 169.324 1.300 1.133 225 4/16/1998 2:56 169.324 1.299 1.133 226 4/16/1998 3:00 169.325 1.298 1.133 227 4/16/1998 3:04 169.325 1.297 1.133 228 4/16/1998 3:08 169.327 1.295 1.133 229 4/16/1998 3:12 169.329 1.290 1.133 230 4/16/1998 3:16 169.333 1.286 1.133 231 4/16/1998 3:20 169.338 1.281 1.133 232 4/16/1998 3:24 169.345 1.274 1.133 233 4/16/1998 3:28 169.354 1.265 1.133 175 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 234 4/16/1998 3:32 169.367 1.255 1.133 235 4/16/1998 3:36 169.382 1.242 1.134 236 4/16/1998 3:40 169.400 1.227 1.136 237 4/16/1998 3:44 169.422 1.209 1.140 238 4/16/1998 3:48 169.447 1.189 1.148 239 4/16/1998 3:52 169.476 1.164 1.161 240 4/16/1998 3:56 169.508 1.132 1.183 241 4/16/1998 4:00 169.542 1.095 1.218 242 4/16/1998 4:04 169.579 1.056 1.272 243 4/16/1998 4:08 169.620 1.002 1.352 244 4/16/1998 4:12 169.663 0.929 1.470 245 4/16/1998 4:16 169.709 0.853 1.651 246 4/16/1998 4:20 169.757 0.779 1.908 247 4/16/1998 4:24 169.808 0.679 2.305 248 4/16/1998 4:28 169.861 0.560 2.894 249 4/16/1998 4:32 169.916 0.461 3.710 250 4/16/1998 4:36 169.973 0.377 4.840 251 4/16/1998 4:40 170.033 0.246 6.210 252 4/16/1998 4:44 170.095 0.161 7.768 253 4/16/1998 4:48 170.159 0.225 9.982 254 4/16/1998 4:52 170.226 0.353 12.192 255 4/16/1998 4:56 170.295 0.578 14.890 256 4/16/1998 5:00 170.365 1.014 17.828 257 4/16/1998 5:04 170.437 1.709 20.904 258 4/16/1998 5:08 170.511 2.612 24.273 259 4/16/1998 5:12 170.585 3.691 27.221 260 4/16/1998 5:16 170.661 5.012 30.811 261 4/16/1998 5:20 170.738 6.489 33.738 262 4/16/1998 5:24 170.815 8.177 37.233 263 4/16/1998 5:28 170.893 10.155 40.111 264 4/16/1998 5:32 170.973 11.986 42.969 265 4/16/1998 5:36 171.057 14.594 45.745 266 4/16/1998 5:40 171.147 17.775 47.707 267 4/16/1998 5:44 171.250 21.117 49.903 268 4/16/1998 5:48 171.364 24.638 51.111 269 4/16/1998 5:52 171.493 27.686 52.540 176 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 270 4/16/1998 5:56 171.637 31.025 53.072 271 4/16/1998 6:00 171.791 33.802 53.334 272 4/16/1998 6:04 171.950 36.910 53.347 273 4/16/1998 6:08 172.108 41.461 52.995 274 4/16/1998 6:12 172.267 44.970 52.414 275 4/16/1998 6:16 172.429 47.884 51.316 276 4/16/1998 6:20 172.595 51.821 50.346 277 4/16/1998 6:24 172.745 54.563 48.899 278 4/16/1998 6:28 172.889 57.644 47.583 279 4/16/1998 6:32 173.024 60.604 45.792 280 4/16/1998 6:36 173.148 63.031 44.325 281 4/16/1998 6:40 173.264 65.900 42.364 282 4/16/1998 6:44 173.369 68.001 40.765 283 4/16/1998 6:48 173.466 70.496 38.754 284 4/16/1998 6:52 173.553 72.566 37.065 285 4/16/1998 6:56 173.633 74.582 35.143 286 4/16/1998 7:00 173.705 76.627 33.482 287 4/16/1998 7:04 173.772 78.181 31.693 288 4/16/1998 7:08 173.829 80.194 30.011 289 4/16/1998 7:12 173.883 81.522 28.445 290 4/16/1998 7:16 173.930 83.178 26.884 291 4/16/1998 7:20 173.973 84.381 25.532 292 4/16/1998 7:24 174.010 85.809 24.072 293 4/16/1998 7:28 174.045 86.910 22.942 294 4/16/1998 7:32 174.074 87.960 21.693 295 4/16/1998 7:36 174.101 89.047 20.758 296 4/16/1998 7:40 174.123 89.893 19.689 297 4/16/1998 7:44 174.143 90.892 18.965 298 4/16/1998 7:48 174.161 91.425 18.147 299 4/16/1998 7:52 174.176 92.429 17.582 300 4/16/1998 7:56 174.189 92.847 16.992 301 4/16/1998 8:00 174.200 93.591 16.578 302 4/16/1998 8:04 174.210 93.989 16.208 303 4/16/1998 8:08 174.217 94.514 15.903 304 4/16/1998 8:12 174.225 95.050 15.690 305 4/16/1998 8:16 174.229 95.135 15.474 177 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 306 4/16/1998 8:20 174.234 95.813 15.361 307 4/16/1998 8:24 174.236 95.720 15.209 308 4/16/1998 8:28 174.238 96.356 15.147 309 4/16/1998 8:32 174.238 96.181 15.037 310 4/16/1998 8:36 174.238 96.580 14.973 311 4/16/1998 8:40 174.235 96.651 14.897 312 4/16/1998 8:44 174.233 96.625 14.811 313 4/16/1998 8:48 174.229 96.942 14.739 314 4/16/1998 8:52 174.224 96.594 14.615 315 4/16/1998 8:56 174.218 97.069 14.526 316 4/16/1998 9:00 174.210 96.579 14.345 317 4/16/1998 9:04 174.202 96.902 14.177 318 4/16/1998 9:08 174.192 96.621 13.939 319 4/16/1998 9:12 174.182 96.573 13.699 320 4/16/1998 9:16 174.170 96.604 13.390 321 4/16/1998 9:20 174.158 96.115 13.062 322 4/16/1998 9:24 174.143 96.446 12.690 323 4/16/1998 9:28 174.129 95.694 12.323 324 4/16/1998 9:32 174.112 96.011 11.904 325 4/16/1998 9:36 174.096 95.302 11.516 326 4/16/1998 9:40 174.077 95.321 11.068 327 4/16/1998 9:44 174.058 94.901 10.685 328 4/16/1998 9:48 174.037 94.427 10.227 329 4/16/1998 9:52 174.016 94.376 9.864 330 4/16/1998 9:56 173.993 93.481 9.409 331 4/16/1998 10:00 173.969 93.570 9.070 332 4/16/1998 10:04 173.945 92.560 8.627 333 4/16/1998 10:08 173.919 92.437 8.309 334 4/16/1998 10:12 173.894 91.674 7.887 335 4/16/1998 10:16 173.866 91.051 7.581 336 4/16/1998 10:20 173.839 90.714 7.198 337 4/16/1998 10:24 173.810 89.548 6.899 338 4/16/1998 10:28 173.781 89.526 6.569 339 4/16/1998 10:32 173.751 88.107 6.279 340 4/16/1998 10:36 173.720 88.011 6.009 341 4/16/1998 10:40 173.689 86.754 5.735 178 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 342 4/16/1998 10:44 173.658 86.187 5.509 343 4/16/1998 10:48 173.626 85.443 5.261 344 4/16/1998 10:52 173.594 84.233 5.068 345 4/16/1998 10:56 173.561 83.943 4.854 346 4/16/1998 11:00 173.528 82.383 4.671 347 4/16/1998 11:04 173.495 82.132 4.500 348 4/16/1998 11:08 173.462 80.749 4.336 349 4/16/1998 11:12 173.429 79.977 4.199 350 4/16/1998 11:16 173.395 79.228 4.041 351 4/16/1998 11:20 173.362 77.719 3.920 352 4/16/1998 11:24 173.328 77.537 3.785 353 4/16/1998 11:28 173.294 75.628 3.673 354 4/16/1998 11:32 173.260 75.498 3.553 355 4/16/1998 11:36 173.227 73.879 3.454 356 4/16/1998 11:40 173.193 73.130 3.348 357 4/16/1998 11:44 173.159 72.263 3.248 358 4/16/1998 11:48 173.125 70.720 3.157 359 4/16/1998 11:52 173.092 70.461 3.063 360 4/16/1998 11:56 173.058 68.612 2.983 361 4/16/1998 12:00 173.024 68.249 2.892 362 4/16/1998 12:04 172.990 66.911 2.818 363 4/16/1998 12:08 172.956 65.769 2.754 364 4/16/1998 12:12 172.923 65.308 2.670 365 4/16/1998 12:16 172.889 63.400 2.618 366 4/16/1998 12:20 172.855 63.402 2.560 367 4/16/1998 12:24 172.821 61.484 2.492 368 4/16/1998 12:28 172.788 61.065 2.434 369 4/16/1998 12:32 172.754 59.941 2.383 370 4/16/1998 12:36 172.721 58.651 2.320 371 4/16/1998 12:40 172.688 58.350 2.280 372 4/16/1998 12:44 172.654 56.575 2.216 373 4/16/1998 12:48 172.621 56.293 2.172 374 4/16/1998 12:52 172.588 54.978 2.133 375 4/16/1998 12:56 172.555 53.936 2.091 376 4/16/1998 13:00 172.522 53.494 2.055 377 4/16/1998 13:04 172.489 51.801 2.019 179 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 378 4/16/1998 13:08 172.456 51.787 1.989 379 4/16/1998 13:12 172.423 50.227 1.950 380 4/16/1998 13:16 172.390 49.672 1.924 381 4/16/1998 13:20 172.358 48.832 1.891 382 4/16/1998 13:24 172.325 47.624 1.862 383 4/16/1998 13:28 172.293 47.222 1.838 384 4/16/1998 13:32 172.261 45.923 1.811 385 4/16/1998 13:36 172.231 45.335 1.780 386 4/16/1998 13:40 172.201 44.592 1.753 387 4/16/1998 13:44 172.170 43.640 1.718 388 4/16/1998 13:48 172.139 43.199 1.686 389 4/16/1998 13:52 172.108 41.986 1.651 390 4/16/1998 13:56 172.078 41.672 1.622 391 4/16/1998 14:00 172.047 40.849 1.593 392 4/16/1998 14:04 172.017 40.150 1.570 393 4/16/1998 14:08 171.987 39.469 1.546 394 4/16/1998 14:12 171.957 38.713 1.520 395 4/16/1998 14:16 171.927 38.051 1.506 396 4/16/1998 14:20 171.898 37.102 1.483 397 4/16/1998 14:24 171.869 36.466 1.471 398 4/16/1998 14:28 171.841 35.915 1.452 399 4/16/1998 14:32 171.813 35.029 1.439 400 4/16/1998 14:36 171.785 34.593 1.421 401 4/16/1998 14:40 171.757 33.777 1.403 402 4/16/1998 14:44 171.729 33.271 1.387 403 4/16/1998 14:48 171.701 32.586 1.372 404 4/16/1998 14:52 171.673 31.964 1.356 405 4/16/1998 14:56 171.645 31.370 1.343 406 4/16/1998 15:00 171.618 30.771 1.328 407 4/16/1998 15:04 171.591 30.164 1.318 408 4/16/1998 15:08 171.564 29.627 1.305 409 4/16/1998 15:12 171.538 29.009 1.296 410 4/16/1998 15:16 171.512 28.568 1.285 411 4/16/1998 15:20 171.486 27.955 1.278 412 4/16/1998 15:24 171.460 27.535 1.266 413 4/16/1998 15:28 171.434 26.964 1.259 180 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 414 4/16/1998 15:32 171.409 26.533 1.248 415 4/16/1998 15:36 171.384 26.007 1.242 416 4/16/1998 15:40 171.359 25.566 1.231 417 4/16/1998 15:44 171.334 25.066 1.227 418 4/16/1998 15:48 171.310 24.642 1.218 419 4/16/1998 15:52 171.286 24.153 1.214 420 4/16/1998 15:56 171.263 23.775 1.206 421 4/16/1998 16:00 171.239 23.278 1.203 422 4/16/1998 16:04 171.216 22.910 1.196 423 4/16/1998 16:08 171.193 22.437 1.193 424 4/16/1998 16:12 171.170 22.065 1.187 425 4/16/1998 16:16 171.148 21.612 1.184 426 4/16/1998 16:20 171.126 21.246 1.179 427 4/16/1998 16:24 171.104 20.804 1.176 428 4/16/1998 16:28 171.082 20.447 1.172 429 4/16/1998 16:32 171.061 20.021 1.170 430 4/16/1998 16:36 171.039 19.706 1.166 431 4/16/1998 16:40 171.019 19.307 1.164 432 4/16/1998 16:44 170.998 18.988 1.160 433 4/16/1998 16:48 170.978 18.608 1.159 434 4/16/1998 16:52 170.958 18.313 1.155 435 4/16/1998 16:56 170.938 17.953 1.155 436 4/16/1998 17:00 170.919 17.660 1.151 437 4/16/1998 17:04 170.899 17.308 1.151 438 4/16/1998 17:08 170.880 17.019 1.148 439 4/16/1998 17:12 170.861 16.677 1.148 440 4/16/1998 17:16 170.842 16.398 1.145 441 4/16/1998 17:20 170.824 16.047 1.146 442 4/16/1998 17:24 170.805 15.767 1.143 443 4/16/1998 17:28 170.787 15.427 1.143 444 4/16/1998 17:32 170.770 15.156 1.141 445 4/16/1998 17:36 170.753 14.839 1.142 446 4/16/1998 17:40 170.736 14.577 1.142 447 4/16/1998 17:44 170.719 14.272 1.145 448 4/16/1998 17:48 170.703 14.031 1.149 449 4/16/1998 17:52 170.688 13.740 1.158 181 Time Step #: Date: Time: h (meters): U/S Mill Creek Q (m 3 /s) U/S East Fork Q (m 3 /s) Chainage: 20732.45 15407.15 11427.12 River Station: 18.83 5179.47 1173.84 450 4/16/1998 17:56 170.672 13.498 1.171 451 4/16/1998 18:00 170.657 13.214 1.193 452 4/16/1998 18:04 170.643 12.986 1.225 453 4/16/1998 18:08 170.628 12.714 1.270 454 4/16/1998 18:12 170.614 12.487 1.332 455 4/16/1998 18:16 170.601 12.226 1.414 456 4/16/1998 18:20 170.587 12.011 1.522 457 4/16/1998 18:24 170.575 11.763 1.654 458 4/16/1998 18:28 170.563 11.563 1.810 459 4/16/1998 18:32 170.551 11.333 1.987 460 4/16/1998 18:36 170.539 11.151 2.186 461 4/16/1998 18:40 170.528 10.941 2.394 462 4/16/1998 18:44 170.517 10.780 2.596 463 4/16/1998 18:48 170.506 10.596 2.789 464 4/16/1998 18:52 170.496 10.459 2.962 465 4/16/1998 18:56 170.485 10.298 3.122 466 4/16/1998 19:00 170.475 10.180 3.245 182 Table E-2. Mill Creek PDC model?s lateral boundary data extracted from the HEC HMS model. Time Step #: Date: Time: Basin 109 Runoff (m 3 /s) Basin 110 Runoff (m 3 /s) Basin 111 Runoff (m 3 /s) Basin 115 Runoff (m 3 /s) Basins 112 - 117 Runoff (m 3 /s) Chainage: 15829.00 16443.00 15850.00 20000.00 20248.00 River Station: 4822.09 4043.30 4577.87 525.69 336.56 1 4/15/1998 12:00 0 0 0 0 0 2 4/15/1998 12:15 0 0 0 0 0 3 4/15/1998 12:30 0 0 0 0 0 4 4/15/1998 12:45 0 0 0 0 0 5 4/15/1998 13:00 0 0 0 0 0 6 4/15/1998 13:15 0 0 0 0 0 7 4/15/1998 13:30 0 0 0 0 0 8 4/15/1998 13:45 0 0 0 0 0 9 4/15/1998 14:00 0 0 0 0 0 10 4/15/1998 14:15 0 0 0 0 0 11 4/15/1998 14:30 0 0 0 0 0 12 4/15/1998 14:45 0 0 0 0 0 13 4/15/1998 15:00 0 0 0 0 0 14 4/15/1998 15:15 0 0 0 0 0 15 4/15/1998 15:30 0 0 0 0 0 16 4/15/1998 15:45 0 0 0 0 0 17 4/15/1998 16:00 0 0 0 0 0 18 4/15/1998 16:15 0 0 0 0 0 19 4/15/1998 16:30 0 0 0 0 0 20 4/15/1998 16:45 0 0 0 0 0 21 4/15/1998 17:00 0 0 0 0 0 22 4/15/1998 17:15 0 0 0 0 0 23 4/15/1998 17:30 0 0 0 0 0 24 4/15/1998 17:45 0 0 0 0 0 25 4/15/1998 18:00 0 0 0 0 0 26 4/15/1998 18:15 0 0 0 0 0 27 4/15/1998 18:30 0 0 0 0 0 28 4/15/1998 18:45 0 0 0 0 0 29 4/15/1998 19:00 0 0 0 0 0 30 4/15/1998 19:15 0 0 0 0 0 31 4/15/1998 19:30 0 0 0 0 0 32 4/15/1998 19:45 0 0 0 0 0 183 Time Step #: Date: Time: Basin 109 Runoff (m 3 /s) Basin 110 Runoff (m 3 /s) Basin 111 Runoff (m 3 /s) Basin 115 Runoff (m 3 /s) Basins 112 - 117 Runoff (m 3 /s) Chainage: 15829.00 16443.00 15850.00 20000.00 20248.00 River Station: 4822.09 4043.30 4577.87 525.69 336.56 33 4/15/1998 20:00 0 0 0 0 0 34 4/15/1998 20:15 0 0 0 0 0 35 4/15/1998 20:30 0 0 0 0 0 36 4/15/1998 20:45 0 0 0 0 0 37 4/15/1998 21:00 0 0 0 0 0 38 4/15/1998 21:15 0 0 0 0 0 39 4/15/1998 21:30 0 0 0 0 0 40 4/15/1998 21:45 0 0 0 0 0 41 4/15/1998 22:00 0 0 0 0 0 42 4/15/1998 22:15 0 0 0 0 0 43 4/15/1998 22:30 0 0 0 0 0 44 4/15/1998 22:45 0 0 0 0 0 45 4/15/1998 23:00 0 0 0 0 0 46 4/15/1998 23:15 0 0 0 0 0 47 4/15/1998 23:30 0 0 0 0 0 48 4/15/1998 23:45 0 0 0 0 0 49 4/15/1998 0:00 0 0 0 0 0 50 4/16/1998 0:15 0 0 0 0 0 51 4/16/1998 0:30 0 0 0 0 0 52 4/16/1998 0:45 0 0 0 0 0 53 4/16/1998 1:00 0 0 0 0 0 54 4/16/1998 1:15 0 0 0 0 0 55 4/16/1998 1:30 0 0 0 0 0 56 4/16/1998 1:45 0 0 0 0 0 57 4/16/1998 2:00 0 0 0 0 0 58 4/16/1998 2:15 0 0 0 0 0 59 4/16/1998 2:30 0 0 0 0 0 60 4/16/1998 2:45 0 0 0 0 0 61 4/16/1998 3:00 0.03 0.006 0.032 0.043 0.034 62 4/16/1998 3:15 0.151 0.0316 0.155 0.198 0.25 63 4/16/1998 3:30 0.367 0.0783 0.382 0.465 0.832 64 4/16/1998 3:45 0.694 0.1482 0.732 0.865 1.846 65 4/16/1998 4:00 1.163 0.248 1.237 1.424 3.248 66 4/16/1998 4:15 1.88 0.4042 2.004 2.26 5.032 184 Time Step #: Date: Time: Basin 109 Runoff (m 3 /s) Basin 110 Runoff (m 3 /s) Basin 111 Runoff (m 3 /s) Basin 115 Runoff (m 3 /s) Basins 112 - 117 Runoff (m 3 /s) Chainage: 15829.00 16443.00 15850.00 20000.00 20248.00 River Station: 4822.09 4043.30 4577.87 525.69 336.56 67 4/16/1998 4:30 2.9 0.6269 3.091 3.453 7.317 68 4/16/1998 4:45 4.37 0.9416 4.589 5.163 10.239 69 4/16/1998 5:00 6.248 1.3418 6.449 7.391 13.92 70 4/16/1998 5:15 8.485 1.812 8.595 10.084 18.174 71 4/16/1998 5:30 10.984 2.3372 10.976 13.142 22.548 72 4/16/1998 5:45 13.776 2.909 13.54 16.558 26.537 73 4/16/1998 6:00 16.746 3.5188 16.189 20.224 29.838 74 4/16/1998 6:15 19.86 4.1353 18.784 24.149 32.293 75 4/16/1998 6:30 22.88 4.7278 21.208 28.096 33.86 76 4/16/1998 6:45 25.693 5.2432 23.245 31.896 34.615 77 4/16/1998 7:00 28.098 5.6607 24.779 35.318 34.561 78 4/16/1998 7:15 29.968 5.9592 25.834 38.187 33.764 79 4/16/1998 7:30 31.318 6.1468 26.414 40.381 32.46 80 4/16/1998 7:45 32.135 6.2362 26.565 41.911 30.866 81 4/16/1998 8:00 32.505 6.2279 26.291 42.877 29.163 82 4/16/1998 8:15 32.448 6.1302 25.691 43.274 27.557 83 4/16/1998 8:30 31.977 5.9602 24.789 43.092 26.067 84 4/16/1998 8:45 31.155 5.7344 23.759 42.467 24.64 85 4/16/1998 9:00 30.085 5.4774 22.604 41.389 23.242 86 4/16/1998 9:15 28.844 5.1956 21.33 39.998 21.839 87 4/16/1998 9:30 27.45 4.8787 19.933 38.416 20.427 88 4/16/1998 9:45 25.916 4.539 18.517 36.657 19.023 89 4/16/1998 10:00 24.225 4.1923 17.124 34.633 17.675 90 4/16/1998 10:15 22.478 3.861 15.797 32.447 16.399 91 4/16/1998 10:30 20.728 3.5481 14.563 30.124 15.192 92 4/16/1998 10:45 19.112 3.2603 13.392 27.839 14.065 93 4/16/1998 11:00 17.599 2.9925 12.275 25.662 13.022 94 4/16/1998 11:15 16.182 2.7401 11.225 23.646 12.05 95 4/16/1998 11:30 14.855 2.504 10.246 21.762 11.16 96 4/16/1998 11:45 13.629 2.2872 9.302 19.981 10.352 97 4/16/1998 12:00 12.474 2.0807 8.387 18.331 9.611 98 4/16/1998 12:15 11.405 1.8806 7.52 16.789 8.942 99 4/16/1998 12:30 10.38 1.6903 6.708 15.345 8.335 100 4/16/1998 12:45 9.386 1.5138 5.962 13.98 7.788 185 Time Step #: Date: Time: Basin 109 Runoff (m 3 /s) Basin 110 Runoff (m 3 /s) Basin 111 Runoff (m 3 /s) Basin 115 Runoff (m 3 /s) Basins 112 - 117 Runoff (m 3 /s) Chainage: 15829.00 16443.00 15850.00 20000.00 20248.00 River Station: 4822.09 4043.30 4577.87 525.69 336.56 101 4/16/1998 13:00 8.459 1.3503 5.287 12.668 7.297 102 4/16/1998 13:15 7.602 1.2038 4.676 11.425 6.862 103 4/16/1998 13:30 6.803 1.0705 4.129 10.276 6.48 104 4/16/1998 13:45 6.09 0.949 3.657 9.214 6.141 105 4/16/1998 14:00 5.444 0.8443 3.244 8.26 5.838 106 4/16/1998 14:15 4.864 0.7531 2.878 7.413 5.567 107 4/16/1998 14:30 4.36 0.6704 2.555 6.646 5.323 108 4/16/1998 14:45 3.914 0.598 2.269 5.976 5.102 109 4/16/1998 15:00 3.506 0.5333 2.018 5.382 4.9 110 4/16/1998 15:15 3.145 0.4756 1.792 4.837 4.715 111 4/16/1998 15:30 2.824 0.4247 1.591 4.351 4.545 112 4/16/1998 15:45 2.532 0.3787 1.413 3.919 4.39 113 4/16/1998 16:00 2.273 0.3379 1.253 3.524 4.245 114 4/16/1998 16:15 2.042 0.3011 1.112 3.169 4.111 115 4/16/1998 16:30 1.831 0.2681 0.988 2.853 3.984 116 4/16/1998 16:45 1.642 0.2395 0.877 2.568 3.865 117 4/16/1998 17:00 1.474 0.2136 0.779 2.308 3.752 118 4/16/1998 17:15 1.322 0.1902 0.697 2.077 3.644 119 4/16/1998 17:30 1.187 0.1699 0.627 1.883 3.543 120 4/16/1998 17:45 1.082 0.1551 0.584 1.727 3.477 121 4/16/1998 18:00 1.001 0.1449 0.561 1.608 3.476 122 4/16/1998 18:15 0.943 0.1393 0.557 1.522 3.545 123 4/16/1998 18:30 0.908 0.137 0.573 1.462 3.663 124 4/16/1998 18:45 0.891 0.1388 0.616 1.431 3.784 125 4/16/1998 19:00 0.891 0.1442 0.682 1.436 3.881 186 Appendix F: Data Dictionary Data Description Class Attribute Units 3dxsectsef Shape file of East Fork cross-sections for use in terrain model modification PolylineZ XYZ coordinates Meters 3dxsectsmc Shape file of Mill Creek cross-sections for use in terrain model modification PolylineZ XYZ coordinates Meters Bnd1 MIKE 11 boundary file depicting base flow conditions of study area .BND11 Time-series boundary conditions m 3 /s, Meters Bnd1PDC1 MIKE 11 boundary file depicting flow conditions of study area?s 25-yr storm event .BND11 Time-series boundary conditions m 3 /s, Meters Channelbds Shape file created from stream channel bounds for modifying terrain model Polygon XYZ coordinates Meters Crtin1 TIN of initial terrain model, without stream features TIN Elevation Meters Eastpdcreachpts Shape file of East Fork points extracted from Nwtin1, used to defined stream network Point XY coordinate Meters 187 Data Description Class Attribute Units Efclip Shape file of clipped East Fork cross- sections of the stream channel PolylineZ XYZ coordinates Meters Floodmap GIS project file for - terrain model modification .apr Gridpts Shape file of point elevations created from the Pdcgrid1 file, for integrating stream features into terrain model Point Elevation Meters HDPar1 MIKE 11 hydrodynamic parameter file of study area .HD11 Manning?s n values Hpoints.txt Shape file of MIKE 11 simulation results Point Time-series stage height Meters Mcclip Shape file of clipped Mill Creek cross- sections of the stream channel PolylineZ XYZ coordinates Meters Millpdcreachpts Shape file of Mill Creek points extracted from Nwtin1, used to defined stream network Point XY coordinate Meters MllCreek_CSO DSS file created from HEC HMS model .dss Runoff hydrographs m 3 /s Nwtin1 TIN of modified terrain model, with stream features TIN Elevation Meters 188 Data Description Class Attribute Units Pdc1 MIKE 11 simulation data created from flow model .MSD Time-series data m 3 /s, Meters Pdc1 MIKE 11 simulation file for study area?s 25-yr storm event .SIM11 pdc1hotstart MIKE 11 simulation file establishing the study area?s initial conditions .SIM11 pdc1model MIKE 11 network file of study area .NWK11 XY coordinates, Chainage Meters pdc2ftcontrs Shape file with 2-ft contour lines for the PDC study area Polyline Elevation Meters pdc5 RAS geometry file of study area .g01 pdc5 RAS GIS export file exported from RAS model into GIS .gis Time-series stage heights Meters pdc5 RAS plan file of study area .p01 pdc5 RAS project file of study area .prj pdc5 RAS unsteady flow file of study area .u01 Pdcbanks Shape file of GeoRAS stream banks Polyline XY coordinates Meters Pdcdem Grid of modified terrain model, with stream features 5-m Grid Elevation Meters 189 Data Description Class Attribute Units Pdcflowpath Shape file of GeoRAS stream and overbank flow paths Polyline XY coordinates, River Stationing Meters Pdcgrid1 Grid of initial terrain model, without stream features 5-m Grid Elevation Meters pdcinput1 GIS import file created by GeoRAS for HEC RAS .geo XYZ coordinates Meters PDCstream1 Shape file of GeoRAS stream centerline Polyline XY coordinates Meters PDCstream3D1 Shape file of GeoRAS stream centerline PolylineZ XYZ coordinates Meters pdctmpts Shape file of point elevations created from 30-m DEM, for developing initial terrain model Point Elevation Meters pdcXSec1 MIKE 11 cross- section file of study area using HEC-2 data .XNS11 XZ coordinates Meters Qpoints.txt Shape file of MIKE 11 simulation results Point Time-series flow m 3 /s rd3clip Shape file of study area road network Polyline XY coordinates Meters Stream1 Shape file of study area?s stream network, digitized from stream points Polyline XY coordinates Meters 190 Data Description Class Attribute Units Stream3def1 Shape file of East Fork stream and channel banks PolylineZ XYZ coordinates Meters Stream3dmc1 Shape file of Mill Creek stream and channel banks PolylineZ XYZ coordinates Meters theme1 Shape file used as boundary for study area Polygon XY coordinates Meters TS1EastUSQ MIKE 11 time- series file of East Fork upstream base flow .dfs0 Time-series flow m 3 /s TS1MillDShlev el MIKE 11 time- series file of Mill Creek downstream base stage .dfs0 Time-series stage height Meters TS1MillUSQ MIKE 11 time- series file of Mill Creek upstream base flow .dfs0 Time-series flow m 3 /s TS2Basin109Q MIKE 11 time- series file of Basin 109 runoff for 25-yr storm .dfs0 Time-series flow m 3 /s TS2Basin110Q MIKE 11 time- series file of Basin 110 runoff for 25-yr storm .dfs0 Time-series flow m 3 /s TS2Basin111Q MIKE 11 time- series file of Basin 111 runoff for 25-yr storm .dfs0 Time-series flow m 3 /s 191 Data Description Class Attribute Units TS2Basin112_1 17Q MIKE 11 time- series file of Basins 112 thru 117 (minus 115) for 25-yr storm .dfs0 Time-series flow m 3 /s TS2Basin115Q MIKE 11 time- series file of Basin 115 runoff for 25-yr storm .dfs0 Time-series flow m 3 /s TS2EastUSQ MIKE 11 time- series file of East Fork upstream flow for 25-yr storm .dfs0 Time-series flow m 3 /s TS2MillDShlev el MIKE 11 time- series file of Mill Creek downstream stage height for 25- yr storm .dfs0 Time-series stage height Meters TS2MillUSQ MIKE 11 time- series file of Mill Creek upstream flow for 25-yr storm .dfs0 Time-series flow m 3 /s Xscutlines Shape file of GeoRAS cross- section cut lines Polyline XY coordinates Meters Xscutlines3D1 Shape file of GeoRAS cross- section cut lines PolylineZ XYZ coordinates Meters 192 Bibliography (1) Andrysiak P.B., Visual Floodplain Modeling with Geographic Information Systems (GIS), Departmental Report, Department of Civil Engineering, University of Texas at Austin, Austin, Texas, December 2000. (2) Azagra-Camino E., Floodplain Visualization Using TINs, Departmental Report, Department of Civil Engineering, University of Texas at Austin, Austin, Texas, December 1999. (3) Barkau R.L., Mathematical Model of Unsteady Flow Through a Dendritic Network, Dissertation, Department of Civil Engineering, Colorado State University, Ft. Collins, Colorado, 1985. (4) Chow V.T., Maidment D.R., and Mays L.W, Applied Hydrology, MacGraw- Hill, Inc., New York, 1988. (5) Djokic D., Beavers M.A., and Deshakulakarni K., ARC/HEC2: An ARC/INFO ? HEC-2 Interface, Proceedings of the 21 st Annual Conference on Water Policy and Management, American Water Resources Association, ASCE, pp 41-44, May 1994. (6) Environmental Protection Agency (EPA), BASINS Internet Site, http://www.epa.gov/ost/basins/. (7) Evans T.A., GIS Data Exchange for the Hydrologic Engineering Center?s Hydraulic and Hydrologic Models, International Water Resources Engineering Conference Proceedings, ASCE, pp 786-789, August 1998. 193 (8) Fread D.L. and Jin M., Channel Routing with Flow Losses, Journal of Hydraulic Engineering, ASCE, vol 122, pp 580-582, 1996. (9) Fread D.L. and Jin M., Dynamic Flood Routing with Explicit and Implicit Numerical Solution Schemes, Journal of Hydraulic Engineering, ASCE, vol 123, pp 166-173, 1997. (10) HEC-GeoRAS: An extension for support of HEC-RAS using Arcview User?s Manual, Version 3.0, U.S. Army Corps of Engineers Hydrologic Engineering Center, Davis, California, April 2000. (11) HEC-HMS Hydrologic Modeling System User?s Manual, U.S. Army Corps of Engineers Hydrologic Engineering Center, Davis, California, 1998. (12) HEC-RAS River Analysis System User?s Manual, Version 2.2, U.S. Army Corps of Engineers Hydrologic Engineering Center, Davis, California, September 1998. (13) Kjelds J. T., Flood Plain Management, Integrating Flood Models with GIS, Danish Hydraulic Institute, 1998. (14) Kjelds J. T. and Jorgensen G. H., Flood Watch: GIS Based Management System for Flood Forecast Applications, Danish Hydraulic Institute, 1997. (15) Modeling Our World: The ESRI Guide to Geodatabase Design, Arcinfo 8.0, Environmental Systems Research Institute, Inc., California, 1999. (16) MIKE 11: A Modelling System for Rivers and Channels, Short Introduction Guide to Getting Started Tutorial, Danish Hydraulic Institute, Denmark, 1999. (17) MIKE 11 GIS: A Flood Modeling and Management Tool, Reference and User Manual, Danish Hydraulic Institute, Denmark, 1998. 194 (18) MIKE View: A Results Presentation Tool for MOUSE and MIKE 11, User Manual and Tutorial, Danish Hydraulic Institute, Denmark, 1998. (19) Project Study Plan: Mill Creek Ohio Flood Damage Reduction Project General Reevaluation Study, U.S. Army Corps of Engineers, Louisville District, Louisville, Kentucky, 1997. (20) Roberson J. A. and Crowe C. T., Engineering Fluid Mechanics, Houghton Mifflin Publishing, New York, 1985. (21) Tate E.C., Floodplain Mapping Using HEC-RAS and Arcview GIS, CRWR Online Report 99-1, Center for Research in Water Resources, Department of Civil Engineering, University of Texas at Austin, 1999. (22) Tate E.C., Photogrammetry Applications in Digital Terrain Modeling and Floodplain Mapping, Final Project Report for GRG 394: Research in Remote Sensing, University of Texas at Austin, December 1998. (23) UNET: One-Dimensional Unsteady Flow Through a Full Network of Open Channels User?s Manual, U.S. Army Corps of Engineers Hydrologic Engineering Center, Davis, California, 1997. (24) United States Geological Survey (USGS), Water Resources Internet Site, http://water.usgs.gov/. 195 Vita Daniel Baldwin Snead was born in Melbourne, Florida on April 15, 1968 the fourth child of six parented by William Archer Snead and Joan Mullin Snead. He received the Bachelor of Science degree in Mechanical Engineering from the Florida Institute of Technology, Melbourne, Florida in August 1990. Upon graduation, Daniel was commissioned as an engineer officer in the United States Army through the Reserve Officer Training Corps. Military schools that he has completed include the U.S. Army Airborne School, Engineer Officer Basic Course, U.S. Army Ranger School, Sapper Leaders Course, U. S. Army Jumpmaster School, Engineer Officer Advanced Course, and the Combined Arms Service and Staff School. His duty assignments include Platoon Leader and Company Executive Officer, 307 th Engineer Battalion, Fort Bragg, North Carolina; Protocol Officer, Eighth U.S. Army and U.S. Forces Korea, Yongsan, Korea; Assistant Battalion Operations Officer, 19 th Engineer Battalion, Fort Knox, Kentucky; and Company Commander, B Company, 10 th Engineer Battalion, Fort Stewart, Georgia. As a Company Commander, his company participated in Operations Intrinsic Action 98-03 and Desert Fox in Kuwait. In May 1999, he entered the Environmental and Water Resources Department of the University of Texas at Austin as a full-time graduate student. Daniel is married to the former Melinda Lee McCaslin, they have one daughter, Charlotte Katherine, and a basset hound named Chloe. Permanent Address: 477 Ironwood Drive Melbourne, Florida 32935 This report was typed by the author.